Giyani Metals Corp. (TSXV:EMM, GR:A2DUU8)
("
Giyani" or the "
Company"),
developer of the K.Hill Battery-Grade Manganese Project in Botswana
("
K.Hill" or “
the Project”), is
pleased to provide an update on the commissioning of the
Demonstration Plant (“
Demo Plant”) in
Johannesburg.
Highlights:
-
The Demo Plant is nearing completion of commissioning, and the team
continues to work determinedly towards first production of
battery-grade high-purity manganese sulphate monohydrate (HPMSM)
before year-end, but due to recent events, production may occur in
early Q1 2025, due to the impact of the following:
-
Power outage from an isolated incident of vandalism and copper
cable theft at an Eskom key point substation on December 11.
-
Water supply was consequently unavailable to the Demo Plant from
December 12 to December 17.
-
Unexpectedly slow progress in commissioning the control
system.
-
The power outage directly impacted the area of Krugersdorp, South
Africa and additionally impacted the local water supply and thus
the ability to run the Demo Plant. Water, which is critical for the
commissioning process, was unavailable to the Demo Plant from
December 12 to December 17, and this has impacted progress.
-
The water supply to the Demo Plant was reinstated midday on
December 17, following which the operations team implemented a
24-hour recovery procedure to flush and clean the crystallisers
after the extended stoppage.
-
One of the key objectives of the Demo Plant is to identify issues
and improve the design, build and ramp-up of the Commercial
Facility, which is planned for construction in Botswana adjacent to
Giyani’s extensive, 100% owned manganese oxide ore sources.
-
Prior to commissioning and during the process, the team has
implemented mitigating adjustments which have also impacted the
timeline to production from the Demo Plant, including the
unexpectedly slow progress in commissioning the control system,
mentioned above.
-
The transition into full process flow hot commissioning and
production remains imminent, now that full utilities, including
power and water, have been restored to site. Demo Plant product
samples will be provided to offtakers for qualification trials
early in Q1 2025, enabling indicative terms in 2025.
Charles FitzRoy, President and CEO of
the Company, commented:
“Giyani’s Demo Plant is progressing through the
commissioning phase, and the team continues to work determinedly
towards first production of battery-grade manganese. Whilst we are
targeting first production of HPMSM this month, delivery in early
Q1 2025 is likely. This is due to the recent unforeseen external
impacts from power and water availability in Krugersdorp, South
Africa, where the plant is located, in addition learnings
identified and mitigations implemented as part of the normal
commissioning process.
Whilst the disruption from power and water
outage has now been resolved, the ongoing learnings will be
leveraged for the construction of the main plant in Botswana;
fine-tuning the process now will have demonstrable operational and
cost benefits when we reach construction of the main Commercial
Plant, and puts us on firmer footing for a successful and smooth
ramp-up. These adjustments further endorse the strategic decision
made to construct a Demo Plant at a 1:10 scale to the planned
Commercial Facility, as this significantly de-risks the final
Project.
The Demo Plant is an essential component in
Giyani’s long-term strategy to deliver high-purity battery-grade
manganese to the EV market. This production capacity establishes a
strong foundation for Giyani to engage with potential offtake
partners, as the continuous process flow of the Demo Plant will
allow the team to target steady-state operations over extended
periods, consequently proving Giyani’s ability to produce
consistent battery-grade manganese and satisfy offtake
requirements. This continuous operation at pre-commercial scale
also provides critical information for understanding how the
Commercial Plant will respond, further de-risking the Project.”
Figure 1: Demo Plant Overview Looking
North
Power and Water Outage
The power outage impacted the local municipal
water systems in the Krugersdorp region of South Africa where the
Demo Plant is located. Whilst the power outage was rectified within
24 hours, the water outage had a more significant impact as
multiple industrial and residential zones ran dry simultaneously.
These events coincided with extended maintenance works on multiple
water systems.
Whilst such incidents are not uncommon within
the South African context, this is the first outage that has
impacted the Demo Plant.
Water supply was reinstated on December 17.
Without water, commissioning work on site was
restricted to areas where water could be recycled and reused. The
boiler, which requires fresh water to generate steam, was
temporarily shut down. This resulted in a delay of the C4 Hot
Commissioning of the crystallisers which was underway at the time
of the outage.
Demo Plant Construction and
Commissioning Update
The construction of the Demo Plant, which
consists of nine Process Modules (each a self-contained process
system within a fixed frame) is largely complete. Full construction
completion is due within the next week.
Since the news release (“NR”)
dated November 14, 2024, commissioning continues apace. Various
parts of the Demo Plant are now in the C4 phase, whilst other areas
are C3 complete and waiting for first reagent delivery.
Whilst C4 commissioning is typically undertaken
on a broader process level, Giyani saw an opportunity to
pre-emptively work with the crystallisers in isolation and gain
important information and learnings ahead of the availability of
the full process flow.
The hot commissioning of the mill, leach, and
impurity removal process areas is expected to commence following
the delivery of first-fill reagents, which is imminent.
The filter presses used for various solid/liquid
separation stages are progressing rapidly through C2 and C3
commissioning, and will be fully commissioned as soon as slurry is
available from the upstream processes.
Figure 2: The Newly Commissioned HMI for
the Filter Presses
The Demo Plant laboratory, independently
installed and operated by Quality Lab Services (QLS, a Minopex
company) is nearing full operational capacity, with only the
calcination furnaces yet to be completed. The key instrumentation
of ICP-OES and XRF are both fully operational and the first sets of
full analytical assays have been completed.
Stages of commissioning:
-
C1 – Full mechanical completion (individual Process Modules)
-
C2 – Dry testing, direction testing, loop testing (individual
Process Modules)
-
C3 – Cold/Water Commissioning, software testing (individual Process
Modules)
-
C4 – Hot Commissioning with reagents and steam (typically full
Process)
-
C5 – Production Ramp-up (full Process)
Figure 3: Onsite Independent Lab –
Preparation Area
In addition to progress at the Demo Plant,
concurrent metallurgical test-work is underway to further optimize
the flowsheet. Giyani is focused on further reducing reagent use
and improving both the operating cost and carbon profiles for the
Commercial Plant, planned for construction adjacent to Giyani’s
extensive 100% owned manganese oxide ore sources in Southern
Botswana.
The Demo Plant is designed at a scale factor of
approximately 1:10 to the planned Commercial Plant. This provides
robust and reliable scale-up from the Demo Plant data when the
Commercial Plant is implemented. To illustrate, the leach tanks
have a 60cm diameter in the Demo Plant and this is expected to be
8-10x larger at approximately 5m in the Commercial Plant.
Figure 4: Demo Plant Render
Demo Plant Operational
Overview
The development of all process plant standard
operating procedures (“SOPs”) is complete and
Minopex will continue to refine these procedures to ISO
International Standards. As the Demo Plant is a direct copy of the
anticipated Commercial Plant, at a 1:10 scale, the overall
operating requirements and system requirements are very similar.
Alongside the engineering, commercial and research benefits of the
Demo Plant, the availability of mature SOPs will facilitate a
smooth transition to full-scale commercial production.
The independent, fully ISO-certified laboratory
will allow commercial-level metal accounting and provide rapid
assay turnaround times to enable effective operation of the Demo
Plant. The laboratory is near complete and is operational, with key
equipment such as the ICP-OES and XRF already in active use.
The laboratory, and all the procedures and
methods associated with it, can be transferred directly to the
Commercial Plant, enabling a tried and tested laboratory set-up
available on Day 1 of Commercial Plant commissioning.
Figure 5: Onsite Independent Lab –
ICP-OES and XRF Instruments
About Giyani
Giyani is focused on becoming a dominant
western-world producer of sustainable, low carbon high purity
battery grade manganese for the electric vehicle
(“EV”) industry. The Company has developed a
proprietary hydrometallurgical process to produce battery grade
manganese (HPMSM), a lithium-ion battery cathode precursor material
critical for EVs.
The Company has secured financing of US$26m from
two strategic partners, ARCH Sustainable Resources Fund LP and the
Industrial Development Corporation of South Africa, enabling it to
progress the K.Hill battery-grade manganese project in Botswana to
construction by building and operating the Demo Plant and
completing a Definitive Feasibility Study in 2025.
Additional information and corporate documents
may be found on www.sedarplus.ca and on Giyani Metals Corp. website
at https://giyanimetals.com/.
Qualified Persons / NI 43-101
Disclosures
A National Instrument 43-101 (“NI
43-101”) technical report including results of the PEA and
the MRE can be found on SEDAR+ at www.sedarplus.ca and made
available on the Company's website at
https://giyanimetals.com/.
Justin Taylor CEng
FIMMM QMR BSc Eng (Chem) is a qualified person, as defined by NI
43-101. Mr. Taylor is the Company’s Group Process Engineer and has
reviewed and approved the scientific and technical content
contained in this news release but is not independent for the
purposes of NI 43-101.
On behalf of Giyani Metals Corp.
Charles FitzRoy, President and CEO
Contact:
|
Giyani Metals Corp.Charles FitzRoy, President
& CEO |
cfitzroy@giyanimetals.com Tel: +1289-291-7632 |
|
|
|
|
|
|
Tavistock, Corporate Communications Tara
Vivian-Neal / Josephine Clerkin |
giyani@tavistock.co.uk Tel: +44 20 7920 3150 |
|
|
|
|
|
Neither the TSX Venture Exchange (the "TSXV")
nor its Regulation Services Provider (as that term is defined in
the policies of the TSXV) accepts responsibility for the adequacy
or accuracy of this news release.
Forward-Looking Information
This news release contains "forward-looking
information" within the meaning of applicable Canadian securities
legislation. All statements in this news release, other than
statements of historical fact, that address events or developments
that Giyani expects to occur, are "forward-looking statements".
Forward-looking statements are statements that are not historical
facts and are generally, but not always, identified by the words
"expects", "does not expect", "plans", "anticipates", "does not
anticipate", "believes", "intends", "estimates", "projects",
"potential", "scheduled", "forecast", "budget" and similar
expressions, or that events or conditions "will", "would", "may",
"could", "should" or "might" occur.
Such statements include without limitation: the
Company the ongoing construction, commissioning and operation of
the Demo Plant, and timing thereof, the completion of hot
commissioning, the delivery of product, and entering into offtake
agreements.
All such forward-looking statements are based on
the opinions and estimates of the relevant management as of the
date such statements are made and are subject to certain
assumptions, important risk factors and uncertainties, many of
which are beyond Giyani's ability to control or predict.
Forward-looking statements are necessarily based on estimates and
assumptions that are inherently subject to known and unknown risks,
uncertainties and other factors that may cause actual results,
level of activity, performance or achievements to be materially
different from those expressed or implied by such forward-looking
statements. In the case of Giyani, these facts include anticipated
operations in future periods, planned construction and development
of its properties and facilities, and plans related to its business
and other matters that may occur in the future. This information
relates to analyses and other information that is based on
expectations of future performance and planned work programs.
Forward-looking information is subject to a
variety of known and unknown risks, uncertainties and other factors
which could cause actual events or results to differ from those
expressed or implied by the forward-looking information, including,
without limitation: inherent exploration hazards and risks; risks
related to exploration and development of natural resource
properties; uncertainty in Giyani's ability to obtain funding;
commodity price fluctuations; recent market events and conditions;
risks related to governmental regulations; risks related to
obtaining necessary licences and permits; risks related to Giyani's
business being subject to environmental laws and regulations; risks
related to the Company's mineral properties being subject to prior
unregistered agreements, transfers, or claims and other defects in
title; risks relating to competition from larger companies with
greater financial and technical resources; risks relating to the
inability to meet financial obligations under agreements to which
they are a party; ability to recruit and retain qualified
personnel; and risks related to the Company's directors and
officers becoming associated with other natural resource companies
which may give rise to conflicts of interests. This list is not
exhaustive of the factors that may affect Giyani's forward-looking
information. Should one or more of these risks and uncertainties
materialize, or should underlying assumptions prove incorrect,
actual results may vary materially from those described in the
forward-looking information or statements.
Giyani's forward-looking information is based on
the reasonable beliefs, expectations and opinions of the Company's
respective management on the date the statements are made, and
Giyani does not assume any obligation to update forward looking
information if circumstances or management's beliefs, expectations
or opinions change, except as required by law. For the reasons set
forth above, investors should not place undue reliance on
forward-looking information. For a complete discussion with respect
to Giyani and risks associated with forward-looking information and
forward-looking statements, please refer to Giyani's continuous
disclosure documents which are filed on SEDAR+ at
www.sedarplus.ca.
Photos accompanying this announcement are available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/27b3cb1a-8429-4656-88f8-0887ab623f6f
https://www.globenewswire.com/NewsRoom/AttachmentNg/e5ca9885-5e2e-40c0-abca-ade7577e9df2
https://www.globenewswire.com/NewsRoom/AttachmentNg/ee384846-d457-4980-8616-ff015e28425e
https://www.globenewswire.com/NewsRoom/AttachmentNg/5269c5c6-7042-41d4-93d6-765eace2c337
https://www.globenewswire.com/NewsRoom/AttachmentNg/81237c7a-b708-4574-86b2-31bf77e81933
Giyani Metals (TSXV:EMM)
Historical Stock Chart
Von Dez 2024 bis Jan 2025
Giyani Metals (TSXV:EMM)
Historical Stock Chart
Von Jan 2024 bis Jan 2025