TIDMGWMO
RNS Number : 3009T
Great Western Mining Corp. plc
14 November 2023
GREAT WESTERN MINING CORPORATION PLC
("Great Western", "GWM" or the "Company")
MILL SITE PROGRESS
& 121 MINING INVESTMENT FORUM
Great Western Mining Corporation PLC (AIM - GWMO, Euronext
Growth - 8GW), which is exploring and developing gold, silver and
copper targets in Nevada, provides the following update on its
joint venture, Western Milling LLC (Western Milling), which is
currently constructing a process mill in Nevada for recovery of
precious metals from mining waste.
MILL SITE COMPLETION STATUS
Following delays outside the Company's control, including the
difficulties of securing concrete supplies in a remote location at
a reasonable price and a shortage of appropriately qualified
personnel available in the area resulting in a stop-go situation,
now resolved, together with unusually severe weather conditions in
2023, the mill project is nearing completion. Set out below is a
schedule of the progress on the main items.
-- Construction: Gravity terraces, ramps, access road, lay down
area and containment are complete. Base for rod mill
outstanding.
-- Process equipment: Hydrocyclones, spirals and shaker tables
are being installed by a finishing team. The Jaw crusher is waiting
on parts but timing is not critical as it will not be needed during
the start-up stage. The Rod Mill has been inspected but is
currently offsite. This 20-ton item will be brought to site in the
final stage pre-start up.
-- Safety Measures: Safety barriers complete and safety
procedures established and written up in a manual in accordance
with MSHA regulations.
-- Testing Laboratory: A near site laboratory for testing
materials has been established and is now operational, providing
for rapid analysis during processing without reliance on external
assay laboratories.
-- Utilities: A generator set-up will provide power for start of
operations. Three-phase power line to be extended to site from
nearby infrastructure at a second stage. Water rights are in the
process of being transferred and a well has now been drilled,
achieving flow capability several times in excess of requirements.
Four water monitoring wells have also been drilled for ongoing
verification that the water table is not affected by operations.
Water tanks have been installed.
-- Land Use: A formal Surface Use Lease Agreement has been
signed with the joint venture partner for use of the mill site at a
peppercorn rent and registered with the county authorities.
-- Containment: All steps considered necessary have been taken
to contain material within the site and prevent spillage in line
with regulatory requirements. Double and triple containment has
been constructed where applicable in anticipation of the second
phase of the project which will involve chemical leaching.
-- Trucking of Material: A 20 ton and a 40 ton truck, with
drivers, are on standby to bring raw material to site. Initially
these are being rented but once the operation is up and running and
the operating practicalities have been assessed, the joint venture
may exercise an option to purchase one or the other or both.
-- Engineering Sign-off: An independent consulting engineer has
been retained to inspect, verify and approve the project as-built
prior to production start-up.
PERMITTING STATUS
Once the project is ready to start operations, anticipated
before the end of the year, the timing of production start-up will
depend on securing two separate permits, application for both
having been made and the approvals of which are due and currently
awaited.
1. NDEP: Production start-up requires an environmental permit
from NDEP (The Nevada Department of Environmental Protection). An
application was filed at the beginning of this year and the Company
was advised that it would be processed within six months. Towards
the end of the six-month period, the joint venture was advised that
there would be a delay of a further 2-3 months due to staff
shortages and work overload. This further period has now
effectively elapsed and the Company has recently met with NDEP to
determine if there are any significant issues affecting the permit.
A response is awaited but the Company is not so far aware of any
outstanding issues beyond an administrative backlog within
NDEP.
2. BLM: A ground disturbance permit is required from the BLM
(the Federal Bureau of Land Management) to move mine waste from its
current locations to the mill site. This is a standard permit,
similar to those routinely granted for drilling operations. Again,
there appears to be an administrative backlog and, although no
problems are anticipated, material cannot be moved until the permit
has been issued.
JOINT VENTURE AGREEMENT
Final documentation between the joint venture partners,
including the Surface Use Lease Agreement and a Bill of Sale for
the inventory of equipment being provided by the joint venture
partner, has been signed and submission has been made to the State
of Nevada for formal registration of Great Western's 50%
shareholding in Western Milling LLC.
121 MINING INVESTMENT FORUM
Great Western is participating in The 121 Mining Investment
Forum in London on 20-21 November and the Company's presentation
will be published shortly before the event.
Great Western Chairman Brian Hall commented: "All the directors
of Great Western are shareholders in the Company and we share the
frustration expressed recently by a number of independent
shareholders over the delays that have arisen in completing this
project. However, it should be noted that the basic design has not
changed since inception and the concept remains sound with costs
under control. It should also be noted that, despite delays, the
project is likely to be achieved at a fraction of the cost of a
green field site using new plant and equipment, which was an
earlier option considered by the Company. The original and
continuing objective of the mill is to generate revenues for the
Company from easily accessible mine waste, for which an independent
resource has been commissioned, and we expect to achieve this in
the near future.
"While generation of first revenues will be an exciting
development for the Company which will support operations, I want
to point out that the main driver for Great Western's growth is not
the process mill but the enormous upside potential of our large
inventory of claims in the Walker Lane Belt of Nevada, which we are
working on fruitfully and moving to the next stage."
For further information:
Great Western Mining Corporation PLC
Brian Hall, Chairman +44 207 933 8780
Max Williams, Finance Director +44 207 933 8780
Davy (NOMAD, Euronext Growth Listing
Sponsor & Joint Broker)
Brian Garrahy +353 1 679 6363
SP Angel Corporate Finance LLP (Joint
Broker)
Ewan Leggat/Harry Davies-Ball +44 203 470 0470
Walbrook PR (PR advisers)
Nick Rome +44 207 933 8783
Notes to Editors
The Company has a large tract of acreage in Mineral County,
Nevada. The area consists of rugged, mountainous terrain, which
means that large parts of it remain under-explored. Mineral
potential is hosted by the regional Walker Lane Structural Belt,
the largest structural and metallogenic belt in Nevada, yet one of
the least explored in recent times, with gold, silver and copper
currently produced in Mineral County. Great Western has seven
distinct concession areas which offer the potential for exploiting
(1) short term gold and silver deposits and (2) long-term,
world-class copper deposits.
Six of the Company's properties are in the west of Mineral
County and are 100% owned and operated. The Company has an option
to acquire a seventh property, the Olympic Gold Project, in the
east of the county. Great Western's small exploration team is
supported by locally based consultants and contractors.
The state of Nevada is generally considered to be one of the
world's most mining friendly jurisdictions. While tightly regulated
and environmentally conscious, Nevada welcomes the mining industry.
Great Western takes care to ensure that its claims are maintained
in good standing and all regulations observed.
There are numerous gold and silver prospects on the Company's
acreage, including extensive historic mine workings which offer the
opportunity for secondary recovery. The Company is party to a 50-50
joint venture known as Western Milling LLC which is constructing a
mill to process pre-mined material for secondary recovery of gold
and silver.
Furthermore, through extensive drilling over a five-year period,
GWM has established a Mineral Resource on its first target area
known as M2, of 4.3 million tonnes at 0.45% copper, for 19,000
tonnes of contained copper metal. This resource has been
independently reported in accordance with JORC guidelines.
GWM has established an Inferred Resource Estimate of 31,000
tonnes grading 1.6 g/t gold and 3.0 g/t silver in tailings for the
OMCO Mine at the Olympic Gold Project. It has also established
Exploration targets. In addition, the Company has reported an
Exploration Target as follows:
-- 3,400 - 6,400 tonnes grading between 0.5 and 1.2 g/t Au and
1.2 and 2.1 g/t Ag in the substrate beneath the tailings volume at
the Olympic Mine.
-- 9,000 - 12,000 tonnes grading between 0.9 and 2.4 g/t Au and
2.0 and 5.1 g/t Ag in a coarse stockpile at Olympic Mine.
-- 4,200 - 7,700 tonnes grading between 40 and 140 g/t Ag and
0.3 and 0.3 g/t Au in spoil heaps at Mineral Jackpot.
, the news service of the London Stock Exchange. RNS is approved by
the Financial Conduct Authority to act as a Primary Information
Provider in the United Kingdom. Terms and conditions relating to
the use and distribution of this information may apply. For further
information, please contact rns@lseg.com or visit www.rns.com.
RNS may use your IP address to confirm compliance with the terms
and conditions, to analyse how you engage with the information
contained in this communication, and to share such analysis on an
anonymised basis with others as part of our commercial services.
For further information about how RNS and the London Stock Exchange
use the personal data you provide us, please see our Privacy
Policy.
END
MSCGPGCAGUPWGRW
(END) Dow Jones Newswires
November 14, 2023 02:00 ET (07:00 GMT)
Great Western Mining (AQSE:GWMO.GB)
Historical Stock Chart
Von Nov 2024 bis Dez 2024
Great Western Mining (AQSE:GWMO.GB)
Historical Stock Chart
Von Dez 2023 bis Dez 2024