Orezone Gold Corporation (TSX: ORE, OTCQX: ORZCF)
(“Orezone” or “Company”) reported its operational and financial
results for the three months ended March 31, 2023. The consolidated
financial statements and Management’s Discussion and Analysis are
available at www.orezone.com and on the Company’s profile on SEDAR
at www.sedar.com. The Company will host a conference call and
webcast on May 10, 2023 commencing at 8:00am PDT to discuss the
Company’s first quarter results. Additional details are provided at
the end of this press release.
Patrick Downey, President and CEO, commented
“Earnings from mine operations exceeded $39 million in Bomboré’s
first full quarter of commercial production and have provided a
strong start to the Company’s net earnings and free cash flow for
2023. Gold production of 41,301 oz was helped by excellent
performance of the process plant with mill throughput at 13% above
design and recoveries at a steady 92.2%. Our operational efficiency
and stringent cost management assisted in offsetting cost pressures
from a stronger local currency and high in-country diesel prices.
With robust gold prices, AISC margin was $966 per oz sold or an
impressive 51%.
Our safety record continues to be exemplary with
no lost time injuries for the quarter from 928,000 hours worked and
an LTIFR of zero since 2021 when construction of the Phase I Oxide
plant commenced.
On the growth front, work on our grid power
connection is advancing at a steady rate with the awards of all
major installation contracts and order placements for
schedule-critical equipment. Significant savings from current
on-site power generation will be realized once the connection is
energized, expected in Q4-2023. Lastly, work on the Bomboré Phase
II Expansion study update remains on track for completion by the
end of this third quarter.”
FIRST QUARTER 2023
HIGHLIGHTS
Operational
- Produced 41,301 gold oz
- Sold 43,139 gold oz at an average
realized price of $1,892 per oz
- AISC¹ of $926 per gold oz
sold
- Zero lost-time injuries with
928,000 personnel hours worked
Financial
- Revenue of $81.7 million
- Earnings from mine operations of
$39.7 million
- Net income and net income per share
(basic) attributable to Orezone shareholders of $22.6 million and
$0.07, respectively
- Adjusted earnings¹ and
adjusted earnings per share¹ (basic) attributable to Orezone
shareholders of $24.6 million and $0.07, respectively
- Cash flow from operations before
changes in non-cash working capital of $41.1 million ($38.9 million
after changes in non-cash working capital)
- Free cash flow¹ of $31.5
million
- Cash of $45.2 million at March 31,
2023
Corporate
- Rob Henderson appointed as VP
Technical Services and Kevin MacKenzie appointed as VP Corporate
Development and Investor Relations on January 5, 2023
- Non-brokered private placement of
13.0 million common shares at C$1.27 per share arranged with a
large, well-established, global institutional fund manager and
closed on March 8, 2023, resulting in net proceeds of $11.6
million
¹ Non-IFRS measures. See “Non-IFRS Measures”
section below for additional details.
PRODUCTION AND FINANCIAL
SUMMARY
(All mine site figures are on a 100% basis) |
|
Q1-2023 |
Q4-2022 |
Operating Performance |
|
|
|
Gold production |
oz |
41,301 |
22,258 |
Gold sales |
oz |
43,139 |
24,676 |
Average realized gold price |
$/oz |
1,892 |
1,760 |
Cash costs¹ per gold ounce sold |
$/oz |
799 |
973 |
All-in sustaining costs¹ (“AISC”) per gold ounce
sold |
$/oz |
926 |
1,075 |
Financial Performance |
|
|
|
Revenue |
$000s |
81,712 |
43,431 |
Earnings from mine operations |
$000s |
39,670 |
16,660 |
Net income attributable to shareholders of Orezone |
$000s |
22,560 |
3,763 |
Net income per common share attributable to shareholders
of Orezone: Basic Diluted |
$$ |
0.07 0.06 |
0.01 0.01 |
Adjusted EBITDA¹ |
$000s |
42,645 |
15,725 |
Adjusted earnings¹ attributable to shareholders of
Orezone |
$000s |
24,574 |
9,903 |
Adjusted earnings per share¹ attributable to
shareholders of Orezone |
$ |
0.07 |
0.03 |
Cash and Cash Flow Data |
|
|
|
Operating cash flow before changes in working capital |
$000s |
41,137 |
15,400 |
Operating cash flow |
$000s |
38,926 |
23,235 |
Free cash flow¹ |
$000s |
31,498 |
8,942 |
Cash |
$000s |
45,172 |
9,158 |
¹ Non-IFRS measures. See “Non-IFRS Measures”
section below for additional information.
BOMBORÉ GOLD MINE (100% BASIS) –
OPERATING HIGHLIGHTS
|
|
Q1-2023 |
Q4-2022² |
Safety |
|
|
|
Lost-time injuries frequency rate (LTIFR) |
per 1M hours |
0.00 |
0.00 |
Personnel-hours worked |
000s hours |
928 |
958 |
Mining Physicals |
|
|
|
Ore tonnes mined |
tonnes |
2,205,056 |
1,526,949 |
Waste tonnes mined |
tonnes |
2,382,135 |
3,087,950 |
Total tonnes mined |
tonnes |
4,587,191 |
4,614,899 |
Strip ratio |
waste:ore |
1.1 |
2.0 |
Processing Physicals |
|
|
|
Ore tonnes milled |
tonnes |
1,445,693 |
806,875 |
Head grade milled |
Au g/t |
0.96 |
0.93 |
Recovery rate |
% |
92.2 |
91.9 |
Gold produced |
oz |
41,301 |
22,258 |
Unit Cash Cost¹ |
|
|
|
Mining cost per tonne |
$/tonne |
2.91 |
2.57 |
Mining cost per ore tonne processed |
$/tonne |
6.51 |
6.58 |
Processing cost |
$/tonne |
9.21 |
12.47 |
Site general and admin (“G&A”) cost |
$/tonne |
3.23 |
4.87 |
Cash cost per ore tonne processed |
$/tonne |
18.96 |
23.92 |
Cash Costs and AISC Details |
|
|
|
Mining cost (net of stockpile movements) |
$000s |
9,417 |
5,306 |
Processing cost |
$000s |
13,322 |
10,062 |
Site general and admin cost |
$000s |
4,667 |
3,928 |
Refining and transport cost |
$000s |
148 |
92 |
Government royalty cost |
$000s |
4,912 |
2,608 |
Gold inventory movements |
$000s |
2,019 |
2,010 |
Cash costs³ on a sales
basis |
$000s |
34,485 |
24,006 |
Sustaining capital |
$000s |
3,530 |
1,550 |
Sustaining leases |
$000s |
187 |
- |
Corporate general and admin cost |
$000s |
1,731 |
959 |
All-In Sustaining Costs³ on a
sales basis |
$000s |
39,933 |
26,515 |
Gold sold |
oz |
43,139 |
24,676 |
Cash costs per gold ounce sold³ |
$/oz |
799 |
973 |
All-In Sustaining Costs per gold ounce sold³ |
$/oz |
926 |
1,075 |
¹ The Bomboré Mine entered into commercial
production on December 1, 2022. Unit cash costs during
pre-commercial production are not representative of cost
performance expected under steady-state operations. Cost figures
presented for Q4-2022 include a blend of costs before and during
commercial production.² The Bombore Mine did not process any
significant quantity of ore for the month of October 2022 due to
insufficient power as the power plant underwent repairs. As a
result, departmental costs for processing and site general and
admin have been excluded from the cash cost and AISC figures
presented for Q4-2022. These costs have been capitalized as
commissioning costs.³ Non-IFRS measure. See “Non-IFRS Measures”
section below for additional details.
Commissioning of the process plant with ore
commenced in late August 2022, resulting in the pouring of first
gold on September 10, 2022 but commissioning was interrupted in
late September 2022 when one of the two working permanent gensets
experienced a major failure. As a consequence, mill operations were
stopped in October 2022 and only recommenced in November 2022 when
replacement rental gensets were mobilized, installed, and put into
service. With full and reliable power, the process plant quickly
ramped-up daily mill tonnages which led to Bomboré declaring
commercial production on December 1, 2022.
Bomboré Production Results
Gold production in Q1-2023 was 41,301 oz, an
increase of 86% from the 22,258 oz produced in Q4-2022. The higher
gold production is attributable to a 79% jump in plant throughput
combined with slight increases in ore grades and plant recoveries.
The process plant performed exceptionally well in Q1-2023 with
throughput averaging 16,063 tonnes per day which exceeded nameplate
by approximately 13% while process recoveries were consistent with
design levels. Favourable ore characteristics and high levels of
plant availability and utilization led to a strong quarterly
performance. Scheduled maintenance was conducted during the quarter
with major mill shutdowns for mill re-line and scheduled
change-outs of wear parts planned for in later quarters of the
year.
Bomboré Operating Costs
AISC per gold ounce sold in Q1-2023 was $926, a
decrease of 14% from the AISC per gold ounce sold of $1,075 in
Q4-2022. The lower AISC was driven mainly by improved performance
in unit costs and a 3% increase in ore grades milled. Cash cost per
ore tonne processed covering mining, processing and site G&A
declined by 21% or $4.96 from $23.92 in Q4-2022 to $18.96 in
Q1-2023 as a result of the higher mill throughput and the
corresponding decrease in fixed unit costs. In addition, processing
costs benefitted from the optimized consumption of major reagents
through enhancements in operator controls and a better
understanding of field operating conditions. However, cost of power
generation remains elevated and above budget due to persistently
high in-country diesel prices set by the Burkina Faso government.
The Company had expected a moderation in diesel prices starting in
2023 to reflect falling global oil prices in H2-2022 but decreases
in diesel prices have not yet materialized. This high diesel cost
also had a negative effect on unit mining costs.
Bomboré Growth Capital
Projects
Grid Power Connection
The project to connect Bomboré to Burkina Faso’s
national grid is progressing well and remains on schedule for
completion before the end of the 2023 year. The Company has engaged
ECG Engineering Pty Ltd. (“ECG”) to manage the design,
construction, and commissioning of the new high voltage
transmission line and dedicated substations, and will work closely
with SONABEL, Burkina Faso’s state-owned electricity company, to
ensure timely deliverables and adherence to schedule. ECG is a
specialized engineering firm that has successfully delivered on
similar projects in West Africa, including Burkina Faso.
To-date, all long lead equipment orders have
been placed and all major contracts have been awarded. Land
compensation for the transmission line corridor has commenced under
the direction of SONABEL and work to clear this ground corridor
will follow shortly upon the mobilization of contractor equipment
and personnel. Drawings and designs for the powerline and
substations have been submitted to SONABEL and are pending their
final review and approval.
RAP Phases II and III
RAP Phases II and III involve the construction
of four new resettlement villages (MV3, MV2, BV2, and BV1). The
Company has sequenced MV3 as the first village to construct in
order to gain access to mining areas that are currently
contemplated in the 2024 mine plan. MV3 is the largest of the
resettlement villages and requires the new erection of over 1,200
private homes and public structures.
The start of construction for the MV3 village
encountered a slight delay in the first two months of 2023 as
communities conducted sacred ceremonies for the new resettlement
grounds. Earthwork for MV3 is now complete and contractors have
commenced the mobilization of personnel, materials, and equipment
to site.
RAP compensation for displaced households is
organized to begin in Q2-2023.
2023 Feasibility Study Update for the
Phase II Expansion (“2023 FS”)
The 2019 feasibility study (“2019 FS”)
contemplated the construction of a 2.2M tonnes per annum (“tpa”)
hard rock facility which would commence production in the third
year of oxide operations. Based on the mineral reserves outlined in
this 2019 FS, the overall plant capacity was to remain at a nominal
5.2Mtpa, comprising of 3.0Mtpa of oxides and 2.2Mtpa of hard rock,
resulting in an average gold production profile of 134,000 oz per
year for the first ten years of commercial operations.
Subsequent to the 2019 FS, over 100,000 metres
of drilling have been completed leading to the discovery of the
near surface P17NE deposit and extensions of other known higher
grade hard rock zones with the main Bomboré deposit. Results of
drilling undertaken in 2022 are expected to successfully convert
Inferred resources of higher grade hard rock material into the
Measured and Indicated categories. The updated resource modelling
is progressing and a new resource, reserve, and mine plan are
targeted for completion in Q3-2023.
Metallurgical test work is also nearing
completion which confirms more rapid leach kinetics and a resultant
significant decrease in required leach time from the 42 hours shown
in the 2019 FS to the estimated 24 hours to be used in plant design
for the 2023 FS. The Company expects the new hard rock expansion
will be sized as a 4.4Mtpa standalone circuit to operate
independently to the existing 5.7Mtpa oxide circuit, a notable
increase to the 5.2Mtpa combined circuit in the 2019 FS. The
Company has chosen to expand the circuit size as it believes recent
drilling successes have demonstrated that the Bomboré mine is
capable of supporting a larger annual operation. The Bomboré
deposit remains open to further extensions and potential new
discoveries from future drilling.
For the 2023 FS, the Company has engaged the
same consultants (Lycopodium and Knight Piésold) that completed the
development and construction of the current Phase I operations to
ensure continuity and consistency. Flowsheet development is
complete, and equipment and capital costs are well advanced. Of
note is that the carbon-in-leach and elution circuits will be
copies of those in current operations.
The Company has held early discussions with its
senior lender, Coris Bank, about their participation in this future
Phase II Expansion. Coris Bank has indicated they are supportive of
this expansion and look forward to furthering discussions as the
Company draws closer to completing its 2023 FS.
NON-IFRS MEASURES
The Company has included certain terms or
performance measures commonly used in the mining industry that is
not defined under IFRS, including “cash costs”, “AISC”, “EBITDA”,
“adjusted EBITDA”, “adjusted earnings”, “adjusted earnings per
share”, and “free cash flow”. Non-IFRS measures do not have any
standardized meaning prescribed under IFRS, and therefore they may
not be comparable to similar measures presented by other companies.
The Company uses such measures to provide additional information
and they should not be considered in isolation or as a substitute
for measures of performance prepared in accordance with IFRS. For a
complete description of how the Company calculates such measures
and reconciliation of certain measures to IFRS terms, refer to
“Non-IFRS Measures” in the Management’s Discussion and Analysis for
the three months ended March 31, 2023 which is incorporated by
reference herein.
CONFERENCE CALL AND WEBCAST
Orezone will host a conference call and audio
webcast to discuss first quarter 2023 results on Wednesday, May 10,
2023 at 8:00am PDT (11:00am EDT).
WebcastDate: Wednesday, May 10,
2023Time: 8:00 am Pacific Time (11:00 am Eastern time)Please
register for the webcast here: Orezone Q1-2023 Conference Call and
Webcast
Conference CallToll-free in
U.S. and Canada: 1-800- 715-9871International callers:
+646-307-1963Event ID: 8574266
QUALIFIED PERSONS
The scientific and technical information in this
news release was reviewed and approved by Dr. Pascal Marquis, Geo.,
Senior Vice President of Exploration, Mr. Rob Henderson, P. Eng,
Vice President of Technical Services, and Mr. Patrick Downey,
P.Eng. President and CEO, all of whom are Qualified Persons as
defined under NI 43-101 Standards of Disclosure for Mineral
Projects.
About Orezone Gold
Corporation
Orezone Gold Corporation (TSX: ORE OTCQX: ORZCF)
is a Canadian mining company operating the open pit Bomboré Gold
Mine in Burkina Faso.
Orezone is focusing on mining and processing the
Phase I near surface free-dig oxides at a planned annual
throughput of 5.7 million tonnes. The Company believes that Bomboré
has a significant underlying sulphide resource to
support a substantially larger Phase II expansion. The Company
has recently completed a resource definition drill program, and
plans to issue an updated mineral resource, reserve and life of
mine plan, as part of this Phase II expansion. It is expected
that the pending study will be completed in Q3-2023 to be
followed by a production decision.
Orezone is led by an experienced team focused on
social responsibility and sustainability with a proven track record
in project construction and operations, financings, capital markets
and M&A.
The technical report for the 2019 Feasibility
Study on the Bomboré Project entitled NI 43-101 Technical Report
(Amended) Feasibility Study of the Bomboré Gold Project is
available on SEDAR under the Company’s profile at
www.sedar.com.
Patrick DowneyPresident and Chief Executive
Officer
Vanessa PickeringManager, Investor Relations
Tel: 1 778 945 8977 / Toll Free: 1 888 673
0663info@orezone.com / www.orezone.com
For further information please contact
Orezone at +1 (778) 945-8977 or visit the Company’s
website at
www.orezone.com.
The Toronto Stock Exchange neither approves nor
disapproves the information contained in this news release.
Cautionary Note Regarding
Forward-Looking Statements
This press release contains certain information
that constitutes “forward-looking information” within the meaning
of applicable Canadian Securities laws and “forward-looking
statements” within the meaning of applicable U.S. securities laws
(together, “forward-looking statements”). Forward-looking
statements are frequently characterized by words such as “plan”,
“expect”, “project”, “intend”, “believe”, “anticipate”, “estimate”,
“potential”, “possible” and other similar words, or statements that
certain events or conditions “may”, “will”, “could”, or “should”
occur. Forward-looking statements in this press release include,
but are not limited to, statements with respect to the Bomboré
Growth Capital Projects and the 2023 Feasibility Study Update for
the Phase II Expansion.
All forward-looking statements are subject to a
variety of risks and uncertainties and other factors that could
cause actual events or results to differ materially from those
projected in the forward-looking statements including, but not
limited to, terrorist or other violent attacks, the failure of
parties to contracts to honour contractual commitments, unexpected
changes in laws, rules or regulations, or their enforcement by
applicable authorities; social or labour unrest; changes in
commodity prices; unexpected failure or inadequacy of
infrastructure, the possibility of project cost overruns or
unanticipated costs and expenses, accidents and equipment
breakdowns, political risk, unanticipated changes in key management
personnel, the spread of diseases, epidemics and pandemics
diseases, market or business conditions, the failure of exploration
programs, including drilling programs, to deliver anticipated
results and the failure of ongoing and uncertainties relating to
the availability and costs of financing needed in the future, and
other factors described in the Company's most recent annual
information form and management’s discussion and analysis filed on
SEDAR on www.sedar.com. Readers are cautioned not to place
undue reliance on forward-looking statements.
Forward-looking statements are based on the
applicable assumptions and factors management considers reasonable
as of the date hereof, based on the information available to
management at such time. These assumptions and factors include, but
are not limited to, assumptions and factors related to the
Company’s ability to carry on current and future operations,
including: development and exploration activities; the timing,
extent, duration and economic viability of such operations,
including any mineral resources or reserves identified thereby; the
accuracy and reliability of estimates, projections, forecasts,
studies and assessments; the Company’s ability to meet or achieve
estimates, projections and forecasts; the availability and cost of
inputs; the price and market for outputs, including gold; foreign
exchange rates; taxation levels; the timely receipt of necessary
approvals or permits; the ability to meet current and future
obligations; the ability to obtain timely financing on reasonable
terms when required; the current and future social, economic and
political conditions; and other assumptions and factors generally
associated with the mining industry.
Although the forward-looking statements
contained in this press release are based upon what management of
the Company believes are reasonable assumptions, the Company cannot
assure investors that actual results will be consistent with these
forward-looking statements. These forward-looking statements are
made as of the date of this press release and are expressly
qualified in their entirety by this cautionary statement. Subject
to applicable securities laws, the Company does not assume any
obligation to update or revise the forward-looking statements
contained herein to reflect events or circumstances occurring after
the date of this press release.
Orezone Gold (TSX:ORE)
Historical Stock Chart
Von Dez 2024 bis Jan 2025
Orezone Gold (TSX:ORE)
Historical Stock Chart
Von Jan 2024 bis Jan 2025