Gold Bull Resources Corp. (TSX-V: GBRC) (“
Gold
Bull” or the “
Company”) is pleased to
report completion of its Sandman Scoping Study at its 100% owned
Sandman Project (“
Sandman” or the
“
Project”) located in Humboldt County, Nevada,
USA.
The Sandman Scoping Study has identified a
stand-alone low-cost start-up heap leach gold opportunity. The
study focused on only mining mineralized material above the water
table, which represents approximately 50% of the current NI 43-101
mineral resource. The Study highlights include:
- Scoping Study based on only
250,000 ounces of 494,000-ounce NI 43-101 gold
resource (refer to table 6 for NI 43-101 resource breakdown)
- Production rate of 2.1
Mtpa for an initial 5-year operation
- 35,000 ounces of
gold per annum produced from conventional heap
leach
- At USD1,800/oz gold
price:
- IRR of 99%
(pre-tax)
- NPV 10% USD$77.2M
(pre-tax)
- Payback period of 1.1
years (pre-tax)
- Average grade 0.74g/t
gold (all oxide)
- Low strip ratio of
1.6:1
- Low Capital requirement of
USD28.8M including working capital USD4.3M
- Low operating cost of
USD15.99 per tonne
- All in Sustaining
Cost (AISC) of USD1,173/oz of gold
- Phase 1 (this study) focusses on
the oxide feed above the water table only
- Phase 2 and remainder of the gold
resource below water table has not yet been investigated
This Scoping Study focused on the extraction of
above water table oxide feed only, to facilitate cost effective and
rapid mine commissioning. Additional Mineral Resources located
below the water table will be included in future mine studies. The
final Scoping Study will be a preliminary economic assessment, per
NI 43-101 regulations, and will be filed on SEDAR within 45
days.
Gold Bull CEO, Cherie Leeden commented:
Sandman
provides Gold Bull with a low-cost start-up opportunity. In our
Phase 1 scoping study we only examined the oxide gold located above
the water table, to investigate what a near-term small-scale
development scenario could deliver. The IRR of 99% and pay back of
just over a year is exceptional, considering this is not a life of
mine study and neglects the other half of the resource lying below
the water table, and the future resource growth potential. Sandman
represents a realistic near-term mine scenario capable of
generating cashflow, located in northern Nevada, a top mining
jurisdiction.
STUDY HIGHLIGHTS
The Sandman Scoping Study [prepared by Jerod
Eastman, President of DJ 6E Consulting LLC, an independent
third-party consultant] has demonstrated potentially strong
financial metrics for the Sandman Project based on a proposed
stand-alone low-cost start-up heap leach gold mine project located
approximately 25 km from the mining town of Winnemucca (Figure 1
and 2) in central Northern Nevada, USA. This study investigated a
Phase 1 five-year mine plan of above water table oxide material
processed onsite via conventional Heap Leach processing. Gold Bull
considers Sandman to be technically low risk, given the low strip
ratio and significant historical database that the study was based
on. The Scoping Study was completed to an overall +/- 30% accuracy
using the key parameters and assumptions set out in Tables 1 and
2.
The figures in the Scoping Study are focused
only on the above water table mining scenario. There is additional
oxide and sulfide gold mineralization below the water table and
these mineralized materials will be included in future feasibility
studies. The above water table mine scenario in the Scoping Study
targets near-term cash flow to later fund below water table oxide
mine studies and development. This work must include further
studies for sulfide product processing and additional resource
drilling.
The Sandman Project Scoping Study reports an IRR
of 99%, NPV10% of USD77M, annual cashflow of estimated USD30M, and
a payback period of 1.1 years when applying a gold price of
USD1,800/oz of gold. The initial capital cost is USD28.8M, which
includes working capital of USD4.3M, and a further USD8.3M will be
required in year 3 as sustaining capital for additional mine
studies and second leach pad commissioning. Total operating cost is
$15.99 per tonne and all in sustaining cost of $1,173/oz gold.
Royalty is low at 1.2% of product.
Phase 1 contained oxide gold above the water
table amounts to approximately 250,000 ounces with a head grade of
0.74 g/t gold spread across four known gold deposits. The 250,000
ounces of contained gold above water table that this study is based
upon comprises approximately 50% of the 2021 pit-constrained NI
43-101 Mineral Resource Estimate of 494,000 ounces. The four gold
resources (see Figure 3: North Hill, Silica Ridge, Southeast
Pediment, Abel Knoll) shall be mined via conventional open pit
mining methods, with an average waste to product ratio of 1.6:1,
annual production is 35K oz gold, with 2.2Mt feed production rate.
Refer Table 1 for further details and estimated financial
metrics.
Metric for Phase 1 (oxide above water table
only) |
Outcome |
Economic Analysis |
|
|
Internal Rate of Return (IRR) |
|
99 |
% |
|
NPV @ 10% |
$ |
77,207,945 |
|
USD |
Average Annual Cashflow |
$ |
29,762,342 |
|
USD |
Undiscounted Cumulative Cashflow |
$ |
119,953,708 |
|
USD |
Pay-Back Period |
|
1.1 |
|
years |
Gold Price Assumption |
$ |
1,800 |
|
per
ounce |
All-in Sustaining Cost |
$ |
1,173 |
|
per ounce |
Capital Costs |
|
|
Initial Capital |
$ |
28,758,000 |
|
USD |
Working Capital (included in above) |
$ |
4,300,000 |
|
USD |
LOM Sustaining Capital |
$ |
8,342,000 |
|
USD |
Operating Costs (Average LOM) |
|
|
Mining |
$ |
6.69 |
|
per ore
tonne |
Processing & Support |
$ |
5.43 |
|
per ore
tonne |
General & Administration (G&A) |
$ |
2.52 |
|
per ore
tonne |
Other Costs |
$ |
1.34 |
|
per ore
tonne |
Total Operating Cost |
$ |
15.99 |
|
per ore
tonne |
Production Data |
|
|
Life of Mine (Phase 1 only) |
|
5 |
|
years |
Ore Production Rate |
|
2,121,185 |
|
tonnes
per annum |
Total Tonnes of Ore Processed |
|
10,605,927 |
|
tonnes |
Grade Au (Average) |
|
0.74 |
|
g/t
Au |
Contained Gold |
|
251,848 |
|
ounces |
Metallurgical Recovery Au (Overall) |
|
70 |
% |
|
Average Annual Gold Production1 |
|
35,259 |
|
ounces
per annum |
Total Gold Produced |
|
176,294 |
|
ounces |
LOM Strip Ratio (Waste Tonnes : Ore Tonnes) |
|
1.6 |
|
: 1 |
Table 1. Scoping Study economic analysis of Sandman Project
Please note, it was assumed in this Cash Flow
Model that Year 1 would follow the normal (reverse) S-curve for
costs and performance. As such, there is an assumed ramp-up period
for gold recovery, and operating costs are assumed to be higher in
Year 1 during this ramp-up to steady state.
Figure 1. Sandman Project location map of Northern Nevada
relative to the surrounding operating gold mines.
Figure 2. Sandman Project location relative to infrastructure
and nearby regional mine servicing town of Winnemucca. The project
is located on Jungo Road 20 kms from Winnemucca.
Figure 3. Sandman Scoping Study proposed mine design.
EXECUTIVE SUMMARY
The Sandman Project presents strong financial
results and a compelling mine opportunity for a stand-alone open
pit mine, commencing at the North Hill deposit, followed by the
Silica Ridge, Southeast Pediment and Abel Knoll deposits. The mine
proposal includes onsite single-stage crushing, which will move
progressively from each pit location, with separate dumps and two
localised leach pads. The first leach pad will be constructed for
North Hill and Silica Ridge, and the second leach pad will be
constructed for $8.3M in year 3 and will receive mineralized
material feed from Southeast Pediment and Abel Knoll.
Economics are based upon contract mining,
crushing and heap leach as the main processing method. It is
planned to load the gold onto activated carbon and then transport
the loaded carbon to off-site stripping and refining plants for
final gold doré recovery. A simplified mining schedule is
anticipated to produce 35,000-40,000 ounces of gold per annum.
Given the North Hill and Silica Ridge deposits
outcrop at surface, these deposits present the best strip ratio
starter pit mine scenarios. Above water table oxide product is
targeted in this Scoping Study to enable rapid permitting for mine
start-up and initial cash flow. There is further additional
opportunity to mine the below water table oxide mineralization and
use initial mine production profit to fund further below water
table mine studies over the initial five-year mine period. The
Scoping Study economics do not include the additional oxide
mineralization located below the water table; as this will be
included in future feasibility studies.
Parameter |
Units |
Value |
Gold Price |
US$/oz |
$1800 |
Gold Recovery |
% |
70 |
Silver Price |
US$/oz |
$20 |
Silver Recovery |
% |
35 |
Dilution |
% |
0 |
Ore Loss |
% |
0 |
Overall Pit Slope Angle |
Degrees |
50 |
Processing Rate |
Tonnes per Annum |
3,000,000 |
Carbon Stripping and Transportation |
$25.00 |
$/ounce |
Final Refining and Marketing |
$10.00 |
$/ounce |
Royalties |
1.2% |
|
Property Tax |
$750,000 |
per year |
New Mining Tax |
2.0% |
|
Mining Waste |
$2.64 |
$/t (waste) |
Mining Ore |
$2.40 |
$/t (ore) |
Ore Crushing |
$0.76 |
$/t (ore) |
Ore Haulage |
$1.05 |
$/t (ore) |
Heap Leach Processing |
$3.05 |
$/t (ore) |
G&A |
$2.52 |
$/t (ore) |
Table 2. Sandman Project Scoping Study mine factors applied to
the economic evaluation
Comments
- This scenario includes above water
table product feed, it does not include below water table or fresh
mineralization
- Recoveries assumed at 70% for
oxide/transitional material heap leaching based on historic studies
by Newmont and others. Opportunity exists to further
optimise/increase recoveries and further metallurgical testwork is
needed
- Optimised pit shells were applied,
not a refined pit design
- Future opportunity exists to
increase mine production, as this schedule assumes dayshift only
mining to meet the planned material movement requirements
- Revenue from silver production is
included in this model, however, there has been little to no work
on modeling of silver grade/tonnage recovery due to lack of silver
assay data in historical drilling
- Cashflow model includes a 1.2%
Royalty
Capital Categories
- Contingency of 30% added to all
capital to cover unknown/ unrecognized categories
- Working capital is sufficient to
cover 2 months of operating costs
- All Capital estimates are based on
previous projects (within the past two years) and inflated to 2022
levels
- Engineering Procurement
Construction Management (EPCM)
- Earthworks – roads, stockpiles and
yard construction
- Crushing/stacking equipment, single
stage crushing for 6-8Kt per day, cost estimate includes
installation and commissioning, entire system to be mobile and
follow mining from pit to pit
- Leach pad and ponds, 5-8Kt per day,
cost estimate includes installation and commissioning. Initial pad
built near North Hill and Silica Ridge will handle 63% of planned
tonnage with a second smaller pad build near Southeast Pediment and
Abel Knoll in year 3.
- Carbon columns, cost estimate
includes installation and commissioning. One set of columns for the
initial leach pad and second set to be constructed for the second
leach pad
- Sustaining capital includes
temporary construction facilities, construction services, supplies,
quality control, survey support, construction equipment and
safety
- Sample preparation conducted on
site with off site gold analysis
- Infrastructure includes portable
office, warehouse/parts storage, and a workshop
- Initial purchase or lease of water
rights necessary to operate the mine
- Option to purchase additional
surface rights included
Operational Categories
- Mining contractor mobilisation for
12-15 equipment units, office space and other resources.
- Contract mining comprises
- Drilling
- Blasting
- In-pit loading
- Waste haulage to near-pit waste
rock stockpile
- Product feed haulage to near-pit
stockpile location (for feed to crusher)
- Loader feed into a portable
(movable) crusher
- Loading of crushed material into
trucks
- Truck haulage to heap leach
pad
- Roads/dumps/stockpile
maintenance
- Company shall maintain small
workforce for project management, administration, SHE
permitting-training-compliance, general labor, crushing/heap leach
operations, supply chain etc.
- Contractor demobilisation at the
end of the project life
- Centralised location for diesel,
gasoline, lubes and oils
- Power Generation and Distribution
with mobile generators for crushing, pumping and other
infrastructure requirements, includes a back-up generator, power
poles, transformers for on-site distribution
- Further studies for alternative
power solutions are needed as this scenario uses diesel
generators
- Water supply and distribution,
water well construction and extraction, pumping and piping to
supply water for the project. Water usage 3,900 gallons per minute
with make-up water consumption rate of 285 gallons per minute
- Additional environmental and
hydrogeological baseline studies are required
- Initial purchase or lease of water
rights necessary to operate the mine
- Indirect owners’ costs include
temporary construction facilities, construction services, supplies,
quality control, survey support, construction equipment, safety
etc.
Operating Costs
An operating cost estimate has been calculated
at US$15.99 per tonne of mineralized material mined and processed
for the project. The estimate relates to all costs to allow
production of gold doré, capturing the processing plant facilities,
contractor mining, product refining and general and administration
(G&A) costs.
Functional Area |
Cost per
Tonne Processed(US$) |
Mining |
$6.69 |
Processing |
$5.44 |
G&A |
$2.52 |
Other |
$1.34 |
Total Site
Operating
Cost1 |
$15.99 |
Table 3. Sandman Project operating cost summary.
Basis for Economic calculations (tonnage/grades)
The Company announced its Mineral Resource
Estimate February 2, 2021 (refer to table 6) with combined
Indicated and Inferred ounces totaling 494K ounces of gold.
- Indicated Resource of 18,550kt @ 0.73g/t gold for 433kozs of
gold
- Inferred Resource of 3,246kt @ 0.58g/t gold for 61kozs of
gold
Table 4 summarises the tonnes and grade applied
to the Scoping Study for above water table oxide
mineralization.
The Scoping Study is preliminary in
nature, includes inferred mineral resources that are considered too
speculative geologically to have the economic considerations
applied to them that would enable them to be categorized as mineral
reserves, and there is no certainty that the Scoping Study will be
realized.
A further grade model was created for the
Scoping Study to include the 2021 and 2022 drill results and
estimate an above water table tonnage and grade model. This was
applied to the Scoping Study pit optimisation work and the
resulting tonnes and grade are summarised in Table 4. The water
table surface was conservatively defined by first intercept of
water in the exploration drill holes. Detailed hydrogeological
studies accurately defining the water table are yet to be
conducted.
Table 4. Scoping Study tonnes and grade depicting 250K oz
contained gold within the pit optimisation and above the estimated
water table depth
Mining MethodsThe Sandman Project is planned to be mined using
conventional open pit mining methods on the four (4) separate
deposits in the order listed in Table 4. The mining operation
schedule is dayshift only with a roster of two production crews on
a 4-days on and 4-days off, 12 hours per day.
Pre-production stripping is minimal as
mineralized material is located at or near surface where mining is
anticipated to begin at the North Hill and Silica Ridge deposits.
The pit areas have small shrubs and grasses that can be easily
cleared with planned mining equipment.Open pit mining is currently
envisaged to be by diesel-powered equipment, utilizing a
combination of one rotary blasthole rig drilling 170mm diameter
blastholes, one 8m3 front-end loader (or similar size excavator),
and five, 70-tonne capacity trucks to handle mineralized material
and waste. The mining fleet has sufficient capacity to move up to
approximately 5.5Mtpa of total material on a dayshift-only
schedule. Support equipment comprising a grader, track dozer(s) and
water truck will aid in the mining. Mineralized material will be
hauled to the crushing area for stockpiling before being rehandled
later for primary crushing. Initially, waste rock will be stored in
the waste rock dumps close to the pit to reduce haulage costs. As
space and design allows, waste will be backfilled into the pit to
reduce haulage costs and surface disturbance.
Haul roads are contemplated to be 9-10m widths
for one-way traffic and 18-20m widths for two-way traffic. The
final location of the ramps will be optimized to reduce the overall
pit slopes and to aid in efficient haulage to various stockpile
locations. The pit is considered dry.
The mine plan was designed to deliver ~2,000,000
tonnes of mineralized material per year to the processing facility.
The mine plan was based on efficient extraction of mineralized
material above the water table and started at the North Hill
deposit (predicted higher-grade and low strip ratio) and then
working the deposits in a southerly direction without regard to
Indicated and Inferred Mineral Resource categories.
Total estimated mining workforce is 45-50
people, comprising a team of 15 Gold Bull personnel and 30-35
mining contractors (20 production operators, 8 maintenance techs, 5
supervisory staff).
Table 5 summarizes the five-year annual mining
production schedule for above water table product, it is not a life
of mine schedule.
Period |
Product |
GoldGrade |
ContainedGold |
TotalWaste |
TotalMaterial |
StripRatio |
|
tonnes |
g/t |
ounces |
tonnes |
tonnes |
w:o |
Year 1 |
1,623,598 |
0.82 |
42,857 |
3,102,181 |
4,725,780 |
1.9 |
Year 2 |
2,291,882 |
0.78 |
57,143 |
3,825,925 |
6,117,807 |
1.7 |
Year 3 |
2,702,106 |
0.66 |
57,143 |
2,824,233 |
5,526,339 |
1.0 |
Year 4 |
2,211,842 |
0.80 |
57,143 |
2,971,717 |
5,183,559 |
1.3 |
Year 5 |
1,776,498 |
0.66 |
37,563 |
4,521,774 |
6,298,272 |
2.5 |
Totals |
10,605,927 |
0.74 |
251,848 |
17,245,830 |
27,851,756 |
1.6 |
Table 5. Sandman Project annual mining production schedule for 5
years of the four Sandman deposits. Mining is for above water table
mining only.
Mineral Processing and Recovery Methods
Precious metal recovery from this Scoping Study
is through conventional heap leaching and adsorption, desorption,
regeneration (ADR) technology for metal extraction from crushed
product using industry standard equipment. Processing will involve
mineralized material passing through a single stage of crushing,
which will allow for haulage transport and end-dump stacking of the
mineralized material onto a heap leach pad. The processing
facilities accommodate a leachable tonnage of approximately 11Mt of
product at a gold grade of 0.74g/t and a process rate of 5,000tpd
or 2.1Mtpa. The heap leach pad facilities have been located and
designed with expandability for a LOM production increase.
Mineralized material will be delivered to the
heap leach pad from the open pit and placed in the stockpile
adjacent to the crushing plant. The mineralized material will be
fed to the crushing plant using a front-end loader and will be
crushed and then transported to the heap leach pad via haul trucks.
The mineralized material will be stacked onto the heap using
industry standard end-dumping and dozer pushing and then leached
with a weak cyanide solution to extract the precious metal values.
The gold will then be recovered from the pregnant solution in the
carbon columns by adsorbing the dissolved gold onto activated
carbon, which will be bagged and transported off-site to an
external facility to extract gold from the loaded carbon. The
stripped carbon will be returned from the external treatment
facility to site for continuous reuse in the process plant. The
doré will be sent to a contract refiner for final refining.
Sensitivity Analysis
High level sensitivity analysis of the Sandman
Project economics was conducted, indicating the project is most
sensitive towards gold price and less sensitive towards operating
cost and least sensitive to capital cost.
Figure 4. Sandman sensitivity analysis evaluating gold price,
capital costs and operating costs.
Table 6. January 2021 NI 43-101 Sandman Gold Resource Estimate.
Full report available: Sandman-NI-43-101_2021-01-20.pdf
(goldbull.ca) Please note that the Sandman 2021 NI 43-101
Resource Estimate does not include drilling conducted by Gold Bull
in 2021 and 2022.
NEXT STEPS
Further metallurgical and hydrogeological
studies are required for inclusion in a Feasibility Study. Baseline
hydrogeological, cultural and biological surveys have previously
been conducted at Sandman, however, may need to be updated for mine
permitting.
CAUTIONARY STATEMENT
This Scoping Study is a preliminary technical
and economic study investigating the potential viability of
commissioning and running a gold mine at the Sandman Project. The
Scoping Study includes inferred mineral resources that are
considered too speculative geologically to have the economic
considerations applied to them that would enable them to be
categorized as mineral reserves, and there is no certainty that the
Scoping Study will be realized.
The Scoping Study in this announcement is based
on technical and economic assumptions and assessments which could
be further refined and evaluated in a prefeasibility and
feasibility study. If the Company were to attempt to bring the
Sandman Project into production without established mineral
reserves on the project supported by a full feasibility study, the
Company cautions that this could result in a higher risk of
economic or technical failure of the operation than if a full
feasibility study had been prepared demonstrating economic and
technical viability.
The Scoping Study is based on material
assumptions outlined in this announcement. These include
assumptions about the availability of funding and other parameters.
While the Company considers all the material assumptions are based
on reasonable grounds, there is no certainty they will prove to be
correct or that the range of outcomes indicated in this Scoping
Study announcement can be achieved or realised. There are no
assurances that the Sandman Project will be found to be
economic.
To achieve the potential mine development
outcomes indicated in the Scoping Study, significant funding is
required as well as further metallurgical, hydrogeological, and
environmental assessments and permits received prior to confirming
mining can take place. The Study has focussed only on initial oxide
mining of mineralized material above the water table using
conventional heap leach processing. Investors should note there is
no certainty that the Company will be able to raise the required
funding when needed, however the Company has concluded that it has
a reasonable basis for providing the forward-looking statements
included in this announcement and believes that it has a
“reasonable basis” to expect it will be able to fund the gold
development project upon receiving satisfactory and favourable
results for further metallurgical, hydrogeological and
environmental studies and permits enabling economic ore extraction.
Further studies are required to confirm the proposed mine scenario
and confirm assumptions made in this Scoping Study.
It is also possible that such funding may only
be available on terms that may be dilutive, or otherwise affect the
value of the Company’s existing shares. It is also possible that
the Company could pursue other strategies to provide alternative
funding options including project finance.Given the uncertainties
involved for the metallurgical, hydrogeological and environmental
assessments and permits, investors should not make any investment
decision based solely on the results of the Scoping Study and
assume a mine will be developed, however every effort will be made
by the Company to progress towards mine development.
ABOUT SANDMAN
In December 2020, Gold Bull purchased the
Sandman Project from Newmont. Gold mineralization was first
discovered at Sandman in 1987 by Kennecott and the project has been
intermittently explored since then. There are four known pit
constrained gold resources located within the Sandman Project,
consisting of 21.8Mt at 0.7g/t gold for 494,000 ounces of gold;
comprising of an Indicated Resource of 18,550kt at 0.73g/t gold for
433kozs of gold plus an Inferred Resource of 3,246kt at 0.58g/t
gold for 61kozs of gold. Several of the resources remain open in
multiple directions and the bulk of the historical drilling has
been conducted to a depth of less than 100m. Sandman is
conveniently located circa 25-30 km northwest of the mining town of
Winnemucca, Nevada.
QUALIFIED PERSON
The technical information in this news release
has been reviewed and approved by Mr. Jerod Eastman, a Qualified
Person under National Instrument 43-101. Mr. Eastman is a
Registered Member (#00885850) of the Society for Mining, Metallurgy
and Exploration, Inc. and is completely independent of Gold Bull
Resources Corp. The information in this news release that relates
to mining and cost estimation is based on, and fairly reflects,
information compiled by Mr. Eastman.
ABOUT GOLD BULL RESOURCES CORP.
Gold Bull’s mission is to grow into a US focused
mid-tier gold development Company via rapidly discovering and
acquiring additional ounces. The Company’s exploration hub is based
in Nevada, USA, a top-tier mineral district that contains
significant historical production, existing mining infrastructure
and an established mining culture. Gold Bull is led by a Board and
Management team with a track record of exploration and acquisition
success.
Gold Bull’s core asset is the Sandman Project,
located in Nevada which has a 494,000 oz gold
resource as per 2021 43-101 Resource Estimate. Sandman is located
23 km south of the Sleeper Mine and boasts excellent large-scale
exploration potential. Drilling at Sandman is currently
underway.
Gold Bull is driven by its core values and
purpose which includes a commitment to safety, communication &
transparency, environmental responsibility, community, and
integrity.
Cherie LeedenPresident and CEO, Gold Bull Resources Corp.
For further information regarding Gold Bull
Resources Corp., please visit our website at www.goldbull.ca or
email admin@goldbull.ca or phone 778.899.3050.
Cautionary Note Regarding Forward-Looking
StatementsNeither the TSX Venture Exchange nor its
Regulation Services Provider (as that term is defined in the
policies of the TSX Venture Exchange) accepts responsibility for
the adequacy or accuracy of this release.
This news release contains certain statements
that may be deemed “forward-looking statements” with respect to the
Company within the meaning of applicable securities laws.
Forward-looking statements are statements that are not historical
facts and are generally, but not always, identified by the words
“expects”, “plans”, “anticipates”, “believes”, “intends”,
“estimates”, “projects”, “potential”, “indicates”, “opportunity”,
“possible” and similar expressions, or that events or conditions
“will”, “would”, “may”, “could” or “should” occur. Although Gold
Bull believes the expectations expressed in such forward-looking
statements are based on reasonable assumptions, such statements are
not guarantees of future performance, are subject to risks and
uncertainties, and actual results or realities may differ
materially from those in the forward-looking statements. Such
material risks and uncertainties include, but are not limited to,
the Company’s ability to raise sufficient capital to fund its
planned activities at the Sandman Project; the timing and costs of
future activities on the Company’s properties; maintaining its
mineral tenures and concessions in good standing, to explore and
develop its projects, to repay its debt and for general working
capital purposes; changes in economic conditions or financial
markets; the inherent hazards associates with mineral exploration
and mining operations, future prices of copper and other metals,
changes in general economic conditions, accuracy of mineral
resource and reserve estimates, the potential for new discoveries,
the ability of the Company to obtain the necessary permits and
consents required to explore, drill and develop the projects and if
obtained, to obtain such permits and consents in a timely fashion
relative to the Company’s plans and business objectives for the
projects; the general ability of the Company to monetize its
mineral resources; and changes in environmental and other laws or
regulations that could have an impact on the Company’s operations,
compliance with environmental laws and regulations, dependence on
key management personnel and general competition in the mining
industry. Forward-looking statements are based on the reasonable
beliefs, estimates and opinions of the Company’s management on the
date the statements are made. Except as required by law, the
Company undertakes no obligation to update these forward-looking
statements in the event that management’s beliefs, estimates or
opinions, or other factors, should change.
Gold Bull Resources (TSXV:GBRC)
Historical Stock Chart
Von Nov 2024 bis Dez 2024
Gold Bull Resources (TSXV:GBRC)
Historical Stock Chart
Von Dez 2023 bis Dez 2024