Bunker Hill Mining Corp. (“
Bunker
Hill” or the “
Company”) (
TSX-V:
BNKR |OTCQB: BHLL) announces it has been advanced the
second tranche, in the amount of US$5 million under the senior
secured credit facility (the ”
Standby Facility”)
with Sprott Private Resource Streaming and Royalty Corp.
(“
Sprott”), pursuant to which Sprott has agreed to
advance up to US$21 million under the Standby Facility, to fund
development costs of the Company’s Bunker Hill Mine located in
Kellogg, Idaho (the “
Bunker Hill Mine”), subject
to the satisfaction of certain conditions.
Sam Ash, President and CEO, stated, "As we enter
the end of an extremely productive year at Bunker Hill, we are
pleased to report the advance of Sprott’s second tranche in the
amount of US$5 million and provide an update on our work on-site,
particularly in the underground. We have readied five stopes for
mining in the UTZ area of the upper mine, near the entrance of
Russell Portal, and are close to completing the geotechnical
stabilization of the main ramp at it cuts the Cate Fault. Once
done, the team will complete the rehabilitation of the ramp down to
the 8-2 Level and prepare the chosen stopes on that level for
mining."
PROGRESS UPDATE - KELLOGG
SITE
Grid Power has now been connected to the
processing and associated facilities, enabling, amongst other
things, the establishment of outside lighting along the conveyors.
Work in the Kellogg Yard continues with the conveyors, crusher
tower, concentrate load-out facility and the tailings filter press.
While inside the concentrator building, the final installation of
the mezzanine floors is completed in anticipation of the placement
of the remaining floatation cells. Piping and electrical fitting
continues, along with the installation of lubrication systems for
the mill.
FIGURE 1: LIGHTS COMPLETED ON THE CONVEYORS LINKING THE
CONCENTRATOR TO THE CRUSHER AND THE CONCENTRATE LOAD OUT
AREA
FIGURE 2: MEZZANINE ACCESS LEVELS INSTALLED AROUND THE
MAIN BALL MILL
PROGRESS UPDATE -
UNDERGROUND
Operating from the mining base in Wardner, the
Company’s underground mining team have nearly completed the
stabilization of the ramp as it cuts across the Cate Fault. Once
final grouting has been done and power and ventilation reconnected,
the teams will recommence with the ramp rehabilitation to the 8-2
Level before preparing stopes there for mechanized long-hole
mining.
Closer to the mining base and the Russell Portal
and in the UTZ area, the teams have prepared five faces for
mechanized cut-and-fill mining whilst concurrently stockpiling
underground ore collected during the ramp rehabilitation and
associated development work. Essential preparatory work has begun,
designed to ensure maximum mine plan optionality during the next
commissioning and ramp-up phases of the mine restart.
Further optimization of the mine plan continues
alongside ongoing preparation of an updated mineral resource
estimate, which the Company plans to issue in Q1 2025.
FIGURE 3: THE GEOTECHNICAL STABILIZATION OF THE MAIN
RAMP AS IT CUTS THE CATE FAULT BETWEEN THE 5 AND 6
LEVELS
FIGURE 4: THE REHABILITATION OF THE UTZ AREA AND THE
PREPARATION OF 5 STOPES FOR MINING
FINANCING NEXT STEPSAs outlined
in the Company’s December 13, 2024 news release, the Company
intends to draw in stages upon the Standby Facility, whilst
concurrently engaging in negotiations with its strategic partners
for potential offtake or similar financing for up to an additional
$30 million.
There is no guarantee the Company will satisfy
any or all of the conditions of further drawdowns under the Standby
Facility. For further details of the Standby Facility, please
see the Company’s June 26, 2023 news release.
The Company looks forward to updating
shareholders on further successful milestones over the near
term.
ABOUT BUNKER HILL MINING
CORP.
Under Idaho-based leadership, Bunker Hill
intends to sustainably restart and develop the Bunker Hill Mine as
the first step in consolidating and then optimizing several mining
assets into a high-value portfolio of operations centered initially
in North America. Information about the Company is available on its
website, www.bunkerhillmining.com, or within the SEDAR+ and EDGAR
databases.
On behalf of Bunker Hill Mining
Corp.
Sam AshPresident and Chief Executive Officer
For additional information, please
contact:
Brenda DaytonVice President, Investor
RelationsT: 604.417.7952E: brenda.dayton@bunkerhillmining.com
Cautionary Statements
Neither the TSX Venture Exchange (the
“TSX-V”) nor its Regulation Services Provider (as
that term is defined in the policies of the TSX-V) accepts
responsibility for the adequacy or accuracy of this news
release.
Certain statements in this news release are
forward-looking and involve a number of risks and uncertainties.
Such forward-looking statements are within the meaning of that term
in Section 27A of the Securities Act and Section 21E of the U.S.
Securities Exchange Act of 1934, as amended, as well as within the
meaning of the phrase ‘forward-looking information’ in the Canadian
Securities Administrators’ National Instrument 51-102 – Continuous
Disclosure Obligations (collectively, “forward-looking
statements”). Forward-looking statements are not comprised
of historical facts. Forward-looking statements include estimates
and statements that describe the Company’s future plans, objectives
or goals, including words to the effect that the Company or
management expects a stated condition or result to occur.
Forward-looking statements may be identified by such terms as
“believes”, “anticipates”, “expects”, “estimates”, “may”, “could”,
“would”, “will”, “plan” or variations of such words and
phrases.
Forward-looking statements in this news release
include, but are not limited to, statements regarding: the
Company’s objectives, goals or future plans, including the restart
and development of the Bunker Hill Mine and planned geotechnical
work; the achievement of future short-term, medium-term and
long-term operational strategies; the Company issuing an updated
resource estimate in Q1 2025; further draws by the Company on the
Standby Facility, including the Company satisfying any or all of
the conditions in connection therewith; and the Company securing
potential offtake or similar financing for an additional $30
million from its strategic investors. Forward-looking statements
reflect material expectations and assumptions, including, without
limitation, expectations and assumptions relating to: Bunker Hill’s
ability to receive sufficient project financing for the restart and
development of the Bunker Hill Mine on acceptable terms or at all;
further drilling and geotechnical work supporting the planned
restart and operations at the Bunker Hill Mine; the future price of
metals; and the stability of the financial and capital markets.
Factors that could cause actual results to differ materially from
such forward-looking statements include, but are not limited to,
those risks and uncertainties identified in public filings made by
Bunker Hill with the U.S. Securities and Exchange Commission (the
“SEC”) and with applicable Canadian securities
regulatory authorities, and the following: the Company’s ability to
operate as a going concern and its history of losses; the Company’s
inability to raise additional capital for project activities,
including through equity financings, concentrate offtake financings
or otherwise; the fluctuating price of commodities; capital market
conditions; restrictions on labor and its effects on international
travel and supply chains; failure to identify mineral resources;
further geotechnical work not supporting the continued development
of the Bunker Hill Mine or the results described herein; failure to
convert estimated mineral resources to reserves; the preliminary
nature of metallurgical test results; the Company’s ability to
raise sufficient project financing, on acceptable terms or at all,
to restart and develop the Bunker Hill Mine and the risks of not
basing a production decision on a feasibility study of mineral
reserves demonstrating economic and technical viability, resulting
in increased uncertainty due to multiple technical and economic
risks of failure which are associated with this production decision
including, among others, areas that are analyzed in more detail in
a feasibility study, such as applying economic analysis to
resources and reserves, more detailed metallurgy and a number of
specialized studies in areas such as mining and recovery methods,
market analysis, and environmental and community impacts and, as a
result, there may be an increased uncertainty of achieving any
particular level of recovery of minerals or the cost of such
recovery, including increased risks associated with developing a
commercially mineable deposit, with no guarantee that production
will begin as anticipated or at all or that anticipated production
costs will be achieved; the Company requiring additional capital
expenditures than anticipated, resulting in delays in the expected
restart timeline; failure to commence production would have a
material adverse impact on the Company's ability to generate
revenue and cash flow to fund operations; failure to achieve the
anticipated production costs would have a material adverse impact
on the Company’s cash flow and future profitability; delays in
obtaining or failures to obtain required governmental,
environmental or other project approvals; political risks; changes
in equity markets; uncertainties relating to the availability and
costs of financing needed in the future; the inability of the
Company to budget and manage its liquidity in light of the failure
to obtain additional financing, including the ability of the
Company to complete the payments pursuant to the terms of the
agreement to acquire the Bunker Hill Mine complex; inflation;
changes in exchange rates; fluctuations in commodity prices; delays
in the development of projects; and capital, operating and
reclamation costs varying significantly from estimates and the
other risks involved in the mineral exploration and development
industry. Although the Company believes that the assumptions and
factors used in preparing the forward-looking statements in this
news release are reasonable, undue reliance should not be placed on
such statements or information, which only applies as of the date
of this news release, and no assurance can be given that such
events will occur in the disclosed time frames or at all, including
as to whether or when the Company will achieve its project finance
initiatives, or as to the actual size or terms of those financing
initiatives, or whether and when the Company will achieve its
operational and construction targets. The Company disclaims any
intention or obligation to update or revise any forward-looking
information, whether as a result of new information, future events
or otherwise, other than as required by law. No stock exchange,
securities commission or other regulatory authority has approved or
disapproved the information contained herein.
Readers are cautioned that the foregoing risks
and uncertainties are not exhaustive. Additional information on
these and other risk factors that could affect the Company’s
operations or financial results are included in the Company’s
annual report and may be accessed through the SEDAR+ website
(www.sedarplus.ca) or through EDGAR on the SEC website
(www.sec.gov).
Photo accompanying this announcement are available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/84b6619d-0f16-4cc7-8b4f-c33ca3ed0982
https://www.globenewswire.com/NewsRoom/AttachmentNg/16dc880f-4476-4c6d-b42b-f8f25a9de4be
https://www.globenewswire.com/NewsRoom/AttachmentNg/c96bb465-3a57-4050-817c-a67136965eb2
https://www.globenewswire.com/NewsRoom/AttachmentNg/467bbbf6-cd5b-4749-a8e2-0e9ca1a896be
Bunker Hill Mining (TSXV:BNKR)
Historical Stock Chart
Von Dez 2024 bis Jan 2025
Bunker Hill Mining (TSXV:BNKR)
Historical Stock Chart
Von Jan 2024 bis Jan 2025