VANCOUVER, BC, Dec. 17, 2021 /CNW/ - East Africa Metals
Inc. (TSXV: EAM) ("East Africa" or the "Company") is
pleased to provide an update on the progress of the engineering and
mine development work at the Magambazi mine in the Handeni region
of the Federal Republic of Tanzania.
With the successful completion of the tailings processing in the
third quarter of 2021, the technical team for PMM Mining Company
Limited ("PMM") are focused on the development of hard-rock mining
operations.
Phase I of the mining operations will be initiated on surface
from two open pit resources, the "North and "South" pits. These
pits will be established on areas of the deposit representing
approximately 15 percent of the recently upgraded one-million ounce
Measured and Indicated resource (see October
19, 2021, press release).
Phase II of the mining operations will be conducted from
underground where the resource within the Magambazi ridge will be
accessed from the valley floor, 200m
below the surface operations, to take full advantage of gravity in
the mining process.
Engineering work is progressing and detailed plans for mining
operations and surface equipment installations are expected to be
complete early January 2022
Infrastructure required to initiate and support surface mining
operations continues to be upgraded and expanded to increase
milling capacity sufficient for surface open-pit operations.
Development of the access road to the South Pit site is
underway.
The processing flow-sheet continues to be refined and expanded
to support the hard-rock mining operations. The plans for the
expansion of the crushing and grinding circuit continue to be
developed. Staged upgrades to the flow-sheet and processing plant
will initially expand the capacity of the existing circuit to 1,000
tonnes per day and ultimately to a capacity capable of supporting a
40,000 ounce production rate per year within forty-eight months of
commissioning of the hard-rock mining operations.
East Africa Metals has completed the formation of its Tanzanian
gold trading company, "EMG Royalty Plc.", in order to
facilitate the acquisition of the Company's share of gold
production from the Magambazi mine. Under the terms of the sale
purchase agreement with PMM, EAM holds the rights to acquire 30% of
the gold produced from the mining operations for a payment equal to
the per ounce cash costs of mining and processing plus
15%.
According to Q2 2021 processing reconciliations provided to EAM
by PMM the tailings operations produced a total of 645 ounces of
gold. EAM's share of the Q2 2021production is 169 ounces with a
current value of US$275,000. The
final transfer of the Magambazi mining licenses to PMM and
reconciliation of Q3 2021 processing are expected to be completed
in early January 2022.
Andrew Lee Smith, P.Geo., C.E.O.,
a Qualified Person under the definitions of National Instrument
43-101, has reviewed and approved the technical contents of this
news release
About East Africa Metals
The Company's principal assets include a 30% Net Profits
Interest in the Mato Bula and Da Tambuk mines (collectively
"Adyabo Property") and a 70% project interest in the Harvest
polymetallic VMS Exploration Project in the Tigray Region of
Ethiopia. In addition, the Company
has a 30% Net Streaming Interest in the Magambazi Mine in the Tanga
Region of Tanzania.
The Mato Bula and Da Tambuk mines are four kilometres apart and
will be developed simultaneously. The development of the mining
operations is scheduled to begin during the second half of
2021.
East Africa retains exploration
rights on areas of the properties outside the Mato Bula, Da Tambuk
and Terakimti mining licenses in all Ethiopian projects and
anticipates the commencement of exploration drilling to test
priority targets during the second half of 2021.
EAM has invested US$66.8M in
African exploration since 2005 and identified a total of 2.8
million ounces of gold and gold-equivalent resources
representing an average discovery cost per ounce of US$24.
The current Global Project Resources discovered by EAM
include:
Project Resources
(Au + Aueqv Metal ounces)
|
Project
|
Category
|
Au
+Aueqvounces
|
Adyabo Project,
Ethiopia (EAM 30% Net
Profit Interest)
|
Indicated
|
446,000
|
Inferred
|
551,000
|
Harvest Project,
Ethiopia
(EAM = 70% Project
Interest)
|
Indicated
|
469,000
|
Inferred
|
426,000
|
Handeni Project,
Tanzania
(EAM = 30%
Streaming Royalty Interest)
|
Measured &
Indicated*
|
1,006,000
|
Inferred*
|
1,800
|
|
* Resource calculated based on 0.40 gAu/t cut-off – see October 19,
2021 press release for details)
|
More information on the Company can be viewed at the Company's
website: www.eastafricametals.com.
On behalf of the Board of Directors:
Andrew Lee Smith, P.Geo., CEO
Cautionary Statement Regarding Forward-Looking
Information
This news release contains "forward-looking information"
within the meaning of applicable Canadian securities legislation.
Generally, forward-looking information can be identified by the use
of forward-looking terminology such as "anticipate", "believe",
"plan", "expect", "intend", "estimate", "forecast", "project",
"budget", "schedule", "may", "will", "could", "might", "should",
"indicate", "confident" or variations of such words or similar
words or expressions. Forward-looking information is based on
reasonable assumptions that have been made by the Company as at the
date of such information and is subject to known and unknown risks,
uncertainties and other factors that may cause the actual results,
level of activity, performance or achievements of the Company to be
materially different from those expressed or implied by such
forward-looking information, including but not limited to:
statements regarding present and future plans and objectives of the
Company, the ability of PMM to meet minimum annual production, the
ability of PMM to make the payment if the minimum annual production
is not met, the ability of PMM to carry out hard rock mining
operations, the Company's expected cash flows from royalties, the
negotiation of a definitive agreement with Zijin reflecting the
anticipated structure and timing outlined herein; the negotiation
of a definitive agreement reflecting the anticipated structure and
timing outlined herein; delays with respect to required payments
and regulatory approvals; results of the due diligence review; the
ability of Tibet Huayu to develop and operate the Ethiopia Adyabo
Project within the required laws and agreements; the ability of PMM
to develop and operate the Tanzanian Magambazi Project within the
required laws and agreements; recoverability of the Ethiopian and
Tanzanian VAT receivable; early exploration; the ability of
East Africa to identify any other
corporate opportunities for the Company; the possibility that the
Company may not be able to generate sufficient cash to service its
planned operations and may be force to take other options; the risk
the Company may not be able to continue as a going concern; the
possibility the Company will require additional financing to
develop the Ethiopian Projects into a mining operation; the risks
associated with obtaining necessary licenses or permits including
and not limited to Ethiopian Government approval of EAM Mineral
Resources extensions for the Company's Ethiopian Properties and
Projects; risks associated with mineral exploration and
development; metal and mineral prices; the demand for precious and
base metals; availability of capital; accuracy of the Company's
Projections and estimates, including the initial and any updates to
the mineral resource for the Adyabo, Harvest and Handeni Projects;
realization of mineral resource estimates; interest and exchange
rates; competition; stock price fluctuations; the ability to carry
on exploration and development activities; actual results of
exploration activities; availability of drilling equipment and
access; the ability to obtain qualified personnel, equipment and
services in a timely and cost-efficient manner; the regulatory
framework including and not limited to license approvals, social
and environmental matters; the ability to operate in a safe,
efficient and effective manner government regulation; political or
economic developments; foreign taxation risks; environmental risks;
insurance risks; capital expenditures; operating or technical
difficulties in connection with development activities; personnel
relations; the speculative nature of strategic metal exploration
and development including the risks of contests over title to
properties; and changes in project parameters as plans continue to
be refined, as well as those risk factors set out in the Company's
filings with securities regulators. Mineral Resources, which
are not Mineral Reserves, do not have demonstrated economic
viability. The estimate of mineral resources may be materially
affected by environmental, permitting, legal, title, taxation,
sociopolitical, marketing, or other relevant issues. The
quantity and grade of reported inferred mineral resources as the
estimation is uncertain in nature and there has been insufficient
exploration to define any inferred mineral resources as an
indicated or measured mineral resource and it is uncertain if
further exploration will result in upgrading inferred mineral
resources to an indicated or measured mineral resource category.
The contained gold, copper and silver figures shown are in situ. No
assurance can be given that the estimated quantities will be
produced. Although the Company has attempted to identify
important factors that could cause actual results to differ
materially from those contained in forward-looking information,
there may be other factors that cause results not to be as
anticipated, estimated or intended. There can be no assurance that
such information will prove to be accurate, as actual results and
future events could differ materially from those anticipated in
such information. The Company does not update or revise forward
looking information even if new information becomes available
unless legislation requires the Company to do so. Accordingly,
readers should not place undue reliance on forward-looking
information contained herein, except in accordance with applicable
securities laws.
Neither TSX Venture Exchange nor its Regulation Services
Provider (as that term is defined in the policies of the TSX
Venture Exchange) accepts responsibility for the adequacy or
accuracy of this release.
SOURCE East Africa Metals Inc.