12 December 2024
Adriatic
Metals PLC
("Adriatic Metals" or the "Company")
OPERATIONS & FINANCING UPDATE
Highlights:
·
Rupice Mine
is operating from two active stopes, with the second stoping level
entering production in early December.
·
Vares Processing Plant
is operating 24/7 and recoveries are steadily improving.
·
Total ore mined in 2024 to the
end of November reached 129,194 tonnes ('t'), with approximately
40,000t expected in December.
·
Guidance for 2025 remains
unchanged at 750,000 - 800,000t of ore mined.
·
Commercial production expected
to be achieved in December and continue into January 2025.
·
Construction of the Veovaca
Tailings Storage Facility ('Veovaca TSF') is progressing well, with
first tailings disposal to take place in January 2025 with no
impact on production.
·
OMF Fund III [F] Ltd ('Orion')
has agreed to reschedule the first quarterly debt repayment of
approximately $19m from 31 December 2024 to 31 March
2025.
·
Adriatic has signed a term
sheet for a $25m concentrate prepayment arrangement with Trafigura
at competitive terms and expects to close the transaction by year
end.
·
As at 30 November 2024,
Adriatic held a cash balance of $23m and approximately $8m in
receivables and concentrate inventory.
Laura Tyler, Managing Director & CEO of Adriatic,
commented:
"I
am pleased to announce that we are now mining a second stope
underground at Rupice Mine and that the Vares
Processing Plant is operating 24/7. Q4
2024 will be a record quarter of production at the Vares Silver
Operation and we are confident commercial production levels will be
reached in the coming weeks.
We
are also pleased to have bolstered our cash position through a
concentrate prepayment arrangement with Trafigura. Additionally, we
would like to express our gratitude to our long-term partner, Orion
Mine Finance, who have agreed to reschedule our first quarterly
debt repayment to the end of March 2025."
Adriatic Metals PLC (ASX:ADT,
LSE:ADT1, OTCQX:ADMLF) ("Adriatic" or the "Company") is pleased to
provide an update on production activities at the Vares Silver
Operation in Bosnia and Herzegovina.
Mining
In October, development rates at
Rupice Mine were temporarily impacted by significant rainfall
following the severe storm on 3 October, which led to increased
pumping requirements. Additionally, mining operations were hindered
by a temporary shortage of ground support bolts which has since
been resolved, with development rates exceeding 300m in
November.
Total ore mined in 2024 to the end
of November was 129,194t. In December, mining commenced on two active stopes on the
1075-1050 and on the 950-925 levels, with approximately 40,000t
expected to be mined in the month.
Figure 1: YTD Ore Mined and
Development Metres by Quarter
Processing
The stockpile at Rupice currently
contains approximately 64,000 tonnes at 259g/t Ag, 2.4g/t Au, 6.2%
Zn, 4.2% Pb, which will allow for blended plant feed closer to
design head grades.
In December the Vares Processing
Plant moved from operating five days a week to 24/7 operations and
recoveries are steadily improving. The Company expects to be
operating above 75% of nominal plant throughput in the coming
weeks, with commercial production being declared when this level
has been sustained over a 21-day continuous period.
Production, grades and recoveries
year-to-date:
|
Q2
|
Q3
|
Oct-Nov
|
Ore milled (t)
|
9,211
|
19,308
|
35,012
|
Head grade - Ag (g/t)
|
96
|
239
|
257
|
Head grade - Au (g/t)
|
0.3
|
2.6
|
2.7
|
Head grade - Zn (%)
|
2.2
|
8.6
|
7.8
|
Head grade - Pb (%)
|
1.6
|
5.6
|
5.0
|
Recoveries - Ag (%)
|
73
|
85
|
95
|
Recoveries - Au (%)
|
57
|
62
|
73
|
Recoveries - Zn (%)
|
32
|
56
|
64
|
Recoveries - Pb (%)
|
57
|
55
|
69
|
Ag/Pb concentrate (t)
|
246
|
1,440
|
2,943
|
Grade - Ag (g/t)
|
2,292
|
2,131
|
2,317
|
Grade - Au (g/t)
|
4.0
|
13.6
|
13.8
|
Grade - Pb (%)
|
33.3
|
41.3
|
41.4
|
Payability - Ag (%)
|
95
|
95
|
95
|
Payability - Au (%)
|
70
|
70
|
70
|
Payability - Pb (%)
|
95
|
95
|
95
|
Zn concentrate (t)
|
139
|
2,095
|
3,793
|
Grade - Ag (g/t)
|
593
|
411
|
446
|
Grade - Au (g/t)
|
5.0
|
5.8
|
7.3
|
Grade - Zn (%)
|
45.6
|
44.4
|
46.4
|
Payability - Ag (%)
|
70
|
70
|
70
|
Payability - Au (%)
|
70
|
70
|
70
|
Payability - Zn (%)
|
85
|
85
|
85
|
* Recoveries included are only into
payable concentrates
Figure 2: YTD Silver
Equivalent Contained Metal Production by Quarter
* Silver equivalent (AgEq) assumes
$25/oz Ag, $2,000/oz Au, $2,500/t Zn, $2,000/t Pb, $6,500/t Cu,
$6,500/t Sb as per the July 2023 Mineral Resource
estimate
Tailings
On 24 October all permits for Phase
I of the Veovaca Tailings Storage Facility ('Veovaca TSF') were
received from the Federal Ministry of Energy, Mining, and Industry
('FMERI') of Bosnia and Herzegovina. These permits include
Environmental, Water, Full Design and Construction Permits.
Construction is underway and the first tailings disposal at the
Veovaca TSF is planned for early January 2024, after some minor
delays caused by winter conditions. The Veovaca TSF will be
constructed under GISTM ('Global Industry Standard on Tailings
Management') standards and will be constructed in two phases. Phase
I will have the capacity to receive tailings for approximately 4-5
years of production and in total the Veovaca TSF will be
operational for over 10 years of production.
The current operating temporary TSF
at the Vares Processing Plant has a maximum capacity of
approximately 133,000 tonnes, which will allow tailings deposition
into mid-Q1 2025 and will ensure no impact on
production.
Finance
The Company ended November with $23m
cash and approximately $8m in receivables and concentrate
inventory.
Orion has agreed to reschedule the
first quarterly debt repayment of approximately $19m from 31
December 2024 to 31 March 2025, with nine quarterly repayments
thereafter.
Adriatic has also signed a term
sheet for a $25m concentrate prepayment arrangement with Trafigura,
an existing offtaker, at competitive terms and a lower interest
rate than the Orion facility. The prepayment includes the delivery
of zinc and lead-silver concentrates at market prices over a
12-month period. The prepaid amount is unsecured, includes a
3-month grace period and will be paid down in line with deliveries
over the final nine months of the arrangement.
The transaction includes extended
offtake agreements for approximately 100kt of zinc and lead-silver
concentrates into 2027, with increased payabilities and lower
treatment charges compared to existing offtakes. The Company
expects to close the transaction by year end, providing additional
liquidity during ramp-up.
Due to the rescheduled debt
repayments and prepayment arrangement with Trafigura, Orion and the
Company have cancelled the additional Orion loan facility of $25m
that was previously announced on 22 April 2024.
-ends-
Authorised by Laura Tyler, Managing
Director & CEO of Adriatic Metals
For further information please
visit: www.adriaticmetals.com;
email: info@adriaticmetals.com,
@AdriaticMetals
on Twitter; or contact:
Adriatic Metals PLC
|
|
Klara Kaczmarek
GM - Corporate
Development
|
Tel: +44 (0) 7859 048228
Klara.kaczmarek@adriaticmetals.com
|
|
|
Burson Buchanan
|
Tel: +44 (0) 20 7466 5000
|
Bobby Morse / Christopher
Jones
|
adriatic@buchanan.uk.com
|
Morgans Corporate Limited
|
|
Rob Douglas / Sam Warriner / Mitch
Duffy
|
Tel: +61 7 3334 4888
|
|
|
RBC
Capital Markets
|
|
Farid Dadashev / James Agnew / Jamil
Miah
|
Tel: +44 (0) 20 7653 4000
|
|
|
Stifel Nicolaus Europe Limited
|
Ashton Clanfield / Callum Stewart /
Varun Talwar
|
Tel: +44 (0) 20 7710 7600
|
|
|
Morrow Sodali
|
|
Cameron Gilenko
|
Tel: +61 466 984 953
|
ABOUT ADRIATIC METALS
Adriatic Metals Plc (ASX:ADT,
LSE:ADT1, OTCQX:ADMLF) is a precious and base metals developer that
is advancing the world-class Vares Silver Operation in Bosnia &
Herzegovina, as well as the Raska Zinc-Silver Project in Serbia.
First concentrate production took place in February 2024 and the
Vares Silver Operation is fully funded to nameplate production,
which is expected in Q4 2024. Concurrent with ongoing operational
activities, the Company continues to explore across its highly
prospective 44km2 concession package.
MARKET ABUSE REGULATION
DISCLOSURE
The information contained within
this announcement is deemed by the Company (LEI:
549300OHAH2GL1DP0L61) to constitute inside information for the
purpose of Article 7 of EU Market Abuse Regulation (EU) No.
596/2014 as it forms part of UK domestic law by virtue of the
European Union (Withdrawal) ACT 2018, as amended. The person
responsible for arranging and authorising the release of this
announcement on behalf of the Company is Laura Tyler, Managing
Director & CEO.