Victoria Gold Corp. (TSX.V-VIT) (“Victoria” or the “Company”) is
pleased to provide an end of May update on the Eagle Gold Mine.
Highlights:
- Construction of the mine is 95% complete;
- Greater than 1.4 million hours have been worked without
a Lost Time Incident;
- Open Pit benches have been established and more than
1.3 million tonnes mined;
- Primary Crusher, conveying systems, and ADR are being
commissioned;
- Secondary-Tertiary Crushing Facility is near
completion;
- The 69kV powerline from the Yukon grid is
energized;
- 200 employees have been hired and 50% are
Yukoners.
Upcoming key milestones:
- Ore to leach pad – July
- First gold pour – September
"Construction of the Eagle Gold Mine is nearing
completion ahead of schedule and the operations team is ready to
take advantage by advancing additional ore delivery to the heap
leach pad in 2019,” stated John McConnell, President & CEO.
“With gold approaching an all-time high in Canadian dollar terms,
70% of our costs in Canadian dollars, and first gold production in
September, Victoria is perfectly timed to become Canada’s next gold
producer.”
Current activities on site are focused on
completing remaining mechanical, electrical and instrumentation
installations at the Secondary/Tertiary Crushing Facility and the
overland conveyor. Commissioning activities are well advanced at
the Primary Crusher, conveying systems, and Gold Recovery Plant.
Photographs and videos of all these facilities can be viewed on the
Company’s web-site (www.vitgoldcorp.com).
Click to view Early June Construction Progress
video: https://vitgoldcorp.com/projects/development/eagle-gold-project/eagle-gold-videos/videos/early-june-2019/
Construction
Site Infrastructure, including Grid
Power
The 45 kilometer 69kV powerline from the Yukon
electrical grid and the on-site 13.8 kV power distribution systems
are energized. All major facilities are operating on grid power.
All water management infrastructure, including
sediment control ponds, water management ditches, spillways, and
event ponds are installed and operable.
With construction nearing completion, portions
of the accommodation camp are being progressively decommissioned in
anticipation of the lower site population during production. Site
offices are being reconfigured and refurbished to suit the
requirements of operations.
Crushing & Conveying
The Primary Crusher MSE retaining wall is now
complete and loaded commissioning of the Primary Crusher took place
in late May, approximately one month ahead of schedule. Over the
coming month, Eagle ore will be crushed and stockpiled to support
commissioning of the Secondary/Tertiary Crushing Facility in late
June.
The Secondary & Tertiary Crushing Facility
structural steel and building envelope are now 100% complete.
Mechanical progress is nearing completion with all equipment and
drives installed and the focus is now on electrical completion,
instrumentation testing, and programming. Mechanical and electrical
progress have reached 95% and 80%, respectively.
The overland conveyor, which transports the
crushed ore 1.4 kilometers across the valley to the Heap Leach
Facility (“HLF”), is now operational, well ahead of schedule. The
conveyor is currently being utilized to transport crushed gravels
to support construction of the HLF solution collection piping
system.
Heap Leach Pad & Gold Recovery
Plant
The four-layer liner system and solution piping
for the sump of the heap leach pad was complete in late 2018. The
event pond is fully lined and phase 1 of the heap leach pad above
the sump is well advanced which provides sufficient ore capacity
through 2020 and into 2021. The Gold Recovery Plant is fully
constructed and commissioning is approximately 75% complete.
Commissioning
Commissioning activities are well underway. A
total of 46 of 88 subsystems have been turned over from
construction to commissioning. The operations and maintenance teams
are now fully engaged within the commissioning plan to support
training and maintenance planning of the process facilities.
Overall commissioning progress is approximately 30%.
Pre-Production Mining
Development of the main haul road into the open
pit is complete and bench development is well advanced. To date,
pre-production mining has moved approximately 1.3 of 1.7 million
tonnes of material well ahead of schedule and below budgeted
costs.
Operations
Victoria continues to advance recruitment of the
operations team. The operations management team and key supervisors
are in place. The remaining operations team are being on boarded
with a current head count of approximately 181 operations
personnel. Approximately 48% of the current operations staff are
Yukon residents including several citizens from the First Nation of
Nacho Nyak Dun (“FNNND”), the Traditional Territory in which we
operate. We are targeting at least 50% Yukon residents to fill the
approximate 260 employees scheduled to be on board by the end of
2019.
All major contract and supply agreements are in
place or are in final stages of completion. A significant number of
the vendors awarded contract or supply agreements have partnership
arrangements with the FNNND Development Corp.
“With a steadfast focus on all of our
stakeholders including shareholders, employees, the local
community, and Yukon Territory, we look forward to a strong start
of a long, responsible and profitable operation,” stated John
McConnell, President & CEO.
Schedule to First Gold Pour
The original schedule had the first ore delivery
to the heap leach pad in August 2019. The Company currently
believes the team can beat this schedule by nearly one month, with
first ore reporting to the heap leach pad during the first half of
July 2019. In doing so, we are currently targeting a first gold
pour in September 2019. With the acceleration of the construction
schedule, over 3 million tonnes of ore will be delivered to the
heap leach pad by 2019 year end.
Qualified PersonThe technical
content of this news release has been reviewed and approved by
Anthony (Tony) George, P.Eng., as the Qualified Person. For
additional information relating to the Property, refer to the
technical report entitled “NI 43-101 Feasibility Study Technical
Report for the Eagle Gold Project, Yukon Territory, Canada”, with
an effective date of September 12, 2016, which is available on the
Company’s profile at www.sedar.com.
About the Dublin Gulch
PropertyVictoria Gold's 100%-owned Dublin Gulch gold
property is situated in central Yukon Territory, Canada,
approximately 375 kilometers north of the capital city of
Whitehorse, and approximately 85 kilometers from the town of Mayo.
The Property is accessible by road year-round, and is located
within Yukon Energy's electrical grid.
The Property covers an area of approximately 555
square kilometers, and is the site of the Company's Eagle Gold
Deposit. The Eagle Gold Mine is under construction and is expected
to be Yukon's next operating gold mine. The Eagle and Olive
deposits, include Proven and Probable Reserves of 2.7 million
ounces of gold from 123 million tonnes of ore with a grade of 0.67
grams of gold per tonne, as outlined in a National Instrument
43-101 feasibility study entitled Report for the Eagle Gold Project
and dated October 26, 2016. The NI 43-101 Mineral Resource for the
Eagle and Olive deposits has been estimated, as at December 5,
2018, to host 208 million tonnes averaging 0.66 grams of gold per
tonne, containing 4.4 million ounces of gold in the "Measured and
Indicated" category, inclusive of Proven and Probable Reserves, and
a further 20 million tonnes averaging 0.64 grams of gold per tonne,
containing 0.4 million ounces of gold in the "Inferred"
category.
Cautionary Language and Forward-Looking
StatementsNeither the TSX Venture Exchange, nor its
Regulation Services Provider accepts responsibility for the
adequacy or accuracy of this release. This press release includes
certain statements that may be deemed "forward-looking statements".
All statements in this discussion, other than statements of
historical facts, that address future exploration drilling,
exploration activities, anticipated metal production, internal rate
of return, estimated ore grades, commencement of production
estimates and projected exploration and capital expenditures
(including costs and other estimates upon which such projections
are based) and events or developments that the Company expects, are
forward-looking statements. Although the Company believes the
expectations expressed in such forward-looking statements are based
on reasonable assumptions, such statements are not guarantees of
future performance and actual results or developments may differ
materially from those in forward-looking statements. Factors that
could cause actual results to differ materially from those in
forward-looking statements include metal prices, exploration
successes, continued availability of capital and financing, and
general economic, market or business conditions. Accordingly,
readers should not place undue reliance on forward-looking
statements.
For Further Information Contact:John McConnell
President & CEO Victoria Gold Corp Tel: 416-866-8800 Fax:
416-866-8801
Victoria Gold (TSXV:VIT)
Historical Stock Chart
Von Dez 2024 bis Jan 2025
Victoria Gold (TSXV:VIT)
Historical Stock Chart
Von Jan 2024 bis Jan 2025