Jubilee Metals Group Plc
Registration number
(4459850)
AIM
share code: JLP
Altx share code:
JBL
ISIN: GB0031852162
("Jubilee" or "Company" or "Group")
Dissemination of a Regulatory
Announcement that contains inside information according to UK
Market Abuse Regulations. Not for release, publication or
distribution in whole or in part in, into or from any jurisdiction
where to do so would constitute a violation of the relevant laws or
regulations of such jurisdiction.
Operational Update H1
FY2025
Jubilee, a diversified metals
producer with operations in South Africa and
Zambia, today publishes
its unaudited operational and project update for the half year
ended 31 December 2024 (H1 FY2025).
Highlights
Zambia
§ Lost Time
Frequency Injury Rate (LTFIR) of 1.00 (H1 FY2025: 0.61).
§ Copper
units produced reached 1 454 tonnes (H1 FY2024: 1 683
tonnes) below the revised half year production target of 1 800
tonnes mainly due to the impact of power constraints.
§ Run-of-Mine (ROM) and in process stock increased sharply as a
result, reaching approximately 1.21 million tonnes containing an
estimated 8 466 tonnes of copper units for future
processing.
§ Additional power
agreement executed with a new broad based power provider to
supplement the existing power supply agreement, specifically aimed
at achieving steady power supply at Roan. The agreement:
o Secures access
to a distributed power base from multiple sources of power
generation to avoid dependency on a single supply source and
localised power network distribution limitations;
o Is expected to
commence with power supply within 7 business days pending
regulatory approval; and
o The new
additional power supply is capable of supplying all of Sable and
Roan's power demands, if required, at a power cost similar to the
existing power agreement.
§ Sable refinery was
able to continue operating and remains operational given its
proximity to the power producer.
§ Roan upgrade and
commissioning completed reaching ramp-up throughput targets of a
combined 45 000 tonnes per month during the period before
experiencing shut-downs due to power constraints.
o Roan was
commissioned and ramped up initially using low-grade waste
materials before targeting the switch to feed materials
containing approximate 1.5% copper (Cu);
o Roan was placed
under care and maintenance to prioritise maintenance activities and
to avoid any risk of equipment damage due to unstable power supply;
and
o Roan will
restart with the commencement of power supply under the additional
power supply agreement.
§ Copper production at
Munkoyo unaffected by power constraints:
o Munkoyo mining
on target producing in excess of 70 000 tonnes per month of ROM
ready for future processing;
o High grade ROM
at a rate of 8 000 tonnes per month exceeding 2.5% total copper,
continues to be directly refined at Sable; and
o Pilot-scale
leach trials targeting all of the ROM produced at Munkoyo have
shown exceptional results and implementation will be accelerated
with final designs and capital estimations expected by end of Q1
CY2025.
§ Copper production
rates are expected to return to target on the back of the
commencement of the additional power agreements and the restart of
Roan plant.
South
Africa
§ South Africa reported
a LTIFR rate of 1.45 (H1 FY2024: 2.41).
§ Chrome concentrate
produced reached record highs on the back of the successful
commissioning of two further chrome processing units increasing by
35.7% to 974 659 tonnes (H1 FY2024: 718 189 tonnes), well on track
to meet and exceed full year guidance of 1.65 million
tonnes.
§ 6E Platinum Group
Metals* (PGM) produced for H1 FY2025 reached 18 435oz (H1 FY2024:
20 244oz), on track to meet full year guidance of
36 000oz.
§ The new chrome
processing modules built at Thutse met design throughput during
December setting a record total chrome concentrate production for
Q2 FY2025 of 519 310 tonnes.
* 6E PGM - Platinum, palladium,
rhodium, ruthenium, iridium and gold
Production
guidance for FY2025
§ Copper: Increased
copper production in place, however, guidance is under review until
such time as consistent power supply is established and Roan is
brought back into operation following the most recent
agreement.
§ Chrome and PGM:
On-track to achieve and exceed chrome concentrate production
guidance of 1.65 million tonnes, and PGM production guidance of
36 000oz.
Statement from
Leon Coetzer, Jubilee CEO:
"Over the
past quarter, we have experienced significant challenges in our
Zambian operations brought on by a combination of extraordinary
circumstances outside of our direct control. We have addressed the
power supply challenge by entering into an additional power supply
agreement that sources power across a broader generation
network to avoid localised exposure to network instabilities and a
single power generation plant. This power supply contract should
successfully address current power supply limitations that affected
Roan's ability to operate.
The timing of
the interruptions was particularly unfortunate given the recent
successful commissioning of the upgraded Roan facility set to
significantly increase the copper production alongside the Munkoyo
operation. We expect to return to the processing rate previously
achieved at Roan once power delivery under the new power supply
agreement commences.
The Munkoyo
process trials have delivered very encouraging results confirming
our ability to process all of the ROM mined at Munkoyo on-site, at
a much lower operating cost and a reduced operating footprint than
originally envisaged. This offers the potential to fast track the
implementation of this process solution. Our technical team is
completing the design and implementation plan which is expected
within this quarter.
While
unexpected setbacks manly outside of our control do provide hurdles
to a smooth growth path in Zambia, we have successfully navigated
these challenges and I remain confident in our ability to bringing
full value to the investment made into the expansion of our
operating and processing footprint. We are withholding an updated
copper guidance until the additional power under the power
agreement is delivered and we are able to return to running the
operations on a continuous basis.
In South
Africa, the team continues to deliver an exceptional performance,
and we are well on track to achieve and exceed our chrome guidance
of 1.65 million tonnes of chrome concentrate for FY2025, following
the two new Thutse production modules reaching design capacity
during December, leading to a quarterly production record for Q2
FY2025. Our Chrome and PGM business have proactively reacted to the
sharp decline in the chrome market prices by successfully
increasing both operational efficiencies and overall throughput.
"
Zambia
Half Year
Production results
The table below presents the unaudited
operational production performance of Zambia for H1
FY2025:
OPERATIONAL PERFORMANCE
|
|
H1 FY2025
|
H1 FY2024
|
% change
|
COPPER
|
|
|
|
|
In
process stock
|
|
|
|
|
Copper in process
stock
|
DMT
|
1 210 312
|
-
|
100.0%
|
Grade
|
Tcu%
|
0.7%
|
-
|
100.0%
|
Copper units
|
tonnes
|
8
466
|
-
|
100.0%
|
Production
|
|
|
|
|
Copper
|
tonnes
|
1
454
|
1
683
|
(13.6%)
|
Power supply
agreement
A new power agreement has been executed with a
broad-based power provider to supplement the existing power supply
arrangement. This agreement secures access to a broader and more
distributed power base and power sources, reducing the Company's
reliance on a single power generation facility that is vulnerable
to local distribution and generation constraints. These constraints
have significantly impacted continuous operations at the Roan
facility, an issue which the supplementary agreement aims to
resolve. Power supply under the new agreement is expected to
commence within 7 business days, pending regulatory approval. The
Company was successful in securing power rates comparative to the
current power rates charged under the existing power agreement. The
new agreement caters for the potential to supply all of the power
demands at both Sable and Roan if required.
Roan
Concentrator
The Roan upgrade and commissioning were
successfully completed during the period, with the operation
achieving ramp-up targets by processing low-grade ROM from
extensive historical stockpiles. However, after reaching capacity,
the Roan operation faced significant challenges, leading to a
partial closure to resolve issues related to supplementary power
agreements. Roan was placed under care and maintenance to
prioritise key maintenance activities during this
period.
Roan achieved a combined throughput of 45 000
tonnes per month processing low grade materials to minimise loss of
copper during the ramp-up and commissioning of the operation. Roan
was scheduled to switch over to the longer-term feed material
targeting a copper grade in excess of 1.5% Cu prior to the forced
closure. Roan is expected to complete with the switch over once
stable power under then new power agreement is
established.
Sable
Refinery
In line with Jubilee's ongoing resource
expansion in Zambia, the Company is upgrading Sable to serve as a
dedicated facility for processing materials from Open-Pit mining
operations, including the recently acquired Munkoyo and Project G.
The upgrade is currently in progress and is expected to be
completed during Q2 FY2026.
The successful acquisition of these targeted
resources has enabled Jubilee to transform Sable into a specialised
refiner focused on shallow Open-Pit mining operations.
Munkoyo
Copper production at Munkoyo has remained
unaffected by recent challenges, with total production of ROM
exceeding 70 000 tonnes per month. The high-grade ROM
exceeding 2.5% Cu is direct leached and refined at Sable targeting
a rate of 8 500 tonnes per month of ROM delivered. The remaining
lower grade ROM at an approximate grade of 0.7% Cu is stockpiled on
site. An on-site leaching process targeting all of the ROM mined at
Munkoyo has been developed by Jubilee's technical team with pilot
trails scheduled during the period.
The pilot-scale leach trials of Munkoyo
material, initiated in December 2024, have delivered exceptional
results, demonstrating significantly reduced acid consumption rates
for copper extraction and the potential to considerably reduce the
required operating footprint. Currently, only high-grade ROM
material is transported to Sable for refining, while the remaining
ROM is stockpiled at Munkoyo for further on-site
processing.
The leach trials confirm not only the
recoverability of copper from the ROM, but also the strong economic
returns this processing method offers to the Munkoyo operation.
Implementation of the leach solution will be accelerated, with
final design and capital estimates expected by the end of Q1
CY2025. Based on pilot run results, a modest capital investment is
required at Munkoyo, with most equipment sourced locally to avoid
long lead times. Further details will be provided as soon as
possible.
Project
G
Following the completion of Jubilee's due
diligence on Project G during August 2024, the Company acquired a
majority interest in Project G.
The project aims to expand existing operations
to achieve an initial mining rate of 10 000 tpm by February 2025.
Project G includes an on-site facility designed to pre-concentrate
mined ROM material, with an immediate capacity to produce 3 000
tonnes of copper concentrate per month, containing 10% to 15%
copper. Lower-grade copper will be stockpiled for future on-site
processing. First copper concentrate was produced at Project G
during October 2024.
Large Scale
Waste Rock Project
The project targets the processing of the
approximate 260 million tonnes of previously mined material through
a dedicated processing footprint resembling the new Roan facility.
The Company is currently focussed on the completion of the extended
industrial trial as part of its ongoing due diligence review. Under
the terms of the option to purchase agreement, a due diligence
extension to the end of January 2025 has been agreed to allow
sufficient time to compile the results from the trial.
South Africa
Half Year
Production results
The table below presents the unaudited
operational production performance of South Africa for H1
FY2025:
OPERATIONAL PERFORMANCE
|
|
H1 FY2025
|
H1 FY2024
|
% change
|
Chrome and PGM
|
|
|
|
|
Production
|
|
|
|
|
Chrome
|
tonnes
|
974
659
|
718 189
|
35.7%
|
PGM
|
Oz
|
18
435
|
20
244
|
(8.9%)
|
The Company continues to experience growth in
its South African operations, which are now well-established and
consistently delivering strong results. Chrome operations increased
output to 974 659 tonnes for H1 FY2025 on the back of improved
efficiencies while PGM production benefited from better quality
feed to produce 18 435 ounces.
Construction and commissioning of the two new
chrome processing modules was successfully completed and
commissioned contributing to the record production achieved over
the past period.
13 January 2025
For further information visit www.jubileemetalsgroup.com,
follow Jubilee on Twitter (@Jubilee_Metals) or contact:
Jubilee Metals
Group PLC
Leon Coetzer (CEO) / Jonathan Morley-Kirk
(FD)
Tel: +27 (0) 11 465 1913 / Tel: +44 (0)
7797 775546
Nominated
Adviser - SPARK Advisory Partners
Limited
Andrew Emmott/James Keeshan
Tel: +44 (0) 20 3368 3555
PR & IR
Adviser - Tavistock
Jos Simson/ Gareth Tredway
Tel: +44 (0) 207 920 3150
Joint
Broker - RBC Capital Markets
Farid Dadashev/Jamil
Miah
Tel +44 (0) 20 7653 4000
Joint Broker -
Zeus Capital
Harry Ansell/Katy
Mitchell
Tel: +44 (0) 20 7220 1670/+44 (0) 113 394
6618
JSE Sponsor -
Questco Corporate Advisory Proprietary
Limited
Alison McLaren
Tel: +27 63 482 3802
About Jubilee Metals Group
Plc
Jubilee is a low-cost, diversified producer,
specialising in the recovery and processing of metals from
previously overlooked resources, such as unprocessed historical
waste rock, run-of-mine materials and tailings in Zambia and South
Africa. The Company's low-capex, modular processing facilities are
deployed close to these various types of material, producing high
grade concentrates for sale or further refining to finished metal
at the Company's downstream facilities. Production currently
consists of copper, chrome, and platinum group metals (PGMs). The
modular processing facilities offer a platform for growth and the
rapid expansion of Jubilee's operational footprint in Zambia and
South Africa. Jubilee's success is derived from operational and
technical excellence, an experienced management team and a
pioneering Technical Development Centre.