Updated Kiniero Feasibility Study Achieves Increase +46% in Gold
Reserves and +89% NPV to US$322M
NOT FOR DISTRIBUTION TO U.S.
NEWSWIRE SERVICES OR DISSEMINATION IN THE
U.S.
HIGHLIGHTS:
-
Increased Reserves Life Of Mine (“LoM”): Mineral
Reserves increased by 442,000oz or 46% to
1.41 million ounces from Kiniero's 2023
Feasibility Study (“2023 FS”);
-
Potential to grow Mineral Reserves: Kiniero has
Indicated Mineral Resources (inclusive of Mineral Reserves) at
2.2Moz @ 0.96g/t Au, plus Inferred Mineral
Resources of 1.53Moz @ 1.05g/t Au (effective
September 1 2024); More than 25,000 metres of drilling completed
since the database cut off. An updated Reserve Statement to include
this drill data is scheduled to be released in Q2
2025;
-
Improved economics: The updated study demonstrates increase
in pre-tax Net Present Value at a discount rate of 5%
(NPV5%)
-
Base Case (Gold Price US$1,800/oz)
-
Pre-tax NPV: US$480M,
-
Pre-tax IRR: 47%.
-
Post-tax NPV: US$322M,
-
Post-tax IRR: 36%.
-
Consensus Case (Gold Price: US$2,330/oz): Pre-tax NPV of US$940M,
Pre-tax IRR of 79%, Post-tax NPV of US$647M, Post-tax IRR of
61%.
-
Stronger economic metrics compared to the 2023 FS (US$1650/oz gold
price), which demonstrated pre-tax NPV5% of US$251M and
IRR of 42%; post-tax NPV5% of US$170M
with IRR of 31%;
-
Average annual gold production: Kiniero expected
to produce 139,000 ounces gold per year over 9-year mine life with
average production of 154,000oz over the first six years;
-
Costs in line with Budget: LoM All-In Sustaining
Costs (“AISC”) of US$1,066 /oz, increasing by 9%
from 2023 FS (US$980/oz);
-
Improved strip ratio: LoM Strip Ratio of 2.0:1,
from 2.8:1 in the 2023 FS; helping to lower mining costs.
QUÉBEC CITY, Jan. 14, 2025 (GLOBE NEWSWIRE) --
Robex Resources Inc. (“Robex” or the
“Company”) (TSXV: RBX) is pleased to announce the
results of an updated feasibility study (the “FS”,
“Feasibility Study” or “Study” or
“2024FS”) for Its Kiniero Gold Project (the
“Kiniero Gold Project”, or the
“Project”) in Conakry, Guinea.
Using a base case gold price of US$1800/oz, the
Study demonstrates Kiniero’s ability to produce an average of
139,000oz of gold per year at a
US$1,066/oz AISC over the 9-year LoM, with an
average gold production of 154,000oz per year in the first
six years. Mine plan optimization efforts prioritized a
stable, long mine life, rather than peak upfront production.
Robex is on track to pour first gold at
Kiniero in Q4 2025, with construction already underway on
the 5 million tonne per annum (Mtpa) processing plant, with a 6Mtpa
capacity on early year high oxide blends and associated
infrastructure. The company will continue its near-mine exploration
efforts to extend the LoM rapidly in conjunction with the annual
production. Robex is still in advance discussions with lenders for
a debt facility which is expected to close in Q1 2025.
Robex Managing Director Matthew
Wilcox commented: “Updating the feasibility study for
our Kiniero Gold Project in Guinea is a major milestone in our
journey towards project development, as the FS optimizations and
updated Mineral Resource Estimate have delivered increased Mineral
Reserves and stronger economics for the project. The base case gold
price of US$1,800/oz post-tax NPV now stands at US$322 million with
an IRR of 36%, which have both improved +89% on the 2023 FS results
within a very short period. At consensus price of US$2,330/oz the
post tax NPV5% stands at US$647m or A$1bn.
In addition, with the high prospectivity of
our property we will be growing the current production and LoM very
rapidly. We expect to average gold production of nearly 140,000oz
of gold a year over the project's 9-year life, with early gold
production of 153,000oz a year over the first six years ideally
timed to benefit from the current high gold price
environment.
An additional 25,000m of drilling has been
completed and it will be part of an updated MRE to potentially
further increase the resources and reserves which should be
released in Q2, 2025.
With construction now progressing well at
Kiniero we issue market updates frequently; we look forward to our
ASX listing in coming months and becoming West Africa's newest gold
producer before the end of 2025.”
The FS was prepared in accordance with Canadian
Securities Administrators’ National Instrument 43-101 - Standards
of Disclosure for Mineral Projects (“NI 43-101”).
The independent NI 43-101 technical report
supporting the Kiniero Gold Project Feasibility Study Update will
be published on SEDAR at www.sedar.com within the next 45 days.
The FS was prepared in accordance with Canadian
Securities Administrators’ National Instrument 43-101 -
Standards of Disclosure for Mineral Projects (“NI
43-101”).
The independent NI 43-101 technical report
supporting the Kiniero Gold Project Feasibility Study Update will
be published on SEDAR at www.sedar.com within the next 45 days.
Table 1 compares the results of the updates
study with the 2023 FS.
Table 1: 2024 Improvements on from 2023 FS
results
Item |
Units |
2023 FS @
US$1,650/oz gold
price |
2024 FS @
US$1,800/oz gold
price |
Variation |
Probable Mineral Reserves
(incl. legacy stockpiles) |
Moz |
0.968 |
1.41 |
+46% |
LoM |
Year |
9.5 |
9 |
-5.2% |
Average annual production LoM |
koz |
90 |
139 |
+54% |
Pre-production Capital |
US$M |
160 |
243 |
+52% |
LoM AISC |
US$/oz |
980 |
1,023 |
+4% |
Pre-tax NPV5%* |
US$M |
251 |
480 |
+91% |
Pre-tax IRR |
% |
42% |
47% |
+12% |
Post-tax NPV5% |
US$M |
170 |
322 |
+89% |
Post-tax IRR |
% |
31% |
36% |
+16% |
*NPV in the 2023 FS calculated as of
1st of July 2023 while the NPV in 2024 FS estimated as
of 1st of September 2024
Update on Construction Activities at
Kiniero
The Kiniero Gold Project construction has
commenced with civil (concrete) works on the process plant, the
erection of the Carbon-in Leach/Gravity (“CIL”)
tanks, and the clearing of the tailings dam basin.
The Project engineering is approximately 75%
complete, all long lead items have been purchased, and 95% of other
equipment has been tendered.
The Project is currently on track to pour first
gold by the end of calendar year 2025.
Highlights of Updated Feasibility
Study
Ore mined from the Kiniero deposit is expected
to be processed through a standard 5Mtpa nominal capacity CIL
plant. The mine is expected to be an open pit using conventional
mining methods.
Table 2: Kiniero 2024 FS Highlights
|
Units |
Value |
Plant, size and CAPEX |
|
|
Plant capacity (@35% Fresh) |
Mtpa |
5 |
Plant capacity (@18% Fresh) |
Mtpa |
6 |
Upfront capital from January 1, 2023 |
US$M |
243 |
Mineral Reserves and Resources (incl. legacy stockpiles) |
|
|
Probable Mineral Reserves |
Moz |
1.41 |
Indicated Resources (incl. Reserves) |
Moz |
2.203 |
Inferred Resources |
Moz |
1.52 |
Mining Operations |
|
|
LoM total tonnes mined |
Mt |
119 |
LoM waste tonnes mined |
Mt |
80 |
LoM ore tonnes mined ex pit |
Mt |
39 |
Average grade mined |
g/t Au |
1.04 |
LoM strip ratio |
W:O |
2.0 |
Processing Operations |
|
|
LoM tonnage processed |
Mt |
45 |
Average grade processed |
g/t Au |
0.97 |
Average recovery LoM |
% |
86.2% |
Production and Costs Summary |
|
|
LoM production |
koz/Au |
1,215 |
Average first three years of production pa |
koz/Au |
153 |
Average LoM production pa |
koz/Au |
139 |
AISC |
US$/oz |
1,066 |
Table 3: Summary of NPV, IRR and payback at $1800/oz and consensus
forward gold price
|
Units |
US$1,800/oz
(Reserve Gold Price) |
US$ ~2,330/oz
(2024 Consensus gold price*) |
Pre-tax returns |
|
|
|
NPV5% |
US$M |
480 |
940 |
IRR |
% |
47% |
79% |
Payback period |
year |
2.1 |
1.3 |
Post-tax returns |
|
|
|
NPV5% |
US$M |
322 |
647 |
IRR |
% |
36% |
61% |
Payback period |
year |
2.6 |
1.6 |
*the S&P consensus long term gold price
at end of October 2024, ranging between US$2431/oz and
US$2,320/oz
As shown in Figure 1 below, the Study
demonstrates Kiniero’s ability to deliver an average of 139koz of
gold per annum at an AISC of US$1,066/oz over the LoM at consensus
gold price, as mine plan optimization efforts prioritized a stable,
long mine life, rather than peak upfront production. Over the
coming years, Robex intends to continue its exploration efforts to
continue to extend the LoM and increase annual production.
Figure 1: Gold Production and AISC Summary
across the LoM
FEASIBILITY STUDY DETAILS
Overview
The Project is located in eastern Guinea in the
Kouroussa Prefecture. It is situated 27km southeast of the town of
Kouroussa and 546km from Conakry, the capital of Guinea (Figure
2: Regional Locality of the Kiniero Gold Project and Regional
Infrastructure of Guinea).
The Kiniero Gold Project is a 470.48km²
exploitation and exploration land package that consists of the
adjoining Kiniero exploitation Licence Area and Mansounia
exploitation Licence Area. The Kiniero Gold Project is one of the
largest gold licences in Guinea.
Figure 2: Regional Locality of the Kiniero
Gold Project and Regional Infrastructure of Guinea
Kiniero gold deposits, located in the prolific
gold-producing Siguiri Basin, were discovered in the early 1900s
and were subsequently explored until 2002 when gold production
began under the ownership of SEMAFO Inc and its subsidiary SEMAFO
Guinée SA.
The historical Kiniero gold mine comprised an
open pit mining operation that produced 418,000 ounces of gold
during its 12-year operational history. The mine was placed on care
and maintenance in early 2014.
Given the strong exploration potential, a
combination of near plant brownfields infill and known extension,
as well as greenfield large-scale targets, Robex is targeting
(i) the discovery of Mineral Resources across the Kiniero
exploration permit area over the next few years, and (ii) the
conversion of Mineral Resources into Mineral Reserves.
An extensive drilling program is ongoing on the
numerous identified deposits to increase the resource base and
extend the LoM at Kiniero predominately through extending the
drilling density at depth and along known strike extensions.
Since the beginning of the construction, Robex
has been committed to involve village communities in the mine's
development, as well as exploring sustainable power energy source
to reduce and limit its environmental footprint.
Geology
The property is located within the Kiniero Gold
District of the Siguiri Basin, which is situated in north-eastern
Guinea, extending into central Mali. Geologically, the Siguiri
Basin comprises a portion of the West Africa Birimian Greenstone
Belt, including intrusive volcanics (ultramafics to intermediate)
and sediments largely deposited through the period 2.13 Ga to 2.07
Ga.
The volcanic and sedimentary lithologies
comprise fine-grained sedimentary rocks (shales and siltstones),
with some intercalated volcanic rocks. Sandstone-greywacke tectonic
corridors have been preferentially altered and locally silicified,
supporting extensive brittle fracture networks. These in turn have
provided host environments for ascending mineralized hydrothermal
fluids.
The deposits located on the property are
associated with the Proterozoic Birimian orogeny of West Africa.
Most gold mineralization in the West African Craton is
shear-zone-hosted and structurally controlled, with lithology
having a minor, local influence. The mineralization developed in
the Kiniero Gold District conforms to this general style of
mineralization.
A total of 47 gold anomalies have been
identified on the property, of which five clusters of deposits
(Sabali, Mansounia, SGA, Jean, and Balan) have been explored
sufficiently to enable the estimation of Mineral Resources.
Figure 3: Location of the main Kiniero
deposits and cross sections (A-B, C-D) and Figure 4: Cross
sections through the SGA (A-B) Sabali South (C-D) deposits
illustrate the location of the main Kiniero deposits and cross
sections through the SGA and Sabali South deposits. The selected
cross sections display the 0.3g/t gold grade shell, Pit and RPEE
(Reasonable Prospects of Economic Extraction) Shells, significant
gold intercepts (minimum of 2m @ 0.5g/t), and regolith profiles
across each deposit. Section A-B, across SGA, demonstrates the
deposit's significant northeast strike and depth extension. Section
C-D, across Sabali South, shows the deposit's deep weathering
saprolite and saprock profile in the east (beyond 100m in
areas).
Section E-F, across Mansounia Central, shows the
depth extension of the northeast strike.
Figure 3: Location of the main Kiniero
deposits and cross sections (A-B, C-D, E-F)
Figure 4: Cross sections through the SGA
(A-B), Sabali South (C-D) and Mansounia Central (E-F)
deposit
Mineral Reserves and
Resources
The January 2025 FS update is based on the
updated Mineral Resources Estimate (“MRE”), as
shown in Table 4 below, which has a resource-to-reserve conversion
ratio for the in-situ estimate of 66%. The MRE includes the Mineral
Reserves.
Table 4: Mineral Reserves and Resources
Summary
100% basis |
Tonnage (Mt) |
Grade
(Au g/t) |
Content (koz) |
Probable Mineral Reserves (in-situ) |
39.3 |
1.04 |
1,320 |
Probable Mineral Reserves (Legacy Stockpiles) |
6.3 |
0.48 |
100 |
Total Probable Mineral Reserves |
45.5 |
0.97 |
1,410 |
Indicated Mineral Resources (in-situ) |
59.62 |
1.08 |
2,064 |
Indicated (Legacy Stockpiles) |
11.61 |
0.37 |
139 |
Total Indicated Mineral Resources (incl. of. Mineral
Reserves) |
71.23 |
0.96 |
2,203 |
Inferred Mineral Resources (in-situ) |
45.10 |
1.05 |
1,519 |
Inferred (Legacy Stockpiles) |
0.19 |
1.31 |
8 |
Total Inferred Mineral Resources |
45.29 |
1.05 |
1,527 |
Notes:
-
The effective date of the Mineral Resource and Reserves is 30
November 2024.
-
The date of closure for the sample database informing the in
situ Mineral Resources excluding Mansounia, is 17 August 2022. The
date of database closure for the Mansounia MRE is 16 October
2024.
-
Cut-off grades for Mineral Resource reporting are:
-
SGA, Jean and Banfara: laterite 0.3 g/t Au, saprolite (oxide)
0.3 g/t Au, saprock (transition) 0.3 g/t Au, fresh 0.4 g/t
Au.
-
Sabali South: laterite 0.3 g/t Au, mottled zone/saprolite/lower
saprolite (oxide) 0.3 g/t Au, saprock (transition) 0.5 g/t Au,
fresh 0.6 g/t Au.
-
Sabali North and Central: laterite 0.3 g/t Au, saprolite
(oxide) 0.3 g/t Au, saprock (transition) 0.6 g/t Au, fresh 0.6 g/t
Au.
-
West Balan: laterite 0.3 g/t Au, saprolite (oxide) 0.3 g/t Au,
saprock (transition) 0.3 g/t Au, fresh 0.5 g/t Au.
-
Mansounia Central: laterite 0.4 g/t Au, saprolite (oxide) 0.3
g/t Au, saprock (transition) 0.5 g/t Au, fresh 0.5 g/t
Au.
-
Stockpiles reported as Mineral Resources have been limited to
those dumps which exhibit an average grade >0.3 g/t Au for the
entire stockpile assuming no selectivity.
-
These are based on a gold price of US$2,200/oz and costs and
recoveries appropriate to each pit and type of feed.
-
The QP for this MRE is Mr Ingvar Kircher.
-
Mineral Resources are reported inclusive of Mineral
Reserves.
-
Open-pit Mineral Resources were constrained using optimum pit
shells based on a gold price of US$2,200/oz.
-
CIM Definition Standards for Mineral Resources and Mineral
Reserves (CIM, 2014) were used for reporting the Mineral
Reserve.
-
Mineral Reserve was estimated using a long-term gold price of
US$1,800 per troy oz for all mining areas.
-
Mineral Reserve is stated in terms of delivered tonnes and
grade before process recovery.
-
Mineral Reserve was defined by pit optimization and pit design
and is based on variable break-even cut-offs as generated by
process destination and metallurgical recoveries.
-
Metal recoveries are variable, dependent on material type and
mining area.
-
Dilution and ore loss was applied through application of 1.0 m
dilution skins to the resource model using Mineable Shape
Optimizer.
-
The QP responsible for this item of the Technical Report is not
aware of any mining, metallurgical, infrastructure, permitting, or
other relevant factors that could materially affect the Mineral
Reserve estimate.
-
The Mineral Resource has been compiled in accordance with the
guidelines outlined in CIM Definition Standards, (2014).
-
The estimates may be materially affected by environmental,
permitting, legal, marketing, or other relevant issues. Please see
“Forward Looking Statements”
below and the technical report for the Kiniero Gold Project that
will be prepared in accordance with NI 43-101 and filed on SEDAR+ R
at www.sedarplus.com within the next 45 day.
-
Tonnage and grade measurements are in metric units. Contained
Au is reported as troy ounces.
-
Totals may not compute exactly due to rounding.
Exploration
The date of closure for the sample database
informing the in situ Mineral Resources is 16 October 2024 for
Mansounia, 17 August 2022 for all other Kiniero deposit areas and
12 November 2022 for the stockpile Mineral Resources.
Additional drilling that has been completed has
not been included in this update of the resources and reserves, due
to time constraints, is shown in Table 5.
Table 5 - Further drilling completed since database cut off
date
Deposit |
No. Drillholes |
Metres* |
SGA |
56 |
8,123 |
Jean |
14 |
2,165 |
GOB D & NEGD |
38 |
6,499 |
Sabali North |
2 |
240 |
Sabali Central |
3 |
370 |
Sabali South |
13 |
2,364 |
Mankan |
43 |
5,633 |
Total |
169 |
25,394 |
*These numbers are a combination of both reverse
circulation and diamond drilling metres
Brownfields exploration will consist of
trenching and drilling at and around the near-mine deposits.
Drilling will be a combination of diamond and Reverse Circulation
(“RC”) drilling and the purpose is twofold, namely Resource
addition and Resource to Reserve conversion. Drilling will focus on
four deposits: SGA, NEGD, Sabali South and Mansounia Central. SGA,
NEGD and Sabali South will comprise Resource addition drilling by
strike and depth extension, as well as Reserve conversion
drilling.
A planned total of approximately 10,000m of
diamond and 50,000m of RC drilling is planned for 2025 across
various deposits. However, the drilling program will be an
iterative process based on the ongoing results and the impact
thereof. As a result, the plan may be changed and adapted to any
changes in strategy.
Mining Operations
Mining at Kiniero is expected to be undertaken
by conventional owner-operated truck and excavator open-pit mining
in the SGA, Jean, SGD, Sabali South, Mansounia and Sabali North and
Central pits using Komatsu PC1250-sized excavators mining on 5m
benches and 2.5m flitches loading 40-tonne Komatsu HM400 haul
trucks.
Mining in upper oxide layers will be free-dig
with drill-and-blast required in areas that mine through the
transitional material into fresh rock. The free-dig nature of the
oxide zones has been confirmed by extensive previous mining at the
site. Drill-and-blast will be required for approximately 30% of the
oxide material, 100% of the laterite, 100% of the transitional, and
100% of the fresh.
Ore will be categorized by material and grade
through in-pit grade control and will be hauled to the mine ore pad
(“MOP”). Waste will be hauled to the nearest available waste dump
by the Komatsu HM400 fleet.
Historic mining in Jean, SGA, and SGD has
resulted in pit lakes that require dewatering and clean-up before
mining.
The key mining infrastructure including pits,
waste dumps, stockpiles, and haulage roads is shown in Figure
5.
Figure 5: Key Mining Infrastructure
Layout
Processing Operations
Primero Pty Ltd. (“Primero”)
was commissioned by Robex to undertake the detailed re-design of
the new processing plant to increase its capacity from 3Mtpa to
expected throughput of 6Mtpa at 18% fresh in ore feed. The process
plant design is based on a metallurgical flowsheet developed for
flexible operation between the various types of ore while
maintaining the throughput and gold recovery. Ore will be processed
on-site, at a centrally located processing facility near the mining
areas. The gold will be recovered in a beneficiation plant that has
been designed to process a blend of oxide, laterite, transition,
and fresh ores from various ore deposits.
Oxide and upper transition ores (soft) require
less comminution energy than laterite and fresh ore (hard).
However, they present other challenges in handling due to the
sticky nature of oxide ore types, justifying dedicated crushing
devices for soft and hard ores. The process plant design has been
based on a nominal capacity of 5.0 Mtpa with 35% fresh in mill
feed to 6.0 Mtpa with 18% fresh ore in feed. The flowsheet (Figure
6) includes two crushing circuits, semi-autogenous, ball grinding,
and pebble crushing milling (SABC), dual CIL circuits, split
Anglo-American Research Laboratories (“AARL”) elution, gold
electrowinning, and carbon regeneration that are well proven in the
industry.
Figure 6: Process plant simplified block flow
diagram
Infrastructure
The Project benefits from good infrastructure
close to the site, and a limited relocation requirement as there
are no villages on the site. Existing mining infrastructure will be
refurbished with minimal additional infrastructure required.
In addition, early works have focused on
advancing the site infrastructure to facilitate a smooth transition
into construction. Site roads to the mine from the national road
network, mine perimeter fence, and the earthworks for the
construction camp have already been completed as part of the early
works, incurred during 2024.
New infrastructure will be added to support
mining, processing and waste management on the mining license
including power transmission line, diesel generators, and
additional site facilities and accommodation for staff.
Power
Due to the Project location, access to the
Guinea national grid is not available, thus an on-site power
generation solution is required. A Heavy Fuel Oil (“HFO”)-solar and
battery storage hybrid power plant is proposed for the Project,
consisting of HFO generators with a capacity of approximately 28
MW, a solar photo-voltaic (“PV”) plant with total capacity of
approximately 21 MWp/ 16MW AC and the battery energy storage system
(“BESS”) with a capacity of 5.2 MWh with 4 MW usable capacity and 4
MW power conversion system.
Water
Water for operations will be sourced from the
existing raw water catchment dam (rainwater runoff collection),
dewatering of historical pits, and boreholes. Potable water will be
required for the mine site and both accommodation camps during
operations and construction. Currently the Main Camp has borehole
water supply available and at the Staff Camp, water will be
obtained from the Niandan River.
Process water will be primarily sourced from
recirculated tailings storage facility (“TSF”) water. It is
continuously recirculated from the TSF, to the process water pond
and to the processing plant, mainly in the milling area. A pump
located in the process water feeds the process water distribution
network of the mill. Raw water is added to the process water pond
through the freshwater tank overflow to compensate for the process
water losses. The proposed water supply is sufficient to meet the
process plant requirements.
Tailings
Knight Piésold Consulting (“KP”) was
commissioned by Robex to undertake detailed design of the TSF,
based on work carried out for the 2023 Technical Report and
supplementary work and studies carried out since the 2023 design.
The proposed TSF is required to accommodate 60 Mt of tailings over
a LoM of 10 years, at a rate of up to 0.5 Mt per month (up to 6
Mtpa). The required storage volume for the tailings was calculated
using an estimated average in situ dry density of the tailings
product of 1.39 t/m3, a particle SG of 2.77 t/m3, and an estimated
average in situ void ratio of 1. Tailings will be pumped to the TSF
in a slurry comprising 38%-42% solids by mass. The proposed TSF
site has been selected as the preferred site for the development of
the Kiniero Mine TSF based on the evaluation of the candidate
sites. The TSF site was selected due to:
-
Reduced rock/earth fill volumes required to construct the main
embankment of the TSF.
-
Opportunities for phasing allows capital expenditure to be spread
over 3 phases.
-
The site allows a facility 32m high, fully lined with a downstream
raised full-containment wall.
-
Elevation to the processing plant is more favourable than other
options and avoids a deposition line running over the ridge between
the existing TSF and other site options, which is favourable in
terms of pumping costs.
-
The site would be less exposed during operational and closure
phases.
-
Rehabilitation and closure of the TSF lends itself to relatively
simple closure principles, without long-term storage of water,
utilizing existing stormwater diversions to direct surface runoff
off the TSF. The relatively smaller downstream embankment surface
area for the TSF would require less material for the rehabilitation
and vegetation of downstream slopes to the TSF.
The TSF is expected to be constructed in phases
as a full containment facility incorporating an high density
polyethylene liner to the basin and inside faces of the containment
walls to mitigate against the potential for groundwater pollution.
Phase 1 will comprise the initial embankment, causeway,
interception trenches, diversion channel, collection pond and
distribution system. Phases 2 and 3 will comprise downstream lifts
for the TSF embankments until the final elevation is reached. Phase
3 will include partial progressive closure and construction of the
post closure emergency spillway.
Management and monitoring systems will be
implemented to ensure that risks associated with the facility are
identified and mitigated in line with accepted practices and
standards.
Figure 7: Site Infrastructure of the Kiniero
complex
Operating Costs Summary
Mining operating cost estimates were prepared by
AMC Consultants (UK) Ltd (“AMC”). Processing costs
were prepared by Primero while Infrastructure and General and
Administration (“G&A”) operating cost
estimates were prepared by Robex. LoM operating unit costs are
summarised in the table below.
Table 6: LoM operating unit costs
Item |
Operating costs (US$/t ore processed) |
Refining and transport charges |
0.05 |
Mining Costs |
9.0 |
Processing Costs |
10.6 |
Maintenance Costs |
0.7 |
General and Administration |
2.1 |
Corporate Costs |
1.6 |
Total |
24.0 |
Capital Costs Summary
The process plant capital cost estimate
(“Capex”) was compiled by Primero with input from Knight Piésold on
the TSF and Robex on the water infrastructure and site access
roads. Robex has provided estimates for mine establishment,
infrastructure facilities, high-voltage power supply and owner’s
costs.
Starting September 1, 2024, the total LoM Capex
is estimated at US$326m, including US$243m of pre-production Capex,
US$19m of development Capex post-construction period and
US$ 63m of sustaining Capex, as shown in the table below. The
pre-production Capex include a 5.8% contingency. The LOM CapEx is
summarized in Table 7.
Table 7: Capital Cost Estimate
Summary
Category, in US$k |
Pre-Production
Capex |
Capex during
operations |
Sustaining Capex
over LoM |
Total Capex LoM |
Mining |
29,150 |
|
1,863 |
31,014 |
Process Plant |
104,533 |
|
|
104,533 |
TSF |
12,868 |
19,129 |
10,889 |
42,886 |
Infrastructure |
35,610 |
|
|
35,610 |
G&A |
31,117 |
|
|
31,117 |
Other costs |
18,968 |
|
17,771 |
36,738 |
Closure costs |
|
|
32,856 |
32,856 |
Contingency |
10,961 |
- |
|
10,961 |
Total |
243,207 |
19,129 |
63,380 |
325,716 |
The construction has commenced and $41m of the planned Capex has
been spent at the end of December 2024.
The closure costs estimate was updated by ABS
Africa increasing from $19.9m in 2023 to US$32.8m. This includes
increased Preliminary and General Costs, Engineering Design and
Environmental Permitting and contingency.
Environment and Social
Under the Mining Code, all applicants for an
exploitation licence must submit an Environmental and Social Impact
Assessment (“ESIA”). Robex completed the ESIA in
2023. There are currently no known objections to Robex to the
development of the Project.
The environmental permit for the Project was
received and an Environmental and Social Management Plan
(“ESMP”) is being implemented to guide Robex’s
local community engagement as well as ensure it fulfils its
environmental obligations, minimizing the mine’s impacts where
possible. The ESMP Is currently based on the 2023 FS, however, the
ESMP Is currently updated with the latest FS project design. The
updated ESMP will be used to ensure compliance with environmental
specifications, monitoring and management measures and will be
implemented from site preparation through to decommissioning and
closure.
Robex believes that its most significant
contribution to sustainable and responsible development is to help
its local employees obtain or complete their professional
qualifications, thereby ensuring long careers. Robex intends to
replicate the mine-school concept in Guinea from its existing
operation in Mali, targeting a >90% local talent of its skilled
workforce.
Ownership, Permitting, Taxes and
Royalties
Once a mining convention is signed with the
Government of Guinea, Robex will have an 85% ownership stake in
Kiniero, while SOGUIPAMI (the Guinean state-owned mining company)
will have a stake of 15%. Subject to the Government of Guinea’s 15%
interest, Robex also has the exclusive rights to full
ownership of the Mansounia exploitation license. Robex has
submitted an application to the Government of Guinea to convert the
licenses into exploitation. Ultimately, Robex will own 85% of
Kiniero and Mansounia with the balance owned by the Guinean state.
Both properties will be governed by the same mining convention.
Subject to adjustment with a mining convention
the corporate tax rate of 30% has been applied in the FS. A royalty
rate of 5.5%, a 1% contribution to the Local Mining
Development Fund and a 0.5% private royalty were applied to
all sales.
FINANCIAL
ANALYSIS
An economic analysis has been carried out for
the Project using a cash flow model. The model has been constructed
using annual cash flows considering annual processed tonnages and
grades for the CIL feed, process recoveries, metal prices,
operating costs and refining charges, royalties and capital
expenditures (both pre-production and sustaining).
The economic model was run at two gold prices;
Scenario 1 with gold price of US$1,800/oz used for the Mineral
Reserve and Scenario 2 with the S&P consensus long term gold
price at end of October 2024, ranging between US$2,431/oz and
US$2,320/oz, as shown in Table 8.
Table 8: LoM Gold Price
LOM Gold Price |
Years |
2026 |
2027 |
2028 |
Long Term |
Scenario 1 Mineral Reserve
|
US$/oz |
1,800 |
1,800 |
1,800 |
1,800 |
Scenario 2 S&P consensus gold price (end of October 2024)
|
US$/oz |
2,431 |
2,314 |
2,320 |
2,320 |
The financial assessment of the Project is carried out on a “100%
equity” basis and no provision has been made for the effects of
inflation. Discounting and IRR calculations have been applied as of
September 1, 2024, using a 5% discount rate.
Project costs included from July 2024 and sunk
costs considered pre-July 2024 with commercial production in
January 2026.
Table 9 - Costs summary across the
LoM
Across the LoM, starting July 1, 2023 |
Total
US$M |
Unit Cost
US$/t ore milled |
Costs
US$/oz |
Refining and transport charges |
2 |
0.05 |
2 |
Mining costs |
407 |
9.0 |
335 |
Processing costs |
513 |
11.3 |
423 |
G&A Guinea |
94 |
2.1 |
77 |
Total Site Costs |
1,016 |
22.4 |
837 |
Government royalty |
198 |
4.4 |
163 |
Private royalties |
31 |
0.7 |
26 |
Total Operating Costs |
1,246 |
27.5 |
1,025 |
Sustaining costs |
50 |
1.1 |
41 |
All-In Sustaining Costs |
1,296 |
28.6 |
1,066 |
G&A outside Guinea |
70 |
1.5 |
57 |
Development costs |
237 |
5.2 |
195 |
Closure costs |
33 |
0.7 |
27 |
Total Costs |
1,635 |
36.0 |
1,346 |
Table 10 - Summary of NPV, IRR and payback at $1800/oz and
consensus forward gold price
|
Units |
US$1,800/oz
(Reserve Gold Price) |
US$ ~2,330/oz
(2024 Consensus gold price*) |
Pre-tax returns |
|
|
|
NPV5% |
US$M |
480 |
940 |
IRR |
% |
47% |
79% |
Payback period |
year |
2.1 |
1.3 |
Post-tax returns |
|
|
|
NPV5% |
US$M |
322 |
647 |
IRR |
% |
36% |
61% |
Payback period |
year |
2.6 |
1.6 |
The Project value was assessed by undertaking sensitivity analyses
using the consensus forward gold price (Scenario 2) on the gold
price, operating costs, capital costs and discount rates:
Table 11 - NPV Sensitivity Gold
Price
Gold Price |
Pre-tax NPV
(US$M) |
Post Tax NPV
(US$M) |
(15.0%) |
639 |
434 |
(7.5%) |
789 |
540 |
- |
940 |
647 |
7.5% |
1,090 |
753 |
15.0% |
1,240 |
860 |
Table 12 - NPV Sensitivity Capital Costs
Capex |
Pre-tax NPV
(US$M) |
Post Tax NPV
(US$M) |
(15.0%) |
969 |
670 |
(7.5%) |
954 |
658 |
- |
940 |
647 |
7.5% |
925 |
636 |
15.0% |
910 |
624 |
Table 13 - NPV Sensitivity Operating Costs
Opex |
Pre-tax NPV
(US$M) |
Post Tax NPV
(US$M) |
(15.0%) |
1,056 |
731 |
(7.5%) |
998 |
689 |
- |
940 |
647 |
7.5% |
881 |
605 |
15.0% |
823 |
563 |
|
|
|
Table 14 - Discount rate Sensitivity
Discount Rate |
Pre-tax NPV
(US$M) |
Post Tax NPV
(US$M) |
5.0% |
940 |
647 |
7.5% |
816 |
557 |
10.0% |
711 |
481 |
Qualified Person
Scientific or technical information in this
press release that relates to Mineral Resources was prepared or
supervised by Mr. Ingvar Kirchner, a full-time employee for AMC
Consultants Pty Ltd. Mr Kirchner is a Fellow of the Australasian
Institute of Mining and Metallurgy and a Member of the Australian
Institute of Geoscientists and has sufficient experience that is
relevant to the project under consideration which he is undertaking
to qualify as a Qualified Person (“QP”) under NI
43-101.
Scientific or technical information in this
press release that relates to geology, exploration, drilling and
sample preparation, analyses and security was prepared or
supervised by Mr. Nicholas Szebor, a full-time employee for AMC
Consultants UK Ltd. Mr Szebor is a Chartered Geologist with the
Geological Society of London (CGeol) and the European Federation of
Geologists (EurGeol) and has sufficient experience that is relevant
to the project under consideration which he is undertaking to
qualify as a QP under NI 43-101.
Scientific or technical information in this
press release that relates to Mineral Reserves and Mining was
prepared or supervised by Glen Williamson, a full-time employee for
AMC Consultants Pty Ltd. Mr Williamson is a Fellow and Chartered
Professional of the Australasian Institute of Mining and Metallurgy
and has sufficient experience that is relevant to the project under
consideration which he is undertaking to qualify as a QP under NI
43-101.
The scientific or technical information in this
press release that relates to geotechnical engineering was prepared
or supervised by Mr. Jody Thompson, founder and principal engineer
of TREM Engineering in South Africa. Mr. Thompson is a certified
rock mechanics engineer under the Chamber of Mines of South Africa,
is a member in good standing with the South African Institute of
Rock Engineering, a member of the South African Institute of Mining
and Metallurgy and a member of the International Society of Rock
Mechanics; he has sufficient experience that is relevant to the
commodity, style of mineralization under consideration and activity
which he is undertaking to qualify as a QP under NI 43-101.
The scientific or technical information in this
press release that relates to metallurgy and processing results was
prepared or supervised by Mr. Ryan Cunningham, a full-time employee
of Primero. Mr. Cunningham is a member of the Ordre des Ingénieurs
du Québec (OIQ) and has sufficient experience that is relevant to
the project under consideration which he is undertaking to qualify
as a QP under NI 43-101.
The scientific or technical information in this
press release that relates to tailings storage facility results was
prepared or supervised by Mr. Darren Anthony King, a permanent
employee of Knight Piésold Limited (UK) . Mr. King is a Chartered
Geologist (Geological Society of London), Chartered Engineer and
Environmentalist (Institute of Engineer) and has sufficient
experience that is relevant to the project under consideration
which he is undertaking to qualify as a QP under NI 43-101.
The scientific or technical information in this
press release that relates to environmental, social and governance
results was prepared or supervised by Mr. Faan Coetzee, a full-time
employee of ABS AFRICA PTY. Mr. Coetzee is a Registered
Professional Natural Scientist with the South African Council for
Natural Scientific Professions and has sufficient experience which
is relevant to the project under consideration which he is
undertaking to qualify as a QP under NI 43-101.
Each of Mr. Ingvar Kirchner, Mr. Nicholas
Szebor, Mr. Glen Williamson, Mr. Jody Thompson, Mr. Ryan
Cunningham, Mr. Darren King and Mr. Faan Coetzee has reviewed and
approved the scientific and technical information relating to his
respective fields of expertise mentioned above and does not or did
not have at the relevant time an affiliation with Robex or its
subsidiaries, except that of independent consultant/client
relationship. The relevant QP’s have verified the data disclosed
including sampling, analytical and test data underlying the
information contained in this news release. This included an
appropriate quality control sampling program of reference
standards, blanks and duplicates to monitor the integrity of all
assay results. Raw Quality Assurance/Quality Control (“QA/QC”) data
was supplied to the QP that has reviewed the data statistically.
Additional checks completed by the QP have included review of
historical QA/QC data and review of a selection of assay
certificates.
Further details on the scientific and technical
information relating to the Kiniero Gold Project will be provided
in the technical report for the Kiniero Gold Project which will be
filed on SEDAR at www.sedar.com within the next 45 days.
Neither the TSX Venture Exchange nor its
Regulation Services Provider (as that term is defined in policies
of the TSX Venture Exchange) accepts responsibility for the
adequacy or accuracy of this press release.
About Robex Resources Inc.
Robex is a multi-jurisdictional West African
gold production and development company with near-term exploration
potential. The Company is dedicated to safe, diverse and
responsible operations in the countries in which it operates with a
goal to foster sustainable growth. The Company has been operating
the Nampala mine in Mali since 2017 and is advancing the Kiniero
Gold Project in Guinea.
Robex is supported by two strategic shareholders
and has the ambition to become one of the most important mid-tier
gold producers in West Africa.
For more information
ROBEX RESOURCES INC.
Matthew Wilcox, Chief Executive Officer
Alain William, Chief Financial Officer
+1 581 741-7421
Email: investor@robexgold.com
www.robexgold.com
Forward-looking information and forward-looking
statements
This press release contains “forward-looking
information” and “forward-looking statements” within the meaning of
applicable Canadian securities legislation
(“forward-looking statements”). Forward-looking
statements are included to provide information about Management’s
current expectations and plans that allows investors and others to
have a better understanding of the Company’s business plans and
financial performance and condition.
Statements made in this press release that
describe the Company’s or Management’s estimates, expectations,
forecasts, objectives, predictions, projections of the future or
strategies may be “forward-looking statements”, and can be
identified by the use of the conditional or forward-looking
terminology such as “aim”, “anticipate”, “assume”, “believe”,
“can”, “contemplate”, “continue”, “could”, “estimate”, “expect”,
“forecast”, “future”, “guidance”, “guide”, “indication”, “intend”,
“intention”, “likely”, “may”, “might”, “objective”, “opportunity”,
“outlook”, “plan”, “potential”, “should”, “strategy”, “target”,
“will” or “would” or the negative thereof or other variations
thereon. Forward-looking statements also include any other
statements that do not refer to historical facts. Such statements
may include, but are not limited to, statements regarding the
perceived merit and further potential of the Company’s properties;
the Company’s estimate of mineral resources and mineral reserves
(within the meaning ascribed to such expressions in the Definition
Standards on Mineral Resources and Mineral Reserves adopted by the
Canadian Institute of Mining Metallurgy and Petroleum (“CIM
Definition Standards”) and incorporated into NI 43-101;
capital expenditures and requirements; the Company’s access to
financing (including any project finance facility); preliminary
economic assessments (within the meaning ascribed to such
expressions in NI 43-101) and other development study results;
exploration results at the Company’s properties; budgets; strategic
plans; market price of precious metals; the Company’s ability to
successfully advance the Kiniero Gold project on the basis of, and
achieve, the results projected in the feasibility study (within the
meaning ascribed to such expression in the CIM Definition Standards
incorporated into NI 43-101) with respect thereto (including
economic and production results), as the same may be updated from
time to time by the Company; the potential development and
exploitation of the Kiniero Gold Project and the Company’s existing
mineral properties and business plan, including the completion of
feasibility studies or the making of production decisions in
respect thereof; work programs; permitting or other timelines;
government regulations and relations; optimization of the Company’s
mine plan; the future financial or operating performance of the
Company and the Kiniero Gold Project; exploration potential and
opportunities at the Company’s existing properties; costs and
timing of future exploration and development of new deposits;.
Forward-looking statements and forward-looking
information are made based upon certain assumptions and other
important factors that, if untrue, could cause the actual results,
performance or achievements of the Company to be materially
different from future results, performance or achievements
expressed or implied by such statements or information. There can
be no assurance that such statements or information will prove to
be accurate. Such statements and information are based on numerous
assumptions, including: the ability to execute the Company’s plans
relating to the Kiniero Gold Project as set out in the feasibility
study with respect thereto, as the same may be updated from time to
time by the Company ; the Company’s ability to reach an agreement
with the Malian authorities to establish a sustainable new tax
framework for the Company, and for the sustainable continuation of
the Company's activities and further exploration investments at
Nampala; the Company’s ability to complete its planned exploration
and development programs; the absence of adverse conditions at the
Kiniero Gold Project; the absence of unforeseen operational delays;
the absence of material delays in obtaining necessary permits; the
price of gold remaining at levels that render the Kiniero Gold
Project profitable; the Company’s ability to continue raising
necessary capital to finance its operations; the Company’s ability
to restructure the Taurus USD35 million bridge loan and adjust the
mandate to accommodate for the revised timeline of the enlarged
project; the Company’s ability to enter into definitive
documentation for the USD115 million project finance facility for
the Kiniero Gold Project (including a USD15 million cost overrun
facility) on acceptable terms or at all, and to satisfy the
conditions precedent to closing and advances thereunder (including
satisfaction of remaining customary due diligence and other
conditions and approvals); the ability to realize on the mineral
resource and mineral reserve estimates; and assumptions regarding
present and future business strategies, local and global
geopolitical and economic conditions and the environment in which
the Company operates and will operate in the future.
Certain important factors could cause the
Company’s actual results, performance or achievements to differ
materially from those in the forward-looking statements and
forward-looking information including, but not limited to:
geopolitical risks and security challenges associated with its
operations in West Africa, including the Company’s inability to
assert its rights and the possibility of civil unrest and civil
disobedience; fluctuations in the price of gold; limitations as to
the Company’s estimates of mineral reserves and mineral resources;
the speculative nature of mineral exploration and development; the
replacement of the Company’s depleted mineral reserves; the
Company’s limited number of projects; the risk that the Kiniero
Gold Project will never reach the production stage (including due
to a lack of financing); the Company’s capital requirements and
access to funding; changes in legislation, regulations and
accounting standards to which the Company is subject, including
environmental, health and safety standards, and the impact of such
legislation, regulations and standards on the Company’s activities;
equity interests and royalty payments payable to third parties;
price volatility and availability of commodities; instability in
the global financial system; the effects of high inflation, such as
higher commodity prices; fluctuations in currency exchange rates;
the risk of any pending or future litigation against the Company;
limitations on transactions between the Company and its foreign
subsidiaries; the risk that the listing of the Company’s shares on
the ASX is not approved and/or otherwise implemented, and even if
it is, that is fails to support the long-term growth of the
Company; volatility in the market price of the Company’s shares;
tax risks, including changes in taxation laws or assessments on the
Company; the Company’s inability to successfully defend its
positions in negotiations with the Malian authorities to establish
a new tax framework for the Company, including with respect to the
current tax contingencies in Mali; the Company obtaining and
maintaining titles to property as well as the permits and licenses
required for the Company’s ongoing operations; changes in project
parameters and/or economic assessments as plans continue to be
refined; the risk that actual costs may exceed estimated costs;
geological, mining and exploration technical problems; failure of
plant, equipment or processes to operate as anticipated; accidents,
labour disputes and other risks of the mining industry; delays in
obtaining governmental approvals or financing; the effects of
public health crises, on the Company’s activities; the Company’s
relations with its employees and other stakeholders, including
local governments and communities in the countries in which it
operates; the risk of any violations of applicable anti-corruption
laws, export control regulations, economic sanction programs and
related laws by the Company or its agents; the risk that the
Company encounters conflicts with small-scale miners; competition
with other mining companies; the Company’s dependence on
third-party contractors; the Company’s reliance on key executives
and highly skilled personnel; the Company’s access to adequate
infrastructure; the risks associated with the Company’s potential
liabilities regarding its tailings storage facilities; supply chain
disruptions; hazards and risks normally associated with mineral
exploration and gold mining development and production operations;
problems related to weather and climate; the risk of information
technology system failures and cybersecurity threats; and the risk
that the Company may not be able to insure against all the
potential risks associated with its operations.
Although the Company believes its expectations
are based upon reasonable assumptions and has attempted to identify
important factors that could cause actual actions, events or
results to differ materially from those described in
forward-looking information, there may be other factors that cause
actions, events or results not to be as anticipated, estimated or
intended. These factors are not intended to represent a complete
and exhaustive list of the factors that could affect the Company;
however, they should be considered carefully. There can be no
assurance that forward-looking information will prove to be
accurate, as actual results and future events could differ
materially from those anticipated in such information.
The Company undertakes no obligation to update
forward-looking information if circumstances or Management’s
estimates, assumptions or opinions should change, except as
required by applicable law. The reader is cautioned not to place
undue reliance on forward-looking information. The forward-looking
information contained herein is presented for the purpose of
assisting investors in understanding the Company’s expected
financial and operational performance and results as at and for the
periods ended on the dates presented in the Company’s plans and
objectives and may not be appropriate for other purposes.
Please refer to the “Risk Factors” section of
the Company’s Annual Information Form for the year ended December
31, 2023, dated April 29, 2024, and to the “Risks and
Uncertainties” section of each of the Company’s Management’s
Discussion and Analysis dated April 29, 2024 for the years ended
December 31, 2023, and the Company’s Management’s Discussion and
Analysis dated November 29, 2024 for the three-month periods ended
September 30, 2024 and September 30, 2023, all of which are
available electronically on SEDAR+ at www.sedarplus.ca or on the
Company’s website at www.robexgold.com All forward-looking
statements contained in this press release are expressly qualified
by this cautionary statement.
Photos accompanying this announcement are available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/f78d305f-feb0-452e-864d-d75218fab9d5
https://www.globenewswire.com/NewsRoom/AttachmentNg/29881c9d-6b6c-4dd2-b858-ea21887b4b13
https://www.globenewswire.com/NewsRoom/AttachmentNg/b6431e8a-f512-4908-8957-ce8109d098d2
https://www.globenewswire.com/NewsRoom/AttachmentNg/b71ccca3-2b62-4f60-b371-75d55beee67a
https://www.globenewswire.com/NewsRoom/AttachmentNg/5109f7de-a091-44b9-abf7-ba5952db7f6f
https://www.globenewswire.com/NewsRoom/AttachmentNg/f8908fb5-b2fd-4a81-9b31-a06f68fa4de7
https://www.globenewswire.com/NewsRoom/AttachmentNg/cdbdf8e7-1a58-4537-95dc-b1181157d3df
https://www.globenewswire.com/NewsRoom/AttachmentNg/e46aec9c-ae9a-41fa-b0a1-1c5d299daf08
Robex Resources (TG:RB4)
Historical Stock Chart
Von Dez 2024 bis Jan 2025
Robex Resources (TG:RB4)
Historical Stock Chart
Von Jan 2024 bis Jan 2025