Petro Matad Limited
("Petro
Matad" or the "Company")
Heron-1 operational
update
LONDON, 19 September 2024:
Petro Matad Limited (AIM: MATD), the AIM quoted
Mongolian oil company, provides the following operational update on
the Heron-1 oil discovery well and anticipated oil production
start-up.
· Petro Matad has proposed that Heron-1 will be put onstream
through temporary facilities so that production is not further
delayed by slow moving bureaucracy.
·
Mineral Resources and Petroleum Authority of
Mongolia (MRPAM) has formally agreed to this proposal, with
production start-up on Heron-1 now anticipated during
October.
Heron-1 well pad - surface
facilities
As previously reported, the
application for the construction permit to install the long-term
production facilities at Heron-1, which could only be initiated
after land access had been approved in late May, had reached the
final stage and the permit is with the provincial Governor for the
final signature required. The Governor is new in-post, having been
formally appointed in early September, and has told the Company
that he needs time to review the application. In light of this, and
with no indication of how long this review will take, Petro Matad
has proposed, and industry regulator MRPAM has formally agreed,
that Heron-1 will be put onstream through temporary facilities so
that production is not further delayed by slow moving bureaucracy.
The temporary facilities will be positioned on the well site to
allow construction of the long-term facilities to go ahead in
parallel with production operations once the construction permit
has been obtained. The Company has given notice to its chosen
contractor to install the temporary facilities and the work is
anticipated to be completed within two to three weeks.
Oil sales
Following the high level meeting
held at the Block XIX facilities some 20km north of the Heron-1
well, agreement in principle has been reached between Petro Matad
and the Block XIX operator for the collection, metering,
processing, storage, export and sale of Block XX production. The
details are now being incorporated into a cooperation agreement
which will then be presented to MRPAM for its approval. The parties
have committed to try to have the agreement in place in time for
production start-up on Heron-1 which is now anticipated to be
during October.
Mike Buck, CEO of Petro Matad,
said:
"The further hold up of the
construction permit at the final step of an unnecessarily complex
process is unwelcome, but we are very pleased that we have the
support of MRPAM to use temporary facilities to expedite
production. We do not anticipate any significant facility cost
increase as a result of this solution and we will closely manage
the construction activities when they start, to allow construction
and production operations to continue simultaneously.
The meeting in Block XIX was very
productive and the operator's willingness to cooperate with the
Company is much appreciated. We look forward to completing the
drafting of the cooperation agreement and to securing MRPAM's
approval within the next few weeks.
Meanwhile, Heron 2 drilling
operations are proceeding smoothly. With Gobi Bear-1 soon to spud,
these are busy and exciting times for the Petro Matad
team."
Further updates will be provided as
the 2024 work programme progresses.
- Ends -
Further
information please contact:
Petro Matad
Limited
|
|
Mike Buck, CEO
|
+976 7014 1099 / +976 7575 1099
|
|
|
Shore Capital
(Nominated Adviser and Broker)
|
Toby Gibbs
Rachel Goldstein
|
+44 (0) 20 7408 4090
|
Zeus (Joint
Broker)
Simon Johnson
Louisa Waddell
|
+44 (0) 20 3829 5000
|
FTI Consulting
(Communications Advisory Firm)
|
|
Ben Brewerton
Christopher Laing
Catrin Trudgill
|
+44 (0) 20 3727 1000
|
About Petro Matad
Petro Matad is the parent company of
a group focused on oil exploration, as well as future development
and production in Mongolia. Currently, Petro Matad holds 100%
working interest and the operatorship of the Matad Block XX
Production Sharing Contract with the government of Mongolia. Block
XX has an area of 214 square kilometres in the far eastern part of
the country.