Alba
Mineral Resources Plc / EPIC: ALBA / Market: AIM / Sector:
Mining
26 June 2024
Alba Mineral Resources
Plc
("Alba"
or the "Company")
Operational
Update
Alba Mineral Resources Plc (AIM:
ALBA) is pleased to report on the progress of ongoing works at the
Company's 100% owned Clogau-St David's Gold Mine in north Wales
("Clogau" or the "Mine"). The Company also reports on other
operational and project-related matters.
Key
Points
Clogau-St David's Gold Mine
· Waste
Tip: all fines from Trenches 1 and 3 have now been processed at the
Company's onsite processing plant. A total of 35 kg of concentrates
have been produced in the current programme to date.
· Underground Operations
o 100m
of cabling is being installed and a new pump lowered to No.4 Level
to enable completion of dewatering of No.5 Level leading to
development of that level.
o Alba's underground works contractor is back on site to
complete safety and access works on No.4 Level and, post
dewatering, No.5 Level.
o A
mining contractor has been selected.
Dolgellau Gold Exploration Project
· Completion of interpretation of surveys over Hafod Owen and
Castell Carndochan.
Andover West Lithium Option
· The
Option Period in respect of the Andover West project has expired,
however discussions are ongoing with the vendors.
Horse Hill Project
· The
Company notes the announcement by the Operator regarding the
Supreme Court's recent adverse decision in relation to the Horse
Hill planning permission.
George Frangeskides, Executive Chairman,
commented:
"I
am pleased to report that we have now entered the main phase of
pre-blasting operations at our primary gold target in the Lower
Llechfraith workings at Clogau. We look forward to providing
further updates as the work plan unfolds."
Details
Clogau: Waste Tip Processing and Refining
All of the collected fines from
Trenches 1 & 3 have now been processed at the Company's onsite
pilot processing plant and a total of 35 kg of concentrate
produced.
Clogau: Underground Bulk Sampling of the Llechfraith
Target
The status of ongoing preparations
for the underground bulk sampling of the Company's primary gold
target within the Mine, the Llechfraith Target, is as
follows:
- 100m of cabling
is presently being installed and a new pump has been lowered to
No.4 Level to enable completion of the dewatering of No.5 Level.
The new pump is a sludge pump with a high head capability
allowing for a single lift to the clarifier tank in the Llechfraith
mine yard before its discharge into the nearby watercourse pursuant
to existing permissions.
- Alba's
underground works contractors are currently on site to complete a
further round of safety and access works on No.4 Level and, post
dewatering of No.5 Level, to install ladderways to enable the team
to access No.5 Level for blasting. Once No.5 Level is accessible,
Alba and its contractors will survey No.5 Level for any safety
works required prior to blasting.
- Ventilation, in
the form of fans and vent ducting, will be installed on Levels 4
and 5 for the removal of blasting
fumes.
- Compressed air
will be extended to No.4 Level by the installation of about 40m of
pipes linking to the existing air pipes located on No. 2
Level. Similarly, water pipes will be extended down to No.4
Level. Once No.5 Level has been dewatered, this will enable both
air and water to be connected from 4 to 5 Level by means of
flexible hoses.
- A 5-tonne
capacity winch is to be installed at the top of the Llechfraith
Shaft with another one on No.4 Level, together with shaft doors and
signalling devices.
- A mining
contractor has been selected for the underground programme.
The blasting phase is expected to take a total of around 2-3
months. Blasting will be performed according to the following
sequence: drilling blast holes and loading them with explosives;
detonating the blast, followed by ventilation to remove blast
fumes; removal of the blasted rock (mucking out); and winching of
the blasted rock to surface for sorting, storing and processing.
Each sequence of blasting is expected to allow the development to
advance by just over 1 metre per blast.
In a revision to the previously
published timeline, the current indicative timeline for the
underground bulk sampling exercise is as follows:
a. Site mobilisation and
preparation: June/July.
b. Blasting, ore removal and
sorting: July to September.
c. Processing ore to gold
concentrate and then refining & smelting: TBA.
Regarding the last point above, the
blasting programme is expected to result in the collection of a
bulk sample of ~300 tonnes. As such, the Company is in the process
of considering the most efficient approach to the processing of
that amount of ore, which is expected to require an upgrade to the
capacity of the Company's existing onsite pilot plant. Further
information about this will be released in due course.
Figure 1: (left) personnel
from Alba's underground works contractor inspecting Llechfraith
Shaft; (right) new sludge pump being lowered to No.4
Level
Figure 2: Proposed bulk
sampling works from No.5 Level of the Lower Llechfraith workings,
involving the development of two inclined raises (in red) between
Nos. 4 and 5 Levels. The development is designed to cross the
extension of an interpreted pay shoot which was intersected in the
levels above.
Dolgellau Gold Exploration Project
The interpretation of the recent
aerial magnetic survey over Clogau, Hafod Owen and Castell
Carndochan has been completed by the specialist geophysicist
contracted by the Company. The contents of the report are under
review by the Alba technical team. A field exploration programme,
building on the new and/or refined targets identified by this
airborne programme, is being developed and will be announced in due
course.
Andover West Lithium Project
Further to the announcement on 31
May 2024 that the Company had agreed with the vendors to an
extension of the option for Alba to acquire an initial 50% interest
in the lithium rights over the Andover West Lithium Project in the
West Pilbara, Western Australia, the option period has now expired
without Alba having given notice to exercise the option.
However, the Company remains in discussion with the vendors of the
project in respect of a possible transaction in relation to Andover
West.
Horse Hill Project
The Company notes the recent
announcement by UK Oil & Gas Plc ("UKOG"), the Operator of the
Horse Hill Oil Project in which Alba owns an 11.765% effective
interest. In its announcement of 20 June, UKOG noted the
Supreme Court's decision of the same date that in its 2019 grant of
planning consent for the oil production at Horse Hill, Surrey
County Council ("SCC") did not request and consider in their
assessment an estimate of the end-use carbon combustion emissions
of produced hydrocarbons. UKOG further stated that "the ruling now retrospectively requires that
the end-use combustion emissions must be included in the
development's Environmental Impact Assessment ("EIA") and assessed
as part of the grant of planning consent for the
development….Consequently, the Company now plans to work closely
with SCC to promptly rectify the situation, either via an amendment
to the original 2018 planning application's EIA or via a new
retrospective planning submission, for which there is recent
planning precedent within Surrey."
Alba awaits the advice of the
Operator as to the next steps and timetable for rectification of
the relevant planning consents.
This announcement contains
inside information for the purposes of the UK Market Abuse
Regulation and the Directors of the Company are responsible for the
release of this announcement.
Forward Looking
Statements
This announcement contains
forward-looking statements relating to expected or anticipated
future events and anticipated results that are forward-looking in
nature and, as a result, are subject to certain risks and
uncertainties, such as general economic, market and business
conditions, competition for and availability of qualified staff and
contractors, regulatory processes and actions, technical issues,
new legislation, uncertainties resulting from potential delays or
changes in plans, uncertainties resulting from working in a new
political jurisdiction, uncertainties regarding the results of
exploration, uncertainties regarding the timing and granting of
prospecting rights, uncertainties regarding the timing and granting
of regulatory and other third party consents and approvals,
uncertainties regarding the Company's or any third party's ability
to execute and implement future plans, and the occurrence of
unexpected events. Actual results achieved may vary from the
information provided herein as a result of numerous known and
unknown risks and uncertainties and other factors.
**ENDS**
For further information, please
visit www.albamineralresources.com or
contact:
Alba Mineral Resources
plc
George Frangeskides, Executive
Chairman
|
+44 20
3950 0725
|
SPARK Advisory Partners Limited
(Nomad)
Andrew Emmott
|
+44 20
3368 3555
|
CMC Markets plc (Broker)
Thomas Smith / Douglas
Crippen
|
+44 20
3003 8632
|
Alba's
Projects & Investments
|
Projects Operated by Alba
|
Location
|
Ownership
|
Clogau (gold)
|
Wales
|
100%
|
Dolgellau Gold Exploration
(gold)
|
Wales
|
100%
|
Gwynfynydd (gold)
|
Wales
|
100%
|
Investments Held by Alba
|
Location
|
Ownership
|
GreenRoc Mining Plc
(mining)
|
Greenland
|
34.72%
|
Horse Hill (oil)
|
England
|
11.765%
|