Monument Mining Limited (TSX-V: MMY and FSE: D7Q1) ("Monument" or
the "Company") is pleased to announce an update at Selinsing Gold
Mine where the Company recently achieved commercial production of
its newly constructed flotation processing plant.
President and CEO Cathy Zhai commented, "We are
very pleased with the continued progress and optimization of the
Selinsing Sulphide gold flotation plant. The production is expected
to be stabilized in the 2024 calendar year and cash flow sustained.
Longer term off take contracts are in progress. Export permits
continue to be renewed every six months with government support.
Gold prices are above the $2,000 per ounce level in the new year
which is in our favor.”
Ms. Zhai emphasizes: “In 2024 we will provide
further training to our senior management with a value-added
approach to lead to excellent performance. Our corporate focus in
2024 is business development in Malaysia, Western Australia and
elsewhere. We are positioning Monument to be a fully funded
producing company with upside growth potential to realize
shareholder value in the marketplace.”
Figure 1: Selinsing Flotation
Plant
Figure 1 is available
at https://www.globenewswire.com/NewsRoom/AttachmentNg/2b5c6533-c589-421c-b3bb-2a2f50ee3352
At the opening of this new year, the production
objective of Selinsing Gold Mine is to streamline and optimize the
flotation plant and operations to achieve the best financial
performance. The Company continues to improve operational
efficiencies through consolidating Selinsing operating activities
and resources, and removal of bottlenecks including: plant
performance improvements, mining cycle harmonization, tailing
storage facilities (TSF) upgrade, refining the gold concentrate
warehousing, shipping and sales process, and security
enhancements.
Plant Process Improvements
The flotation plant achieved the design capacity
of 119 tph in early December 2023, however mill feed rate continues
to be hampered by the bottleneck at the McLanahan filter press.
Recent improvements to the filter press operation have included the
installation of pressure regulators to reduce the compressed air
pressure for the core blow and cake dry cycles; the pressure
reduction has certainly reduced the frequency of filter cloth
failure. Torn filter cloths have been replaced as required by local
and internationally sourced cloths. Worn filter plates are being
repaired locally and new units have been ordered from the
manufacturer and are expected to arrive at site in March 2024.
Figure 2. Flotation Control
Cabin
Figure 2 is available
at https://www.globenewswire.com/NewsRoom/AttachmentNg/1ad6f366-5840-4d9c-9140-02a9541f88f4
Ongoing plant improvements included an upgrade
to the concentrate thickener underflow pipeline to the filter press
surge tank. One of the concentrate thickener overflow pumps was
replaced with a bigger pump along with a new pipeline; a standby
pump will be installed once refurbishment work is completed.
Modifications to the cleaner flotation circuit were initiated to
allow cleaning of the first rougher concentrate to produce a
cleaner final concentrate during processing of transition ore
types.
Figure 3. Atomic Absorption Spectrometer
at Assay Laboratory
Figure 3 is available
at https://www.globenewswire.com/NewsRoom/AttachmentNg/4e093972-16f7-49eb-b27a-3ad32fd59e09
Flotation recovery continued to be variable due
to the inconsistent quality of the transition ores processed. New
flocculant was received for the water recovery thickener, allowing
the flotation circuit to operate at the design pH 9.0-9.5. Dosing
of the sulphidising agent sodium sulphide continued along with
copper sulphate as activator. Some daily recoveries of over 80% and
sometimes 90% were recorded, with reconciled recovery of 73.6%
reported for December 2023.
Construction of the concentrate shed has been
completed and the lighting power supply connected. Roofing was
installed over the rougher and cleaner flotation cells. The one
tonne bulk bagging system was delivered to Port Klang and
transported to the Selinsing site. The contract for the new
flotation tailings hopper was awarded and fabrication initiated;
civil works commenced in mid-December 2023 and installation of the
tailings hopper and associated pipework is scheduled in the 1st
week of February 2024.
The procurement plan and strategies have been
tabled for review focusing on critical spare parts for the sulphide
flotation plant and by allocating resources to enhance this
improvement with the aim to avoid any unforeseen stoppage of plant
operations.
Mining and Ore Stockpile
Buildup
Mining of Buffalo Reef pits continued with
Stages 1 and 2 mined at BRC2 and BRC3 pits and Stage 1 started at
BRC4. Delivery of fresh and transition ore continued and the run of
mine (ROM) stockpile was increased to 255,000 tonnes, which is over
three months’ processing plant capacity, at the end of December
2023 and critically ahead of the imminent Northeast monsoon
season.
A new three-year mining contract was negotiated
with the long-term mining contractor Minetech, starting January
1st, 2024. Ten grade control drilling rigs are currently
operational and performing well; the Minetech fleet of eight
excavators and around forty dump trucks have shown good
availability.
To smooth mining cycle, capacity of the
preparation lab has been reviewed and improved with two new
pulverisers installed at the new sample preparation laboratory. The
ventilation system has been installed and is under commissioning to
improve the working environment and avoid contamination.
Routine deliveries of ammonium nitrate emulsion
to the Austin Powders explosives depot continued. The site-based 13
tonne capacity emulsion tanker was replaced by a 16-tonne capacity
unit and blasting was carried out on up to five days per week as
required.
Construction of the TSF upgrade resumed in
August 2023. Zone A and Zone C fill to 540 mRL was completed at the
main embankment and the upstream slope was lined with riprap to
protect against erosion. Construction of the TSF south embankments
was completed and riprap placed on the upstream slopes. The new
spillway will be constructed in January 2024 followed by the
installation of the seepage sumps and related pipework at the toe
of the main embankment. The overall TSF upgrade is expected to be
completed by February 2024.
Gold Concentrate Shipments and
Sales
To date the flotation plant has produced over
16,000 tonnes of concentrates at a grade of 37 g/t Au. Shipments
have been made to three separate buyers and negotiations continue
with several potential new customers. To date over 12,500 tonnes of
concentrate have been delivered to Johor and Port Klang Free Zones.
Export permits have been renewed with the relevant state
authorities as required. Transport of the latest delivery of 3,500
wet metric tonnes to Port Klang Free Zone has been completed with
vessel to depart in mid-January 2024. Sale of a further 3,000
tonnes of concentrate currently available has been finalized and
shipment preparation of the concentrate to the port is in
progress.
Warehouse review and improvements are ongoing
including tightened up of security features.
Stock Compensation
To reward the success of placing the Sulphide
Gold Project into commercial production, the Company also announces
that the board has granted under its equity compensation plans a
total 3.4 million restricted share units and 3.8 million incentive
stock options to its directors, officers and employees. Each stock
option is exercisable at a price of $0.145 for a term of five years
from the date of grant with a three years vesting period.
About Monument
Monument Mining Limited (TSX-V: MMY, FSE: D7Q1)
is an established Canadian gold producer that 100% owns and
operates the Selinsing Gold Mine in Malaysia and the Murchison Gold
Project in the Murchison area of Western Australia. It has 20%
interest in Tuckanarra Gold Project jointly owned with Odyssey Gold
Ltd in the same region. The Company employs approximately 250
people in both regions and is committed to the highest standards of
environmental management, social responsibility, and health and
safety for its employees and neighboring communities.
Cathy Zhai, President and CEOMonument Mining
LimitedSuite 1580 -1100 Melville StreetVancouver, BC V6E 4A6
FOR FURTHER INFORMATION visit the company web
site at www.monumentmining.com or contact:
Richard Cushing, MMY Vancouver T:
+1-604-638-1661 x102 rcushing@monumentmining.com
"Neither TSX Venture Exchange nor its Regulation
Services Provider (as that term is defined in the policies of the
TSX Venture Exchange) accepts responsibility for the adequacy or
accuracy of this release."
Disclaimer Regarding Forward-Looking
Statements
This news release includes statements containing
forward-looking information about Monument, its business and future
plans ("forward-looking statements"). Forward-looking statements
are statements that involve expectations, plans, objectives or
future events that are not historical facts and include the
Company's plans with respect to its mineral projects, expectations
regarding the completion of the ramp-up period to target production
level at Selinsing and the timing thereof, expectations regarding
the Company’s continuing ability to source explosives from
suppliers, expectations regarding completion of the proposed
storage shed and ammonium nitrate depot and the timing thereof, and
the timing and results of the other proposed programs and events
referred to in this news release. Generally, forward-looking
information can be identified by the use of forward-looking
terminology such as "plans", "expects" or "does not expect", "is
expected", "budget", "scheduled", "estimates", "forecasts",
"intends", "anticipates" or "does not anticipate", or "believes",
or variations of such words and phrases or state that certain
actions, events or results "may", "could", "would", "might" or
"will be taken", "occur" or "be achieved". The forward-looking
statements in this news release are subject to various risks,
uncertainties and other factors that could cause actual results or
achievements to differ materially from those expressed or implied
by the forward-looking statements. These risks and certain other
factors include, without limitation: risks related to general
business, economic, competitive, geopolitical and social
uncertainties; uncertainties regarding the results of current
exploration activities; uncertainties in the progress and timing of
development activities, including those related to the ramp-up
process at Selinsing and the completion of the proposed storage
shed and ammonium nitrate depot; uncertainties and risks related to
the Company’s ability to source explosives from suppliers; foreign
operations risks; other risks inherent in the mining industry and
other risks described in the management discussion and analysis of
the Company and the technical reports on the Company's projects,
all of which are available under the profile of the Company on
SEDAR at www.sedar.com. Material factors and assumptions used to
develop forward-looking statements in this news release include:
expectations regarding the estimated cash cost per ounce of gold
production and the estimated cash flows which may be generated from
the operations, general economic factors and other factors that may
be beyond the control of Monument; assumptions and expectations
regarding the results of exploration on the Company's projects;
assumptions regarding the future price of gold of other minerals;
the timing and amount of estimated future production; assumptions
regarding the timing and results of development activities,
including the ramp-up process at Selinsing and the completion of
the proposed storage shed and ammonium nitrate depot; expectations
that the Company will continue to be able to source explosives from
suppliers in a timely manner; costs of future activities; capital
and operating expenditures; success of exploration activities;
mining or processing issues; exchange rates; and all of the factors
and assumptions described in the management discussion and analysis
of the Company and the technical reports on the Company's projects,
all of which are available under the profile of the Company on
SEDAR at www.sedar.com. Although the Company has attempted to
identify important factors that could cause actual results to
differ materially from those contained in forward-looking
statements, there may be other factors that cause results not to be
as anticipated, estimated or intended. There can be no assurance
that such statements will prove to be accurate, as actual results
and future events could differ materially from those anticipated in
such statements. Accordingly, readers should not place undue
reliance on forward-looking statements. The Company does not
undertake to update any forward-looking statements, except in
accordance with applicable securities laws.
Monument Mining (TSXV:MMY)
Historical Stock Chart
Von Nov 2024 bis Dez 2024
Monument Mining (TSXV:MMY)
Historical Stock Chart
Von Dez 2023 bis Dez 2024