Western GeoPower Corp., (TSX VENTURE:WGP)(FRANKFURT:WE6) a renewable energy
company, today announced that independent consultants GeothermEx, Inc., have
recommended a drilling program at the South Meager geothermal reservoir to
target a recently-identified zone of high permeability which has demonstrated
commercial potential.


Reporting on the results of airlift-assisted flow-testing of well MC-8,
GeothermEx projected that a new deviated well starting from a lower wellhead
elevation into the same permeable zone and at a much shorter vertical depth than
well MC-8 would flow at the equivalent of more than 6 megawatts (MW) of
electrical energy. Well MC-8 itself was unable to sustain self-flow following
air lifting due to physical constraints imposed by the deep water table.


To access the zone of permeability, GeothermEx has designed a deviated well
starting from the valley floor with a projected true vertical depth of 1,660
meters and a total wellbore length of less than 2,000 meters. Wellbore
simulation indicates that this well could flow at the equivalent of 6.4 MW of
electrical output at a wellhead pressure of 140 psig. If the reservoir fluid
encountered by this new well is at a greater temperature than the temperature
measured in MC-8, or should the well be drilled deeper than the targeted 1,660
meters, the megawatt capacity of the well could increase accordingly.


"The recent flow testing has corroborated our earlier projection of high
temperature, reasonable permeability and a deep water table at South Meager,"
said Dr. Subir Sanyal, President of GeothermEx. "While a deep water table has
limited the well's productivity, commercial productivity can still be achieved
in a well drilled from the valley floor and targeted to the permeable zones in
wells MC-8 and MC-6."


Several excellent and easily-accessible locations for new drill pads are
available on the valley floor with ready access to the permeable zones in MC-8
and MC-6. The Company intends to commence the permitting process for the future
wells once the snow has cleared sufficiently to allow surveying of the sites.


"Our understanding of the geothermal reservoir characteristics at South Meager
has increased substantially," said Kenneth Macleod, President and CEO of Western
GeoPower. "We can now focus on securing the funding and permitting necessary to
complete the drilling program and prepare a feasibility report on the project."


In 2004 and 2005, wells MC-6, MC-7 and MC-8 were drilled on a single pad
approximately 700 vertical meters above Meager Creek on the shoulder of Pylon
Peak. The pad was located closer to the projected upflow zone of the geothermal
reservoir in comparison with earlier pads located on the valley floor.
Subsequent testing confirmed that two of the wells, MC-6 and MC-8 encountered
significant permeability and all three wells showed higher temperatures at
shallower depth than previous wells. However, the presence of the geothermal
water table at over 500 meters below the pad has inhibited the ability of the
recent wells to self flow. The wells are being maintained for additional testing
purposes and future enhancements are being considered, such as deepening and/or
sidetracking, once additional permeable targets are identified by future
drilling activities. Further drilling is required to define the full commercial
power production potential for South Meager.


Western GeoPower continues to liaise with provincial government agencies and key
community and First Nations stakeholders in preparation for submission of an
Application for Certification of the South Meager project under the BC
Environmental Assessment Act. The Company also is actively engaged in soliciting
federal funding for project development and working directly with the British
Columbia government on the updating of provincial geothermal legislation and
regulations.


About Western GeoPower Corp.

Western GeoPower Corp. is a renewable energy company dedicated to the
development of geothermal energy projects for the delivery of clean,
sustainable, baseload electricity generation. The Company is developing The
Western GeoPower Unit 1 geothermal power plant at The Geysers Geothermal Field
in California, United States and the South Meager Geothermal Project in British
Columbia, Canada.


On behalf of the Board of Western GeoPower Corp

Kenneth MacLeod, President & CEO

Cautionary Note Regarding Forward-Looking Statements

Statements in this release that are forward-looking are subject to various risks
and uncertainties concerning the specific factors identified above that reflect
the Company's expectations and projections about its future results. The Company
has tried whenever possible to identify these forward-looking statements which
include but are not limited to, words such as "anticipates," believes,"
"estimates," "expects," "plans," "intends," "potential," and similar
expressions. Although the Company believes the expectations expressed in such
forward-looking statements are based on reasonable assumptions, such statements
are not guarantees of future performance and actual results or developments may
differ materially from those in the forward-looking statements. Investors are
cautioned that any such statements are not guarantees of future performance and
that actual results or developments may differ materially from those projected
in the forward-looking statements. The Company disclaims any obligation or
intention to update or to revise any forward-looking statement, whether as a
result of new information, future events or otherwise. Such information
contained herein represents management's best judgment as of the date hereof
based on information currently available.


Western Geopower Corp Com Npv (TSXV:WGP)
Historical Stock Chart
Von Jun 2024 bis Jul 2024 Click Here for more Western Geopower Corp Com Npv Charts.
Western Geopower Corp Com Npv (TSXV:WGP)
Historical Stock Chart
Von Jul 2023 bis Jul 2024 Click Here for more Western Geopower Corp Com Npv Charts.