Alba
Mineral Resources Plc / EPIC: ALBA / Market: AIM / Sector:
Mining
31 May 2024
Alba Mineral Resources
Plc
("Alba"
or the "Company")
Update on Clogau Gold Mine
Operations & Lithium Option
Alba
Mineral Resources Plc (AIM: ALBA) is pleased to report on the
progress of ongoing works at the Company's 100% owned Clogau-St
David's Gold Mine in north Wales ("Clogau" or the "Mine"). The
Company also confirms an extension to the option period in respect
of its option over the Andover West Lithium Project in Western
Australia.
Key
Points - Clogau
· Processing of Waste Tip
o Further improvements made to onsite pilot processing
plant.
o All
of the Trench 3 fines (sampled grade 17g/t Au) have now been
processed.
· Underground Operations
o Dewatering ongoing, with water level remaining steady below
No. 4 Level despite recent heavy rains.
o Preparations ongoing for underground bulk sampling at primary
Llechfraith Target, with final development plan now in place and
roll-out of underground work plan in progress,
including:
o High-powered pump acquired for dewatering down to No.5
Level.
o Access to onsite historic explosives magazine
reinstated.
o Site
visit undertaken by Police as the issuer of explosives
certificate.
o Selection process for key contractors nearing
completion.
· Appointment of highly experienced Mine & Operations
Manager.
Key
Points - Andover West Lithium
· Option Period extended to 18 June 2024 to enable completion of
due diligence.
George Frangeskides, Executive Chairman,
commented:
"I
am pleased to be able to provide this update on ongoing operations
at Clogau. The team have been doing sterling work recently to
further improve plant efficiencies onsite, which should translate
into lower weights of concentrates having to be sent offsite,
greatly enhancing the overall economics for the processing and
production of gold at Clogau. The underground plan is also
progressing well, and in that regard I am delighted to welcome our
new Mine & Operations Manager, Kobus Byleveldt, to the team.
Kobus is highly experienced in all aspects of underground gold mine
planning, construction and development. He is a really strong
addition to our existing team and will be supporting our COO Mark
Austin as we roll out the next phases of work at
Clogau."
Details
Onsite Pilot Processing Plant and Waste Tip
Processing
Further improvements have been made
to the Company's onsite pilot processing plant at Clogau. In
particular, a milling stage has been added to the process circuit
and material is now being subjected to several passes over the
shaking and wave tables. These adaptations have succeeded in
greatly reducing the weight of concentrate which will have to be
sent offsite for final refining. This in turn is expected to
materially improve the overall economics of the production of gold
from Clogau.
As reported on 15 May 2024, in the
first phase of trenching over the Waste Tip a total of 33 tonnes of
fines were collected from four trenches. The processing and
refining of samples from each of those trenches resulted in Trench
3 returning the highest-grade results, with a back-calculated head
grade of 17.22 g/t or 0.55 oz/t. All of Trench 3 has now been
processed at the Company's onsite processing plant. The gold
content of the Trench 3 concentrates will only be known once those
concentrates have been refined at the Company's offsite
refiner.
Underground Bulk Sampling of the Llechfraith
Target
Preparations are ongoing for the
underground bulk sampling of the Company's primary gold target
within the Mine, the Llechfraith Target. A final development plan
is now in place for taking bulk samples from two zones (see Figure
1). The forward work plan includes the following aspects, among
others:
-
Completion of dewatering down to No. 5
Level. At present, the water level within the Lower
Llechfraith workings remains steady below No. 4 level, despite
recent heavy rains. A high-powered pump has recently been acquired
in order to facilitate the completion of dewatering down to No.5
Level and, thereafter, in order to maintain the water level below
No. 5 Level.
-
Implementation of appropriate measures in relation
to the handling and use of explosives. Access to the historic
explosives magazine close to the Mine has been reinstated and a
site visit undertaken by the Police as the issuer of the necessary
explosives certificate.
-
The selection of specialist contractors is nearing
completion, notably contractors who will undertake: the No. 5 Level
safety works; the installation of ventilation, compressed air and
water pipes to the lower levels; the installation of a 5-tonne
winch system from No.5 Level to the top of the Llechfraith Shaft;
the supply and use of explosives; and the bulk sampling operation
itself (i.e., drilling, blasting and mucking out).
Appointment of Highly Experienced Mine & Operations
Manager
To assist in this next stage of
development at Clogau, the Company is delighted to confirm the
appointment of Kobus Byleveldt as Mine & Operations Manager at
Clogau. Mr Byleveldt has more than 26 years of mining and
management experience within the gold mining sector in South Africa
and Scotland, including in mine planning, construction and
development. His most recent role was as Mine Manager (for
approximately 2.5 years) at the Cononish Mine in Scotland, where he
also acted as Senior Production Supervisor and Process Plant
Manager.
Figure 1: Proposed bulk
sampling works from No.5 Level of the Lower Llechfraith workings,
involving the installation of two inclined raises (in red) between
Nos. 4 and 5 Levels.
Andover West Lithium Project
Further to the announcement of 24
April 2024 that the Company had secured an option to acquire an
initial 50% interest in the lithium rights over the highly
prospective Andover West Lithium Project in the West Pilbara,
Western Australia, the parties have agreed to extend the option
period to 18 June 2024 to enable the Company to complete its due
diligence.
This announcement contains
inside information for the purposes of the UK Market Abuse
Regulation and the Directors of the Company are responsible for the
release of this announcement.
Forward Looking
Statements
This announcement contains
forward-looking statements relating to expected or anticipated
future events and anticipated results that are forward-looking in
nature and, as a result, are subject to certain risks and
uncertainties, such as general economic, market and business
conditions, competition for qualified staff, the regulatory process
and actions, technical issues, new legislation, uncertainties
resulting from potential delays or changes in plans, uncertainties
resulting from working in a new political jurisdiction,
uncertainties regarding the results of exploration, uncertainties
regarding the timing and granting of prospecting rights,
uncertainties regarding the timing and granting of regulatory and
other third party consents and approvals, uncertainties regarding
the Company's or any third party's ability to execute and implement
future plans, and the occurrence of unexpected events. Actual
results achieved may vary from the information provided herein as a
result of numerous known and unknown risks and uncertainties and
other factors.
**ENDS**
For further information, please
visit www.albamineralresources.com or
contact:
Alba Mineral Resources
plc
George Frangeskides, Executive
Chairman
|
+44 20
3950 0725
|
SPARK Advisory Partners Limited
(Nomad)
Andrew Emmott
|
+44 20
3368 3555
|
CMC Markets plc (Broker)
Thomas Smith / Douglas
Crippen
|
+44 20
3003 8632
|
Alba's
Projects & Investments
|
Projects Operated by Alba
|
Location
|
Ownership
|
Clogau (gold)
|
Wales
|
100%
|
Dolgellau Gold Exploration
(gold)
|
Wales
|
100%
|
Gwynfynydd (gold)
|
Wales
|
100%
|
Investments Held by Alba
|
Location
|
Ownership
|
GreenRoc Mining Plc
(mining)
|
Greenland
|
37.49%
|
Horse Hill (oil)
|
England
|
11.765%
|