ENDEAVOUR REPORTS THAT WET COMMISSIONING IS UNDERWAY AT ITS ITY CIL PROJECT
20 Februar 2019 - 11:47AM
ENDEAVOUR REPORTS THAT WET COMMISSIONING IS UNDERWAY AT ITS
ITY CIL PROJECT
View News Release in PDF
HIGHLIGHTS
- Over 8 million man-hours have been worked without a lost
time injury
- Construction is on-budget & two months ahead of schedule
with first gold pour expected in early Q2-2019
- Dry commissioning has been completed and wet commissioning
has commenced; demobilization of the construction team has also
commenced
- Ity is expected to produce 160 - 200koz in 2019 at an AISC
of $525 - 590/oz, with the bottom-end of production guidance
corresponding to the nameplate capacity
- Aggressive exploration program underway with seven drill
rigs active on the La Plaque target with the aim of publishing an
updated resource in Q2-2019
Abidjan, February 20, 2019 - Endeavour
Mining Corporation (TSX:EDV)(OTCQX:EDVMF) ("Endeavour") is pleased
to announce that excellent progress continues to be made at its Ity
CIL project in Côte d'Ivoire, as wet commissioning has commenced.
Construction is progressing on-budget with over 97% of the total
project complete and the first gold pour expected to occur two
months ahead of schedule in early Q2-2019.
Sébastien de Montessus, President & CEO,
stated: "We are proud of the key milestones achieved in recent
months as the project construction has been significantly
de-risked. We are excited to have commenced the commissioning phase
several months ahead of the initial schedule and look forward to
the first gold pour in early Q2-2019.
The start of production at Ity will be a
transformative moment for Endeavour. It will become, alongside
Houndé, our second flagship mine, and marks the end of several
years of large capital-intensive projects which will allow us to
focus on cash flow generation and generating returns on our capital
employed.
With seven drill rigs currently operating in the
Le Plaque area, we expect our additional exploration activity to
further demonstrate the potential of Ity."
Key milestones achieved to date include:
- Over 8 million man-hours have been worked without a lost time
injury.
- Overall project completion stands at more than 97%, tracking
approximately two months ahead of schedule.
- The project remains on-budget with the remaining cash outflow
for 2019 amounting to $50 - $60 million.
- Wet commissioning has commenced and, in preparation for
production, ore is expected to be introduced into the process plant
milling circuit in the coming days.
Image 1: Process Plant - Wet Plant
- The dry plant has been successfully commissioned.
Image 2 : Process Plant - Dry Plant
Image 3 : Site Aerial View
- The tailings storage facility construction is complete.
Image 4: Tailings Storage Facility
- The 11kV switch room and 11kV overhead power line have been
commissioned, the 90kV transmission line construction is nearly
complete, and the back-up power station has been commissioned.
Image 5 : Switchyard and Power Station
- The Daapleu haul bridge construction and river diversion have
been completed.
Image 6: Haul Bridge
- The resettlement of Daapleu is complete and the official
ceremony of handing over the houses took place on December 10,
2018.
Image 7: Village Resettlement
- Construction of the 312-room permanent employee camp, messing,
and staff recreation facilities are complete.
Image 8: Employee Permanent Camp
- Pre-stripping commenced at the Bakatouo and Ity Flat deposits
in late 2018.
Image 9: Mining Activity
- Demobilization of construction personnel has begun following
the completion of key construction milestones, and operating teams
are in place with training programs well underway.
- Ity is expected to produce 160 - 200koz in 2019 at an AISC of
$525 - 590/oz, with the bottom-end production guidance
corresponding to the nameplate capacity while the top-end factors
possible upsides such as an earlier start date, a quicker than
expected ramp-up and the plant producing above its nameplate.
- An aggressive exploration program is underway, with seven drill
rigs active on the La Plaque target with the aim of publishing an
updated resource in Q2-2019. For 2019, a total of 70,000-meters are
planned to be drilled in the Le Plaque area and on other nearby
targets.
QUALIFIED PERSONS
Jeremy Langford, Endeavour's Chief Operating
Officer - Fellow of the Australasian Institute of Mining and
Metallurgy - FAusIMM, is a Qualified Person under NI 43-101, and
has reviewed and approved the technical information in this news
release.
CONTACT INFORMATION
Martino De Ciccio VP - Strategy & Investor Relations +44
203 640 8665 mdeciccio@endeavourmining.com |
Brunswick Group LLP in London Carole Cable, Partner +44 7974
982 458 ccable@brunswickgroup.com |
ABOUT ENDEAVOUR MINING CORPORATION
Endeavour Mining is a TSX listed intermediate
African gold producer with a solid track record of operational
excellence, project development and exploration in the highly
prospective Birimian greenstone belt in West Africa. Endeavour is
focused on offering both near-term and long-term growth
opportunities with its project pipeline and its exploration
strategy, while generating immediate cash flow from its
operations.
Endeavour operates 4 mines across Côte d'Ivoire
(Agbaou and Ity) and Burkina Faso (Houndé, Karma) which are
expected to produce 615-695koz in 2019 at an AISC of
$760-810/oz.
For more information, please visit
www.endeavourmining.com.
CAUTIONARY STATEMENT ON FORWARD-LOOKING
INFORMATION
This news release contains "forward-looking
statements" including but not limited to, statements with respect
to Endeavour's plans and operating performance, the estimation of
mineral reserves and resources, the timing and amount of estimated
future production, costs of future production, future capital
expenditures, and the success of exploration activities. Generally,
these forward-looking statements can be identified by the use of
forward-looking terminology such as "expects", "expected",
"budgeted", "forecasts", and "anticipates". Forward-looking
statements, while based on management's best estimates and
assumptions, are subject to risks and uncertainties that may cause
actual results to be materially different from those expressed or
implied by such forward-looking statements, including but not
limited to: risks related to the successful integration of
acquisitions; risks related to international operations; risks
related to general economic conditions and credit availability,
actual results of current exploration activities, unanticipated
reclamation expenses; changes in project parameters as plans
continue to be refined; fluctuations in prices of metals including
gold; fluctuations in foreign currency exchange rates, increases in
market prices of mining consumables, possible variations in ore
reserves, grade or recovery rates; failure of plant, equipment or
processes to operate as anticipated; accidents, labour disputes,
title disputes, claims and limitations on insurance coverage and
other risks of the mining industry; delays in the completion of
development or construction activities, changes in national and
local government regulation of mining operations, tax rules and
regulations, and political and economic developments in countries
in which Endeavour operates. Although Endeavour has attempted to
identify important factors that could cause actual results to
differ materially from those contained in forward-looking
statements, there may be other factors that cause results not to be
as anticipated, estimated or intended. There can be no assurance
that such statements will prove to be accurate, as actual results
and future events could differ materially from those anticipated in
such statements. Accordingly, readers should not place undue
reliance on forward-looking statements. Please refer to Endeavour's
most recent Annual Information Form filed under its profile at
www.sedar.com for further information respecting the risks
affecting Endeavour and its business. AISC, all-in sustaining costs
at the mine level, cash costs, operating EBITDA, all-in sustaining
margin, free cash flow, net free cash flow, free cash flow per
share, net debt, and adjusted earnings are non-GAAP financial
performance measures with no standard meaning under IFRS, further
discussed in the section Non-GAAP Measures in the most recently
filed Management Discussion and Analysis.
Corporate Office: 5 Young St, Kensington,
London W8 5EH, UK
- Image 1: Process Plant - Wet Plant.jpg
- View News Release in PDF Format.pdf
- Image 8: Employee Permanent Camp.jpg
- Image 7: Village Resettlement.jpg
- Image 2 : Process Plant - Dry Plant.jpg
- Image 3 : Site Aerial View.jpg
- Image 5 : Switchyard and Power Station.jpg
- Image 9: Mining Activity.jpg
- Image 4: Tailings Storage Facility.jpg
- Image 6: Haul Bridge.jpg
Endeavour Mining (TSX:EDV)
Historical Stock Chart
Von Nov 2024 bis Dez 2024
Endeavour Mining (TSX:EDV)
Historical Stock Chart
Von Dez 2023 bis Dez 2024