Orezone Gold Corporation (TSX: ORE, OTCQX: ORZCF)
(“Orezone” or “Company”) reported its operational and financial
results for the three and six months ended June 30, 2023. The
consolidated financial statements and Management’s Discussion and
Analysis are available at www.orezone.com and on the Company’s
profile on SEDAR+ at www.sedarplus.ca. The Company will host a
conference call and webcast on August 10, 2023 commencing at 8:00am
PDT to discuss the Company’s second quarter results. Additional
details are provided at the end of this press release.
Patrick Downey, President and CEO, commented
“The Bomboré mine delivered another solid quarter of gold
production which allowed the Company to reduce its debt by a
further $19.1 million while maintaining a healthy cash balance.
During the quarter, the operations team successfully completed
several mill maintenance tasks including a full mill re-line with a
new liner design that will increase liner life going forward.
Processed head grades were lower than modelled in the first half of
2023 as we encountered a greater intensity of historical artisanal
depletion in certain near-surface higher-grade ore zones mined. As
a result, we now forecast that 2023 gold production will trend
towards the low-end of our guidance range with a modest increase in
AISC guidance.
With our value enhancing initiatives, we are
advancing fieldwork to connect to Burkina Faso’s national grid and
remain on track to receive grid power before year-end. Once
completed, this will significantly reduce our cost for power which
is currently being generated using on-site diesel gensets rented
from a third party. In addition, our Phase II hard rock expansion
feasibility study and LOM plan update is nearing completion with
release of study results planned for the end of September.”
SECOND QUARTER 2023
HIGHLIGHTS
Operational
- Produced 35,482 gold oz
- Sold 33,608 gold oz at an average
realized price of $1,970 per oz
- AISC¹ of $1,109 per gold oz
sold
- Zero lost-time injuries with
1,037,000 personnel hours worked
Financial
- Revenue of $66.4 million
- Earnings from mine operations of
$27.5 million
- Net income and net income per share
(basic) attributable to Orezone shareholders of $11.4 million and
$0.03, respectively
- Adjusted earnings¹ and
adjusted earnings per share¹ (basic) attributable to Orezone
shareholders of $11.2 million and $0.03, respectively
- Cash flow from operations before
changes in non-cash working capital of $25.2 million ($20.2 million
after changes in non-cash working capital)
- Free cash flow¹ of $8.0
million
- Principal repayment of $19.1
million under the Coris Bank senior debt facility
- Cash of $32.3 million at June 30,
2023
¹ Non-IFRS measures. See “Non-IFRS Measures”
section below for additional details.
PRODUCTION AND FINANCIAL
SUMMARY
(All mine site figures are on a 100% basis) |
|
Q2-2023 |
Q1-2023 |
H1-2023 |
Operating Performance |
|
|
|
|
Gold production |
oz |
35,482 |
41,301 |
76,783 |
Gold sales |
oz |
33,608 |
43,139 |
76,747 |
Average realized gold price |
$/oz |
1,970 |
1,892 |
1,926 |
Cash costs per gold ounce sold¹ |
$/oz |
924 |
799 |
854 |
All-in sustaining costs¹ (“AISC”) per gold ounce sold |
$/oz |
1,109 |
926 |
1,006 |
Financial Performance |
|
|
|
|
Revenue |
$000s |
66,396 |
81,712 |
148,108 |
Earnings from mine operations |
$000s |
27,490 |
39,670 |
67,160 |
Net income attributable to shareholders of Orezone |
$000s |
11,380 |
22,560 |
33,940 |
Net income per common share attributable to shareholders of
Orezone: |
|
|
|
|
Basic |
$ |
0.03 |
0.07 |
0.10 |
Diluted |
$ |
0.03 |
0.06 |
0.09 |
Adjusted EBITDA¹ |
$000s |
31,526 |
42,645 |
74,171 |
Adjusted earnings attributable to shareholders of Orezone¹ |
$000s |
11,236 |
24,574 |
35,810 |
Adjusted earnings per share attributable to shareholders of
Orezone¹ |
$ |
0.03 |
0.07 |
0.10 |
Cash and Cash Flow Data |
|
|
|
|
Operating cash flow before changes in working capital |
$000s |
25,228 |
41,137 |
66,365 |
Operating cash flow |
$000s |
20,155 |
38,926 |
59,081 |
Free cash flow¹ |
$000s |
8,016 |
31,498 |
39,514 |
Cash, end of period |
$000s |
32,309 |
45,172 |
32,309 |
¹ Cash costs, AISC, Adjusted EBITDA, Adjusted
earnings, Adjusted earnings per share, and Free cash flow are
non-IFRS measures. See “Non-IFRS Measures” section below for
additional information.
The Company poured first gold on September 10,
2022 and declared commercial production on December 1, 2022 at its
Bomboré mine. As a result, comparative figures for the
corresponding quarter and year-to-date period in the prior year
have not been presented as they are not meaningful as the Bomboré
mine was under construction during this period. Operating and
financial performance in the current quarter have been compared
against Q1-2023 to highlight quarter-over-quarter movements in
performance.
2023 Guidance Update
The Company previously issued 2023 gold
production guidance of between 140,000 to 155,000 oz with AISC per
gold ounce sold in the range of $1,010 to $1,110. The Company is
now forecasting 2023 gold production at the bottom end of its
guidance range. Greater-than-anticipated artisanal depletion has
been encountered in certain high-grade zones mined to the end of
H1-2023 which has resulted in lower-than-modelled ore grades being
delivered to the process plant. Significant artisanal workings were
encountered in H1-2023 but evidence of artisanal activity has
diminished as the Company mines towards lower pit benches. As a
result, the Company expects historical artisanal activity to have
less influence on the modelled mined grades in H2-2023. In
addition, the mining contractor is currently approximately 10%
behind plan in terms of material movement which has delayed access
to areas of higher-grade ore. A second mining contractor, currently
on-site assisting with the expansion of the tailings storage
facility, has been hired on a temporary basis to improve mining
volumes and to catch-up to plan by the end of 2023.
As planned, the Company has processed its last
remaining stockpiles of higher-grade ore accumulated during
construction in June 2023, and therefore, gold production in
H2-2023 is expected to decline from production levels realized in
H1-2023, offsetting the benefits of greater mining volumes and
expected lower artisanal depletion.
AISC per ounce sold for 2023 is now revised
upwards to $1,100 - $1,180, up from the previous guidance range of
$1,010 - $1,110. The cost increase is driven mainly by the lower
forecasted gold production and head grades. Other contributing
factors include persistently high local diesel prices which affect
both mining costs and on-site power generation, a stronger XOF
currency, and additional government royalties from a
higher-than-budgeted realized gold price.
BOMBORÉ GOLD MINE (100% BASIS) –
OPERATING HIGHLIGHTS
|
|
Q2-2023 |
Q1-2023 |
H1-2023 |
Safety |
|
|
|
|
Lost-time injuries frequency rate (LTIFR) |
per 1M hours |
0.00 |
0.00 |
0.00 |
Personnel-hours worked |
000s hours |
1,037 |
928 |
1,965 |
Mining Physicals |
|
|
|
|
Ore tonnes mined |
tonnes |
1,927,753 |
2,205,056 |
4,132,809 |
Waste tonnes mined |
tonnes |
3,152,264 |
2,382,135 |
5,534,399 |
Total tonnes mined |
tonnes |
5,080,017 |
4,587,191 |
9,667,208 |
Strip ratio |
waste:ore |
1.64 |
1.08 |
1.34 |
Processing Physicals |
|
|
|
|
Ore tonnes milled |
tonnes |
1,400,160 |
1,445,693 |
2,845,853 |
Head grade milled |
Au g/t |
0.87 |
0.96 |
0.92 |
Recovery rate |
% |
91.1 |
92.2 |
91.7 |
Gold produced |
oz |
35,482 |
41,301 |
76,783 |
Unit Cash Cost |
|
|
|
|
Mining cost per tonne |
$/tonne |
2.86 |
2.91 |
2.89 |
Mining cost per ore tonne processed |
$/tonne |
6.46 |
6.51 |
6.49 |
Processing cost |
$/tonne |
10.72 |
9.21 |
9.95 |
Site general and admin (“G&A”) cost |
$/tonne |
3.73 |
3.23 |
3.47 |
Cash cost per ore tonne processed |
$/tonne |
20.91 |
18.95 |
19.91 |
Cash Costs and AISC Details |
|
|
|
|
Mining cost (net of stockpile movements) |
$000s |
9,050 |
9,417 |
18,467 |
Processing cost |
$000s |
15,006 |
13,322 |
28,328 |
Site G&A cost |
$000s |
5,217 |
4,667 |
9,883 |
Refining and transport cost |
$000s |
164 |
148 |
312 |
Government royalty cost |
$000s |
3,930 |
4,912 |
8,842 |
Gold inventory movements |
$000s |
(2,299) |
2,019 |
(280) |
Cash costs¹on a sales basis |
$000s |
31,068 |
34,485 |
65,552 |
Sustaining capital |
$000s |
4,308 |
3,530 |
7,838 |
Sustaining leases |
$000s |
- |
187 |
187 |
Corporate G&A cost |
$000s |
1,883 |
1,731 |
3,614 |
All-In Sustaining Costs¹on a sales
basis |
$000s |
37,259 |
39,933 |
77,192 |
Gold sold |
oz |
33,608 |
43,139 |
76,747 |
Cash costs per gold ounce sold¹ |
$/oz |
924 |
799 |
854 |
All-In Sustaining Costs per gold ounce sold¹ |
$/oz |
1,109 |
926 |
1,006 |
¹ Non-IFRS measure. See “Non-IFRS Measures”
section for additional details.
Bomboré Production Results
Gold production in Q2-2023 was 35,482 oz, a
decrease of 14% from the 41,301 oz produced in Q1-2023. The drop in
gold production is attributable to decreases in head grades of 9%,
plant throughput of 3%, and plant recoveries of 2% as compared to
the prior quarter.
Head grades were lower in Q2 due to mine
sequencing, greater prevalence of historical artisanal activity in
areas mined, and the mill feed prioritization of better grade ore
stockpiles in Q1.
Plant throughput declined marginally from Q1
which exceeded nameplate by approximately 13%. Lower plant
availability in Q2 was the result of routine maintenance for the
installation of newly designed mill liners in April 2023 and the
replacement of worn shafts in the front-end mineral sizer in late
May 2023. All major planned maintenance is now complete for 2023
with plant throughput expected to trend upwards again towards
record levels.
As mining deepens in certain pits, the quantity
of transition ore is starting to increase. The presence of
transition ore results in slightly lower metallurgical recovery and
the generation of additional ball mill scats that must be
recirculated through the circuit to achieve the required grind size
fraction. Consequently, plant recoveries were slightly lower in Q2
as compared to Q1.
To improve the treatment efficiency of scats and
to crush hard oversize transition material, the Company has
acquired a used mobile crushing system (a jaw crusher and a cone
crusher) in good condition to pre-treat transition ore ahead of the
ROM dump pocket and to crush scats prior to recirculation. The
system is currently in transit from overseas and is scheduled to be
placed into operations by the end of October 2023. This system will
also provide additional process plant operational flexibility once
the future Phase II Hard Rock plant expansion is in operation.
Bomboré Operating Costs
AISC per gold ounce sold in Q2-2023 was $1,109,
an increase of 20% from the AISC per gold ounce sold of $926 in
Q1-2023. The increase in AISC was mainly driven by a combination of
lower head grades, plant throughput, and recovery as explained
above, higher unit operating costs, and timing of sustaining
capital. Cash cost per ore tonne processed increased by 10% from
$18.95 per tonne in Q1 to $20.91 per tonne in Q2 due primarily to
lower plant throughput and higher processing costs for maintenance
from the mill re-line and sizer shaft change-outs, and greater
consumption of lime, grinding media, and power to treat a larger
percentage of transition ore and scats. Site G&A also increased
modestly from the planned spending increase on site security
improvements including additional reinforcements of highly-trained
guards and a greater frequency of patrols on and around the mining
permit.
Bomboré Growth Capital
Projects
Grid Power Connection
The project to connect Bomboré to Burkina Faso’s
national grid continues to advance and remains on schedule for
completion before the end of the 2023 year.
All long lead equipment orders are in
fabrication with certain deliveries already received at site. The
main installation contractors have mobilized and fieldwork has
commenced for the switching station, the main on-site substation,
and the transmission line towers. SONABEL, Burkina Faso’s
state-owned electricity company, has approved the required drawings
and designs for the powerline and substations while land
compensation under the direction of SONABEL and ground clearing for
the transmission line corridor are essentially complete. Pouring of
concrete foundations for the 56 transmission towers are on-going
with the first shipment of transmission towers and stringing gear
expected to arrive in August 2023. The Company is reviewing
opportunities to accelerate or to mitigate risks to schedule. The
Company has also initiated discussions to formalize a power
purchase agreement with SONABEL following the memorandum of
understanding signed between the parties earlier in the year.
Resettlement Action Plan (“RAP”) Phases II and
III
RAP Phases II and III involve the construction
of four new resettlement villages (MV3, MV2, BV2, and BV1). The
Company has sequenced MV3 as the first village to construct in
order to gain access to mining areas that are currently
contemplated in the 2024 mine plan. MV3 is the largest of the
resettlement villages and requires the erection of over 1,200
private homes and public structures.
RAP construction is currently behind schedule as
the construction start for the MV3 village was delayed for two
months as communities conducted sacred ceremonies for the new
resettlement grounds. The Company has engaged several local
contractors to complete homes on distinct lots within the MV3 site.
To improve the pace of construction, the Company has commenced the
award of work to additional contractors along with the recruitment
of a small owner’s team to assist with procurement of building
material and site construction activities.
RAP compensation for displaced households began
in late Q2-2023 and has continued into Q3-2023.
2023 Feasibility Study (“2023 FS”)
Update for the Phase II Expansion
The 2019 feasibility study (“2019 FS”)
contemplated the construction of a 2.2M tonnes per annum (“tpa”)
hard rock facility which would commence production in the third
year of oxide operations. Based on the mineral reserves outlined in
the 2019 FS, the overall plant capacity was to remain at a nominal
5.2Mtpa, comprising of 3.0Mtpa of oxides and 2.2Mtpa of hard rock,
resulting in an average gold production profile of 134K oz per year
for the first ten years of commercial operations.
Subsequent to the 2019 FS, over 150,000 m of
drilling has been completed leading to the discovery of the near
surface P17NE deposit and extensions of other known higher grade
hard rock zones within the main Bomboré deposit. Results of
drilling undertaken in 2022 are expected to successfully convert
Inferred resources of higher grade hard rock material into the
Measured and Indicated categories.
The Company expects the new hard rock expansion
will be sized as a 4.4Mtpa standalone circuit to operate
independently and in parallel to the existing 5.7Mtpa oxide
circuit, a notable increase to the 5.2Mtpa combined circuit in the
2019 FS. The Company has chosen to expand the circuit size to
10.1Mtpa as it believes recent drilling successes have demonstrated
that the Bomboré mine is capable of supporting a larger annual
operation. The Bomboré deposit remains open to further extensions
and potential new discoveries from future drilling.
Metallurgical test work is complete and confirms
more rapid leach kinetics than those contemplated in the 2019 FS,
leading to a significant reduction in required leach time from the
42 hours shown in the 2019 FS to the estimated 24 hours to be used
in plant design for the 2023 FS. Flowsheet development is also
complete and will follow the same design (e.g. carbon-in-leach and
elution circuits) of the current operations where feasible to
standardize equipment and processes. Firm quotes have been received
for the SAG mill, which is on the critical path, and budgetary
quotes for all other major equipment are in hand and under
evaluation and will form the basis for the expansion capital
estimate. Modelling of the new mineral resource estimate has
concluded with modelling of the new mineral reserve estimate
well-advanced. The Company remains on track to release the study
results by the end of Q3-2023.
The Company has held early discussions with its
senior lender, Coris Bank, about their participation in this future
Phase II Expansion. Coris Bank has indicated they are supportive of
this expansion and the Company intends to launch more formal
discussions with Coris Bank as it draws closer to completing the
2023 FS when information about the new expansion economics and
capital requirements are better known.
NON-IFRS MEASURES
The Company has included certain terms or
performance measures commonly used in the mining industry that is
not defined under IFRS, including “cash costs”, “AISC”, “EBITDA”,
“adjusted EBITDA”, “adjusted earnings”, “adjusted earnings per
share”, and “free cash flow”. Non-IFRS measures do not have any
standardized meaning prescribed under IFRS, and therefore, they may
not be comparable to similar measures presented by other companies.
The Company uses such measures to provide additional information
and they should not be considered in isolation or as a substitute
for measures of performance prepared in accordance with IFRS. For a
complete description of how the Company calculates such measures
and reconciliation of certain measures to IFRS terms, refer to
“Non-IFRS Measures” in the Management’s Discussion and Analysis for
the three and six months ended June 30, 2023 which is incorporated
by reference herein.
CONFERENCE CALL AND WEBCAST
Orezone will host a conference call and audio
webcast to discuss second quarter 2023 results on Thursday, August
10, 2023 at 8:00am PDT (11:00am EDT).
WebcastDate: Thursday, August
10Time: 8:00 am Pacific Time (11:00 am
Eastern time)Please register for the webcast here: Orezone Q2-2023
Conference Call and Webcast
Conference CallToll-free in
U.S. and Canada: 1-800-715-9871International callers:
+646-307-1963Event ID: 1179590
QUALIFIED PERSONS
The scientific and technical information in this
news release was reviewed and approved by Dr. Pascal Marquis, Geo.,
Senior Vice President of Exploration, Mr. Rob Henderson, P. Eng,
Vice President of Technical Services, and Mr. Patrick Downey,
P.Eng. President and CEO, all of whom are Qualified Persons as
defined under NI 43-101 Standards of Disclosure for Mineral
Projects.
About Orezone Gold
Corporation
Orezone Gold Corporation (TSX: ORE OTCQX: ORZCF)
is a Canadian mining company operating the open pit Bomboré Gold
Mine in Burkina Faso.
Orezone is focusing on mining and processing the
Phase I near surface free-dig oxides at a planned annual
throughput of 5.7 million tonnes. The Company believes that Bomboré
has a significant underlying sulphide resource to
support a substantially larger Phase II expansion. The Company
has recently completed a resource definition drill program, and
plans to issue an updated mineral resource, reserve and life of
mine plan, as part of this Phase II expansion. It is expected
that the pending study will be completed in Q3-2023 to be
followed by a production decision.
Orezone is led by an experienced team focused on
social responsibility and sustainability with a proven track record
in project construction and operations, financings, capital markets
and M&A.
The technical report for the 2019 Feasibility
Study on the Bomboré Project entitled NI 43-101 Technical Report
(Amended) Feasibility Study of the Bomboré Gold Project is
available on SEDAR+ under the Company’s profile at
www.sedarplus.ca.
Patrick DowneyPresident and Chief Executive
Officer
Vanessa PickeringManager, Investor Relations
Tel: 1 778 945 8977 / Toll Free: 1 888 673
0663info@orezone.com / www.orezone.com
For further information please contact
Orezone at +1 (778) 945-8977 or visit the Company’s
website at
www.orezone.com.
The Toronto Stock Exchange neither approves nor
disapproves the information contained in this news release.
Cautionary Note Regarding
Forward-Looking Statements
This press release contains certain information
that constitutes “forward-looking information” within the meaning
of applicable Canadian Securities laws and “forward-looking
statements” within the meaning of applicable U.S. securities laws
(together, “forward-looking statements”). Forward-looking
statements are frequently characterized by words such as “plan”,
“expect”, “project”, “intend”, “believe”, “anticipate”, “estimate”,
“potential”, “possible” and other similar words, or statements that
certain events or conditions “may”, “will”, “could”, or “should”
occur. Forward-looking statements in this press release include,
but are not limited to, statements with respect to the Bomboré
Growth Capital Projects and the 2023 Feasibility Study Update for
the Phase II Expansion.
All forward-looking statements are subject to a
variety of risks and uncertainties and other factors that could
cause actual events or results to differ materially from those
projected in the forward-looking statements including, but not
limited to, terrorist or other violent attacks, the failure of
parties to contracts to honour contractual commitments, unexpected
changes in laws, rules or regulations, or their enforcement by
applicable authorities; social or labour unrest; changes in
commodity prices; unexpected failure or inadequacy of
infrastructure, the possibility of project cost overruns or
unanticipated costs and expenses, accidents and equipment
breakdowns, political risk, unanticipated changes in key management
personnel, the spread of diseases, epidemics and pandemics
diseases, market or business conditions, the failure of exploration
programs, including drilling programs, to deliver anticipated
results and the failure of ongoing and uncertainties relating to
the availability and costs of financing needed in the future, and
other factors described in the Company's most recent annual
information form and management’s discussion and analysis filed on
SEDAR+ on www.sedarplus.ca. Readers are cautioned not to place
undue reliance on forward-looking statements.
Forward-looking statements are based on the
applicable assumptions and factors management considers reasonable
as of the date hereof, based on the information available to
management at such time. These assumptions and factors include, but
are not limited to, assumptions and factors related to the
Company’s ability to carry on current and future operations,
including: development and exploration activities; the timing,
extent, duration and economic viability of such operations,
including any mineral resources or reserves identified thereby; the
accuracy and reliability of estimates, projections, forecasts,
studies and assessments; the Company’s ability to meet or achieve
estimates, projections and forecasts; the availability and cost of
inputs; the price and market for outputs, including gold; foreign
exchange rates; taxation levels; the timely receipt of necessary
approvals or permits; the ability to meet current and future
obligations; the ability to obtain timely financing on reasonable
terms when required; the current and future social, economic and
political conditions; and other assumptions and factors generally
associated with the mining industry.
Although the forward-looking statements
contained in this press release are based upon what management of
the Company believes are reasonable assumptions, the Company cannot
assure investors that actual results will be consistent with these
forward-looking statements. These forward-looking statements are
made as of the date of this press release and are expressly
qualified in their entirety by this cautionary statement. Subject
to applicable securities laws, the Company does not assume any
obligation to update or revise the forward-looking statements
contained herein to reflect events or circumstances occurring after
the date of this press release.
Orezone Gold (TSX:ORE)
Historical Stock Chart
Von Dez 2024 bis Jan 2025
Orezone Gold (TSX:ORE)
Historical Stock Chart
Von Jan 2024 bis Jan 2025