Tanzanian Royalty's recently released Mine Feasibility Study
(MFS) defines 1.064 million ounces of open pit minable gold, and
initiates discussion on development of the underground Mine
potential.
TORONTO, July 13, 2017 /PRNewswire/ - Tanzanian
Royalty Exploration ("TRX" or the "Company") (NYSE: TRX) (TSX: TNX)
is providing an update to its shareholders, discussing the findings
of its recently completed Mining Feasibility Study ("MFS" or the
"Study") on its JV-owned Buckreef Gold Mine Project (the
"Project"). The Study was led by an external consultant team
from MaSS Resources Ltd. of Tanzania, with technical support provided by
an internal team and combined previous published Preliminary
Economic Assessment study results by Venymn of South Africa, as well as other historical
feasibility studies conducted over the years on this historic
deposit. The Buckreef project is in the Geita District in Lake
Victoria Greenstone Belt in central Tanzania, East
Africa. The full study can be found on the home page of the
Company's website: www.tanzanianroyalty.com
"We want to take this opportunity to inform our loyal investors
of not only the next steps towards mining production but also
direct their attention to the discussion of the underground
potential of Buckreef.," stated Jeffrey
Duval, Acting Chief Executive Officer of TRX. We have
included a small portion of the underground discussion in this
release and are excited with the potential that our last the deep
drilling program uncovered. The results mirrored favorably with the
historical records from the old Buckreef underground workings.
"As you can see in the slide, the underground mineralisation
extends several hundred meters below the bottom of the open pit
mine and the drill hole is open in all directions. It is this
feature that has us most excited for the future."
"We are also pleased to have achieved third-party validation of
the tremendous economic potential for the open pit portion of the
Buckreef Project.
"The Company maintains a 55% economic interest in the Buckreef
project, which infers a 55% interest in the 1.064 million ounces of
gold reserves at Buckreef, which has been validated by independent
consultants. When one compares our current stock price levels to
the Company's economic interests at Buckreef, measured at gold
prices levels throughout the last several years, our stock price is
trading at significantly discounted
levels.
"The Study results reflect the continued refinement of pit
optimized mining reserves, mine production schedule, process plant
ore feed schedule and financial projections & analysis based on
comprehensive cost estimations for process plant (design,
fabrication, construction and operation) and mining (equipment
purchase and mine production) on the Buckreef Project.
The Company has begun active negotiations to complete financing
on a straight loan basis. This will ensure that we have the
necessary capital to complete the reconditioning and construction
of new modules for our modern Gravity/CIL plant. We have brought in
a team of experts with decades of experience in building and
maintaining these types of plants. We have the utmost confidence in
their ability to complete the project under budget and ahead of
schedule. Importantly, this Gravity/CIL plant will allow us to run
pay dirt at an efficiency rate of 90% or higher in the recovery of
gold. We anticipate the plant being built in approximately 8
months.
The Company has successfully operated in Tanzania since 1992. The significant
experience of our technical team, as well as the consultants in
Tanzania contributes to the
integrity of the results. The soon-to-commence grade control
drilling will be essential to further refine the mineable reserves
during the pre-stripping development plan, and in advance of our
process plant construction," concluded Mr. Duval.
Highlights
- Conventional open pit mining methods selected in pit
designs.
- Over LoM, a total of 17.49Mt of ore with a strip ratio of 8.1:1
will be mined.
- Pre-existing stockpile (ROMPAD) ore totaling 119,726t grading
1.89g/t to be used for process plant commissioning.
- 1.064Moz of gold to be mined over the life of the project.
- Recoveries of 89% for primary ore and 93%for saprolite ore,
utilizing a simple EDS comminution, flotation and leaching process
with gravity recovery circuit for free Au component
collection.
- 0.91Moz of gold will be produced over the life of the
project.
- Initial capital cost outlay estimated at US $32.5 Million with a Life of mine cost over the
three phases of US $59.6 million and
sustaining capital, excluding closure costs.
- Cash operating costs of US $696/oz produced equivalent US $35.95 per tonne milled.
- Generation of a positive NPV of US $243
million at a 5% discount rate and an IRR of 53.7%
Major Assumptions
- Gold price of US $1250/oz
- Effective Tax Rate of 15.25%
- Royalty Rate of 4.3%
- Transport refining cost of $15.00/oz Au
- Discount rate of 5%
Mineral Resources and Reserves
The mineral resources and reserves of the Buckreef deposits
were classified using logic consistent with the CIM definitions
referred to in National Instrument 43-101.
The mineral resource block model, which serves as the basis of
the Mineral Resources and Mineral Reserves in the Study, were
developed utilizing 3D lithology models. Table 1 summarizes
the Mineral Resources for the Buckreef project as of February 14, 2014. The mineral resource is
reported at a 0.5 g/t Au cut-off grade.
Table 1 – Buckreef Mineral Resources
Prospect
|
MEASURED
|
INDICATED
|
INFERRED
|
MEASURED+INDICATED
|
EXPLORATION
TARGET
|
Tonnes
(Mt)
|
Grade
(g/t)
|
Contained
Gold
(oz Au)
|
Tonnes
(Mt)
|
Grade
(g/t)
|
Contained
Gold
(oz Au)
|
Tonnes
(Mt)
|
Grade
(g/t)
|
Contained
Gold
(oz Au)
|
Tonnes
(Mt)
|
Grade
(g/t)
|
Contained
Gold
(oz Au)
|
Tonnes
(Mt)
|
Grade
(g/t)
|
Contained
Gold
(oz Au)
|
Buckreef
|
8.902
|
1.72
|
491,529
|
13.100
|
1.41
|
594,456
|
7.528
|
1.33
|
322,902
|
22.022
|
1.53
|
1,085,985
|
4.385
|
1.10
|
155,321
|
Eastern
Porphyry
|
0.087
|
1.20
|
3,366
|
1.016
|
1.17
|
38,355
|
1.239
|
1.39
|
55,476
|
1.103
|
1.18
|
41,721
|
1.324
|
1.14
|
48,664
|
Tembo
|
0.017
|
0.99
|
531
|
0.185
|
1.77
|
10,518
|
0.267
|
1.29
|
16,521
|
0.202
|
1.71
|
11,048
|
0.095
|
1.12
|
3,429
|
Bingwa
|
0.906
|
2.83
|
82,387
|
0.569
|
1.38
|
25,274
|
0.312
|
1.36
|
12,922
|
1.475
|
2.26
|
107,661
|
0.049
|
1.25
|
1,982
|
TOTAL
|
9.912
|
1.81
|
577,813
|
14.870
|
1.40
|
668,603
|
9.346
|
1.36
|
407,821
|
24.782
|
1.56
|
1,246,415
|
5.853
|
1.11
|
209,396
|
The pit optimization was produced using NPV Scheduler software
which utilizes the industry standard Lerchs Grossman algorithm for
analysis. Updated cost and recovery inputs in conjunction with new
geotechnical parameters and ramp design from the preliminary
economic assessment study were incorporated in the final pit design
process.
The base case US $1,100 gold shell
was selected for the ultimate pit design. The final pit contains
approximately 17.5Mt of ore (saprolite and primary), with
142Mt of waste resulting in an
overall strip ratio of 8:1.
Table 2 summarizes the Project Mineral Reserves effective as of
April 27, 2017. Reserves were
calculated using a US $1,100 per oz
gold price and the corresponding cut-off grade of 0.59 g/t for all
ore categories.
Table 2 – Buckreef Mineral Reserves
Mineral Reserve
Category
|
Tonnes
(T)
|
Grade
(g/t)
|
In-Situ Gold
(Ozs)
|
Measured
|
12,249,856
|
1.78
|
702,169
|
Indicated
|
4,256,531
|
2.17
|
297,619
|
Measured +
Indicated
|
16,506,387
|
1.88
|
999,788
|
Inferred
|
984,710
|
1.99
|
63,064
|
Mining
The deposit is projected to be mined utilizing owner-operated
conventional open pit mining methods. Mining will be completed
using 5 meter benches in the saprolite zone and 10 meter benches in
the primary sulphide zone. Updated pit wall angle designs and
Tanzanian mining regulations were incorporated into the mine
plan.
The mine is estimated to produce sufficient ore to maintain an
initial process plant feed scheduled at 60tph (Yr1-Yr4) with
upgrades to 120tph (Yr5-Yr9) and 180tph (Yr10 onwards). Targeted
ore production during commercial production is 1,500,000 tonnes per
year LOM. Stockpiling of ore over LOM will result in surplus ore to
be processed up to Year 17.
Mineral Processing
The process design for the Buckreef Project is based on
extensive metallurgical test-work. Results from the work have
established that high gold recoveries can be achieved with a
conventional process of comminution (using the latest EDS system as
a replacement for the conventional ball & roller mill circuit),
gravity concentrate, flotation and flotation concentrate leaching
circuit.
Buckreef project ores are projected to be treated at a rate of
1.5Mt per annum with process plant capacity upgrades in Yr-5 and
Yr-10. Overall recoveries from the flotation and cyanide leach
circuits are expected to be 89% and 93% for primary ore and
saprolite ore, respectively. Over the life of the mine an
average of 53,534 oz Au per annum will be produced as doré.
Project Economics
Cost estimates were developed to a feasibility level of
accuracy. Budget quotations for mobile and plant equipment were
obtained from international suppliers. Unit rates for
material commodities (earthworks, concrete, and steel) in
Tanzania were verified from
contractor and supplier quotations and based on current practice in
Tanzania.
Construction and labor costs applicable for the region were
built up from first principles for salaries, burdens and overhead.
Contingency was applied to each item based on the source and
accuracy of the estimate data, resulting in an overall initial
contingency of 10%. The Project Capital Cost Summary is included in
Table 3.
Table 3 – Project Capital Cost Summary
Item
|
Description
|
Initial
(US#)
|
A
|
Mining
|
12,649,184
|
B
|
Process
Plant
|
35,384,625
|
C
|
HR &
Community
|
3,795,000
|
D
|
HSE
|
100,000
|
E
|
Finance &
IT
|
2,241,519
|
Total Direct
Costs
|
54,170,328
|
Indirect
Costs
|
|
Owner's
Costs
|
|
Contingency
(10%)
|
5,417,033
|
Total Installed
Cost
|
59,587,361
|
Operating costs were also developed from first principles,
inclusive of labor, consumables, fleet maintenance and repair, and
general and administration costs, and data from current operations
in Tanzania. The estimated
Operating Cost is summarized in Table 4.
Table 4 – Operating Cost Summary
Operating
Costs
|
Units
|
LOM Average
(US$)
|
Mining Cost
(mined)
|
$/t mined
|
1.94
|
Mining Cost
(ore)
|
$/t ore
|
17.67
|
Processing
Cost
|
$/t milled
ore
|
16.89
|
G&A
|
$/t ore
|
7.89
|
Direct Operating
Cost
|
$/t
ore
|
42.44
|
Direct Operating
Cost
|
$/t
ounce
|
696
|
The Project economic analysis has been carried out for a range
of gold prices with $1,250 per ounce
selected as the base case. The analysis demonstrates that the
Project is expected to generate a positive NPV at a 5% discount
rate of US $243 million and a
positive IRR of 53.7%. Sensitivity of the Project NPV and IRR
to changing metallurgical recovery or operating costs to
fluctuations in gold price are illustrated in Figure 1
below.
Figure 1: Sensitivity Analysis
Gold price is very sensitive to project NPV. An increase in gold
prices by 20% will result in double the project NPV. Though a
decrease in gold price has a negative impact on project NPV, the
project remains viable with a 30% decrease in Gold price
Metallurgical recovery follows the same trend as gold price
variations. A decrease in recovery results into low project NPV.
This is an important parameter to be monitored as slight negative
change in recovery has big impact on project profitability
The project is sensitive to OPEX. A decrease in operating cost
result into cash-flow saving and hence increase in project NPV.
While the base case demonstrates a positive return at the
Feasibility capital and operating costs, the chart demonstrates
further opportunities for improving the economics of the Project by
investigating Capital and Operating cost savings. TRX
is confident that the capital and operating costs can be further
optimized, improving the value of the project.
Permitting
The SML renewal permitting process for the Buckreef Project
continues to advance with positive support of the local communities
and government authorities of Geita Municipality and Republic of
Tanzania. The preparation of
documents for the renewed 10-year permit was completed in
October 2016 and the offer letter
confirming approval and granting renewal of the SML was received in
February 2017. The Environmental
Management Plan (EMP) was approved in October 2016. The original Environmental Impact
Assessment (EIA) certification was granted in October 2014, and encompassed the mining, ore
processing and support infrastructure.
Underground Mining Potential
Mining of the Buckreef open pit will commence in year 0
(pre-stripping). Production from the underground can commence
towards the end of current LOM of the open pit via development of
an access decline/ramp without leaving a crown pillar below the pit
floor. An accurate cutover point between open pit and underground
can be calculated by comparing the cost to mine one tonne of
mineralized material considering waste movement and development
costs by both methods.
Underground Mineralization
The main Buckreef prospects are near surface deposits that are
amenable to be mined by open pit methods which in this project are
assumed to extend to a depth of 150-200 meters below surface.
This is an arbitrary cutoff point and it is most likely that
further optimization of the mineralization through grade control
drilling would result in either deeper or wider pits given the
grades and vein thickness (Figure 13.15). The two vein
systems being considered are assumed to be robust in terms of
continuity and thickness. The extents of the zone are 300m long and
15m wide at depths below 150m. The dip is assumed to be
sub-vertical to vertical.
Figure
0.1a Schematic
Section of Mineralisation at Buckreef
One of the veins has already been mined in the past and openings
extend down to 150m from surface. Considerable caution would need
to be exercised if mining near the old workings as voids may not
have been surveyed correctly and ground conditions around old
workings are often unstable.
Figure 13.15b: Section view - West East Buckreef Main
Pit
Figure 12.15c: Section View - North South
Buckreef Main Pit
Materials Inventory
No materials inventory (reserves) has been estimated for this
study. From initial ore-body modelling, an assumption that the bulk
of the inferred resource for the Buckreef Main deposit estimated to
contain about 35.54Mt grading 1.50g/t Au will constitute the bulk
of the underground resource inventory.
The geological continuity and grade distribution of the Buckreef
mineralisation is well constrained and the upside potential to
define additional Mineral Resources in extensions of the known ore
body has been confirmed through drilling.
Exploration should concentrate on laterally expanding open pit
mineralization down to say 100m and on deeper high grade
underground targets. Further detailed drilling will ensure
that the project economics would improve accordingly.
Accordingly, drilling should be concentrated in this target to firm
up a resource estimate.
Project Development
A conventional approach to mining and processing provides a
solid platform on which to develop this well-defined gold
deposit. Opportunities to improve the economics and value of
the project have been identified in the study. These areas
will continue to be investigated as development of the project
continues.
Thank you for your continued support of the Company as we move
forward toward commercial gold production.
The Company's Qualified Person, Mr. Peter Zizhou, has reviewed and approved the
contents of this news release. Mr. Zizhou is the COO of Tanzam2000,
a subsidiary of Tanzanian Royalty Exploration Corporation Limited.
He has a Master of Science (Exploration Geology) degree from the
University of Zimbabwe (2000) and
is a registered scientist with SACNASP (Reg. No.400028/08).
Respectfully Submitted,
"James E. Sinclair"
James E. Sinclair
Executive Chairman
Cautionary Note Regarding Forward-looking
Statements
Certain of the statements made herein may contain
forward-looking statements or information within the meaning of the
United States Private Securities Litigation Reform Act of 1995 and
applicable Canadian securities laws. Often, but not always,
forward-looking statements and forward-looking information can be
identified using words such as "plans", "expects", "is expected",
"budget", "scheduled", "estimates", "forecasts", "intends",
"anticipates", or "believes" or the negatives thereof or variations
of such words and phrases or statements that certain actions,
events or results "may", "could", "would", "might" or "will" be
taken, occur or be achieved. Forward-looking statements or
information herein include, but are not limited to the Positive
Feasibility Study on Buckreef.
Forward-looking statements and forward-looking information by
their nature are based on assumptions and involve known and unknown
risks, uncertainties and other factors which may cause the actual
results, performance or achievements of the Company to be
materially different from any future results, performance or
achievements expressed or implied by such forward-looking
statements or information. We have made certain assumptions
about the forward-looking statements and information and even
though our management believes that the assumptions made and the
expectations represented by such statements or information are
reasonable, there can be no assurance that the forward-looking
statement or information will prove to be accurate.
Furthermore, should one or more of the risks, uncertainties or
other factors materialize, or should underlying assumptions prove
incorrect, actual results may vary materially from those described
in forward-looking statements or information. These risks,
uncertainties and other factors include, among others, the
following: gold price volatility; discrepancies between
actual and estimated production, mineral reserves and resources and
metallurgical recoveries; mining operational and development risk;
litigation risks; regulatory restrictions, including environmental
regulatory restrictions and liability; risks of sovereign
investment; currency fluctuations; speculative nature of gold
exploration; global economic climate; dilution; share price
volatility; competition; loss of key employees; additional funding
requirements; and defective title to mineral claims or property, as
well as those factors discussed in the sections entitled
"Forward-Looking Statements" and "Risk Factors" in the Company's
Form 20-F Annual Report dated November 25,
2016.
There can be no assurance that forward-looking statements or
information will prove to be accurate, as actual results and future
events could differ materially from those anticipated in such
statements. Accordingly, you should not place undue reliance
on the forward-looking statements or information contained
herein. Except as required by law, we do not expect to update
forward-looking statements and information continually as
conditions change and you are referred to the full discussion of
the Company's business contained in the Company's reports filed
with the securities regulatory authorities in Canada and the U.S.
Cautionary Note Regarding Mineral Reserves and Mineral
Resources
The terms "Mineral Reserve", "Proven Mineral Reserve" and
"Probable Mineral Reserve" used in this release are Canadian mining
terms as defined in accordance with National Instrument 43-101 –
Standards of Disclosure for Mineral Projects under the guidelines
set out in the Canadian Institute of Mining, Metallurgy and
Petroleum (the "CIM") Standards on Mineral Resources and Mineral
Reserves, adopted by the CIM Council on August 20, 2000 as may be amended from time to
time by the CIM. These definitions differ from the
definitions in the United States
Securities Exchange Commission ("SEC") Guide 7. In
the United States, a mineral
reserve is defined as a part of a mineral deposit which could be
economically and legally extracted or produced at the time the
mineral reserve determination is made.
The terms "Mineral Resource", "Measured Mineral Resource",
"Indicated Mineral Resource", "Inferred Mineral Resource" used in
this release are Canadian mining terms as defined in accordance
with National Instruction 43-101 – Standards of Disclosure for
Mineral Projects under the guidelines set out in the CIM Standards.
Mineral Resources which are not Mineral Reserves do not have
demonstrated economic viability.
For a detailed discussion of Buckreef resource and reserve
estimates and related matters see the Company's reports, including
the Form 20-F Annual Report dated November
25, 2016 and technical reports filed under the Company's
name at our website at: www.TanzanianRoyalty.com.
Cautionary Note to US Investors Concerning Estimates of
Measured, Indicated and Inferred Resources
Note to U.S. Investors. While the terms "mineral
resource", "measured mineral resource," "indicated mineral
resource", and "inferred mineral resource" are recognized and
required by Canadian regulations, they are not defined terms under
standards in the United States and
normally are not permitted to be used in reports and registration
statements filed with the SEC. As such, information contained
in this report concerning descriptions of mineralization and
resources under Canadian standards may not be comparable to similar
information made public by U.S companies in SEC filings. With
respect to "indicated mineral resource" and "inferred mineral
resource" there is a great amount of uncertainty as to their
existence and a great uncertainty as to their economic and legal
feasibility. It cannot be assumed that all or any part of an
"indicated mineral resource" or "inferred mineral resource" will
ever be upgraded to a higher category. Investors are
cautioned not to assume that any part or all mineral deposits in
these categories will ever be converted into reserves.
There can be no assurance that forward-looking statements or
information will prove to be accurate, as actual results and future
events could differ materially from those anticipated in such
statements. Accordingly, you should not place undue reliance
on the forward-looking statements or information contained
herein. Except as required by law, we do not expect to update
forward-looking statements and information continually as
conditions change and you are referred to the full discussion of
the Company's business contained in the Company's reports filed
with the securities regulatory authorities in Canada and the U.S.
SOURCE Tanzanian Royalty Exploration Corporation