Athabasca Minerals Inc. Announces Q1 2014 Results and Submits
Conservation and Reclamation Business Plan to Alberta Government
EDMONTON, ALBERTA--(Marketwired - Apr 28, 2014) - Athabasca
Minerals Inc. ("Athabasca" or the "Corporation") (TSX-VENTURE:ABM)
is pleased to announce its financial results for the three months
ended February 28, 2014. The Corporation's unaudited interim
financial statements and management's discussion and analysis
("MD&A") for the three months ended February 28, 2014 are
available on SEDAR at www.sedar.com and on the Athabasca Minerals
website at www.athabascaminerals.com.
Q1 2014 Highlights
- Issued common shares for gross proceeds totalling $5.75 million
through a private placement;
- The Corporation initiated production and sales from its
corporate-owned Cowper aggregate operation, the first operation
brought into production under its agreement with a First Nations
company;
- Built up strategically stockpiled aggregate inventory with cost
in excess of $8.1 million, providing a competitive advantage by
ensuring a guaranteed supply to service construction demand in
2014;
- Commencement of the winter drilling program at the Richardson
Project in order to further investigate granite and dolomite
resource potential;
- Construction of corporate-owned camp to accommodate employees
at Conklin versus using third party camp facilities in order to
reduce accommodation costs.
Q1 2014 sales from corporate-owned aggregate operations were
negatively impacted as a result of disruption in planned sales
activities involving two customer contracts. A customer suspended a
Logan pit contract when they put their project on hold.
Approximately 165,000 tonnes of fully processed gravel remains to
be hauled pending notification of contract resumption from the
customer. The majority of the remaining contract was expected to be
delivered and invoiced during Q1 2014. Secondly, a sales agreement
had been reached with a customer to purchase aggregates produced
from the Cowper pit. However, the agreement was cancelled and as a
result, a further amount of Q1 2014 planned sales did not
occur.
Due to the seasonality of the industry, during Q1 2014 Athabasca
also focused effort on equipment repair, and the setup of its
corporate-owned Conklin stockpile work camp to accommodate its
workers.
President and CEO Dom Kriangkum states, "While aggregate demand
within the region was considerably lighter than normal during the
first fiscal quarter, we are pleased to see that sales have picked
up in the second quarter, both at Susan Lake and at our
corporate-owned pits. During Q1 2014 management had noted a
significant reduction in inventory stockpiling outside of the Susan
Lake pit by our customers in advance of Q2 construction activity.
This was seen as a contributing factor in reduced aggregate sales
this past quarter. Despite the light sales volume in the early
months of fiscal 2014, management anticipates full year results
will normalize. As well as focusing on Q2 sales opportunities, the
executive team is currently undertaking a review of current
operating parameters and operational execution intended to identify
continued efficiency improvements. A detailed strategic analysis is
being performed to ensure key performance indicators are being
benchmarked, cost control measures are being achieved and maximum
productivity and efficiency are being achieved."
Operations Update
Aggregate demand has begun to ramp up during Q2, and management
anticipates Susan Lake demand will continue to accelerate as Q2
progresses. By the mid-point of Q2, Susan Lake sales had already
surpassed Q1 2014 Susan Lake sales. Management anticipates further
acceleration in Q2 aggregate demand, followed by strong demand
through the remainder of the fiscal year.
Activity at our corporate-owned pits is ongoing.
- Initial fiscal 2014 sales from the Kearl pit got underway in
mid-April, when hauling of aggregates to its nearby major customer
began and remains in progress;
- Unsold gravel processed at the Cowper pit has been hauled to a
new third party stockpile site near a major highway north of
Conklin, where it is available for year round delivery. Crushing
operations at the now depleted Cowper pit had concluded during Q2
2014, and reclamation activity at the pit is currently
underway;
- Some recent tree clearing has been initiated at the
corporate-owned Pelican Hill pit in order to prepare for future
production at that location.
Mining and crushing activity at the Logan and House River pits
is not expected to resume before late fall.
Financial Highlights
|
Three months ended February 28 |
|
|
Q1 2014 |
|
Q1 2013 |
|
Aggregate management fees |
$ |
554,567 |
|
$ |
1,489,017 |
|
Net aggregate sales |
$ |
2,863,278 |
|
$ |
5,194,379 |
|
Total revenue |
$ |
3,417,845 |
|
$ |
6,683,396 |
|
Aggregate operating expenses |
$ |
4,576,715 |
|
$ |
5,810,597 |
|
Gross (loss) profit |
$ |
(1,158,870 |
) |
$ |
872,799 |
|
Total aggregate tonnes sold |
|
578,537 |
|
|
1,516,224 |
|
Net loss from land use agreement |
$ |
Nil |
|
$ |
(227,796 |
) |
Net loss from aggregate operations |
$ |
(1,910,393 |
) |
$ |
(146,786 |
) |
Net loss and comprehensive loss |
$ |
(1,910,393 |
) |
$ |
(374,582 |
) |
Basic loss per common share |
$ |
(0.063 |
) |
$ |
(0.013 |
) |
Basic cash flow per share |
$ |
(0.029 |
) |
$ |
0.026 |
|
The $3,265,551 decline in Q1 2014 revenue compared to Q1 2013
was the primary reason for the resulting net loss of $1,910,393, an
increase of $1,535,811 over Q1 2013. The sales decline includes a
$934,450 reduction in aggregate management fees, resulting from a
62.5% reduction in aggregate tonnes sold from Susan Lake; and, a
$2,331,101 reduction in net aggregate sales, resulting from a 57.2%
reduction in aggregate tonnes sold from corporate-owned pits.
Aggregate operating expenses during Q1 2014 had decreased by
$1,233,882 compared to Q1 2013, primarily as a result of reduced
costs associated with lower sales volume from corporate-owned
pits.
Management attributes the sales decline to a reduction in
inventory stockpiling outside of the Susan Lake pit, and a slower
ramp up of civil projects during Q1 2014 in the Fort McMurray
area.
Outlook
Athabasca's core business relies on aggregate demand from
Alberta's oil, natural gas and mining industries in addition to
municipal and road construction projects. Historically Athabasca
has stronger third and fourth quarters following typically slower
first and second quarters due to seasonal considerations such as
winter conditions and spring break-up conditions.
The Corporation determines demand for the year by discussing
expected aggregate requirements with its major customers.
- Improving sales demand during Q2 and expected strong demand
during Q3 and Q4 is expected to offset the Q1 sales shortfall.
- Existing inventory turnover during fiscal 2014, along with the
efficient production of further processed aggregates from its
corporate-owned pits is a management priority;
- Cost savings have been targeted for near term implementation,
including equipment repair and maintenance costs, work crew
accommodation costs, and reduced hauling rates for aggregates
delivery. These initiatives will provide improved productivities
and increased efficiencies, resulting in measurable performance
gains;
- Athabasca plans for strategic crushing at its corporate-owned
pits during Q2 and continuing through Q4 based on market
demand.
The conservation, reclamation and business plan (CRBP) for the
Firebag Project has now been submitted for government approval;
meanwhile further work will be performed for the 43-101 resource
report.
AGGREGATE OPERATIONS:
Corporate-Owned
Pits
Management is focussed on opportunities to sell its existing
aggregate inventory, and is actively negotiating with various
customers who have expressed interest for the purchase of
aggregates, which involves all of the Corporation's inventory
locations.
Currently, processed and stockpiled inventory includes
approximately 530,000 tonnes of gravel and 440,000 tonnes of sand
located across Athabasca's corporate-owned pits and stockpile
sites. This leaves the Corporation well positioned to supply
aggregates to regional customers from its existing inventory of
processed aggregate products.
- Fiscal 2014 Kearl pit sales are now underway, with current
hauling in progress to its nearby major customer. Based on
additional purchasing interest expressed by other parties for its
crushed aggregate products, management anticipates strong overall
sales at the Kearl pit during fiscal 2014 from its inventory which
includes over 250,000 tonnes of gravel and 389,000 tonnes of
sand;
- Logan pit inventory sales discussions are occurring with oil
and gas developers in the area. The majority of aggregate sales are
expected to resume in late fall 2014 when winter haul road
conditions improve access to the pit. Currently 121,000 tonnes of
gravel remains available for sale at the Logan pit;
- 68,000 tonnes of gravel at Athabasca's Conklin stockpile site
is currently available for year round sales and delivery;
- 50,000 tonnes of processed sand remaining onsite at Athabasca's
Cowper pit. A further 46,000 tonnes of processed gravel and 20,000
tonnes of pit run is now available at a stockpile site near
Conklin, Alberta for year round sales.
The Logan pit is currently accessible only during the winter
months. The Corporation is considering the construction of an
all-season road during the summer of 2014, to allow for year round
access and product delivery, and help enable an earlier sale of its
existing inventory.
Under an agreement with a First Nations company, the Corporation
is awaiting approval from the Alberta Government to open a second
new pit later this year, and anticipates the pit will be available
to commence production during fiscal 2014.
During fiscal 2014 Athabasca seeks to improve its corporate pit
cost efficiencies, through its improved Kearl pit dewatering
method, and other experience gained during its first year of
operation within the pit. Improvement in the overall rate of
aggregate processing is anticipated, resulting in a reduction in
production cost per tonne.
Susan Lake Public
Pit
Q1 2014 was subject to frozen conditions and periods of extreme
cold and snow resulting in very little construction activity
requiring sand and gravel. Despite the soft first quarter in 2014,
the Corporation is observing increased activity at the Susan Lake
gravel pit during Q2. Increasing demand for aggregate is evident as
Q2 Susan Lake sales to date have already surpassed what was sold
during all of Q1. Indications from its customers point to a return
to solid demand for aggregates beginning in Q2, with strong sales
in Q3 and Q4.
The Corporation has received sand and gravel orders from
existing users for significant quantities to be fulfilled during
fiscal 2014. Management also received substantial gravel requests
from new customers who are bidding on works for a new oil sands
project at the north end of the Susan Lake pit. Management
anticipates construction of the project will last between two to
three years before being placed into production. Oil sands projects
typically consume 5 to 8 million tonnes of aggregates for plant
construction and another 0.5 to 1.0 million tonnes annually to
maintain roads and other infrastructure.
INDUSTRIAL METALLIC
MINERALS PROJECTS:
Firebag Project (Silica
Sand)
- The Firebag silica sand has been tested and found to be
suitable as frac sand for the oil and gas industry;
- In February 2014 the Corporation received notification from
Alberta Environment and Sustainable Resources Development ("ESRD")
that the department has completed its review of Athabasca's silica
sand surface material lease application at the Firebag Project. The
notice confirms that ESRD has, in principle, completed its review
of the lease boundary that is approximately 80 acres in size, and
forms a part of the larger Firebag Project;
- Athabasca previously submitted a technical memo documenting
development and reclamation.
- On April 23, 2014 the Corporation submitted a Conservation and
Reclamation Business Plan ("CRBP") to ESRD for their review before
receiving final approval. The CRBP is a normal course requirement
of the approval process;
- The Corporation is currently in discussion with a major
engineering firm being considered to perform a preliminary economic
assessment of the Firebag Project in order to confirm the economic
potential of the Firebag deposit.
Athabasca has also been in discussion with a major railway
company for developing a future frac sand trans-loading facility,
wet sand facility, drying facility and storage terminal east of
Fort McMurray, within a strategically situated location. Management
is preparing preliminary cost estimates and examining alternatives
for processing and trans-loading of products.
Next steps include progress towards the completion of a National
Instrument 43-101 resource report for the Firebag Project.
The Firebag project consists of a silica sand deposit located
139 km north of Fort McMurray and is accessible via Highway 63. The
Corporation has completed laboratory testing of silica sand from
the Firebag project as previously disclosed. Testing indicates the
viability as a potential frac sand for use in hydraulic fracking
for the oil and gas industry.
Richardson Project
(Granite and Dolomite)
Work continues on development of the Richardson Project.
- Detailed core logging and sampling has recently been completed
at Athabasca's Edmonton facility;
- Samples are next being sent to a major independent testing lab
in Calgary in order to verify the materials are suitable as
aggregate for use in concrete, asphalt and road base.
These 2014 drill holes coupled with additional drilling from the
same area in 2013 will provide the information necessary to
complete a National Instrument 43-101 (NI 43-101) resource estimate
for the Richardson granite and dolomite in fiscal 2014. Following
completion of the NI 43-101 report, the Corporation intends to
apply for a mineral lease on a portion of the Richardson Project
currently held by Athabasca under mineral permits; and
subsequently, the submission of a development application to
operate a hard rock quarry.
The complete financial statements for Athabasca for the three
months ended February 28, 2014 and Management's Discussion &
Analysis for the same period are available for viewing on the
Corporation's website at www.athabascaminerals.com and on SEDAR at
www.sedar.com.
About Athabasca Minerals
The Corporation is a resource company involved in the
management, exploration and development of aggregate projects.
These activities include contracts works, aggregate pit management,
aggregate production and sales from corporate-owned pits, new
aggregate development and acquisitions of sand and gravel
operations. The Corporation also has industrial mineral land
holdings for the purpose of locating and developing sources of
industrial minerals and aggregates essential to high growth
economic development.
Neither the TSX Venture nor its Regulation Services Provider
(as that term is defined in the policies of the TSX Venture)
accepts responsibility for the adequacy or accuracy of this
release.
This news release contains forward-looking statements that
involve risks and uncertainties. Forward-looking statements or
information are based on current expectations, estimates and
projections that involve a number of risks and uncertainties which
could cause actual results to differ materially from those
anticipated by the Corporation. The forward-looking statements or
information contained in this news release are made as of the date
hereof and the Corporation does not undertake any obligation to
update publicly or revise any forward-looking statements or
information, whether as a result of new information, future events
or otherwise, unless so required by applicable securities
laws.
The securities of Athabasca have not been, nor will be,
registered under the United States Securities Act of 1933, as
amended, and may not be offered or sold within the United States or
to, or for the account or benefit of, U.S. persons absent U.S.
registration or an applicable exemption from U.S. registration
requirements. This release does not constitute an offer for sale of
securities in the United States.
Athabasca Minerals Inc.Dean
Stuart403-517-2270dean@boardmarker.netwww.athabascaminerals.com
Aben Minerals (TSXV:ABM)
Historical Stock Chart
Von Dez 2024 bis Jan 2025
Aben Minerals (TSXV:ABM)
Historical Stock Chart
Von Jan 2024 bis Jan 2025