Rio Alto Mining Limited ("Rio Alto" or the "Company") (TSX
VENTURE:RIO)(OTCQX:RIOAF)(BVLAC:RIO)(DBFrankfurt:MS2) is pleased to announce
updated resource and reserve estimates and financial estimates for the La Arena
Project in north central Peru. The resources and reserves estimate and financial
model review was completed by the Company's independent engineers, Coffey Mining
Pty. Ltd. ("Coffey Mining"), based on information from recently completed
studies. These estimates will be incorporated in a National Instrument 43-101
Technical Report with an effective date of July 31, 2010 to be filed on the
Company's SEDAR profile within 45 days. Certain information in this announcement
is compared to the Company's previous NI 43-101 Technical Report, with an
effective date of March 31, 2008, on the La Arena Project (the "March 2008
Report"). The March 2008 Report may be referenced within Rio Alto's SEDAR
profile at www.sedar.com.


Mineral Reserve Highlights (comparison to the March 2008 Report)



--  Gold in probable oxide mineral reserves increased 40% from 587,000 oz Au
    to 821,000 oz Au 
--  Recoverable gold in probable oxide mineral reserves increased 65% from
    385,000 oz Au to 634,000 oz Au 
--  Oxide metallurgical gold recoveries increased from 65% to 80% 
--  Cyanide consumption reduced from 0.5kg / tonne of ore to 0.2kg / tonne
    of ore 
--  Gold in probable sulphide mineral reserves increased 24% from 1,415,000
    oz Au to 1,748,000 oz Au 
--  Copper in probable sulphide mineral reserves increased 24% from 1,274M
    lbs Cu to 1,574M lbs Cu 
--  Total metal in probable reserves increased to 2,569,000 oz Au and 1,574M
    lbs Cu 



(note: all oz rounded to nearest 1,000 and lbs rounded to nearest 1,000,000)

Financial and Technical Highlights

The probable mineral reserves in oxides and the financial estimates for gold
oxide production are prepared at the feasibility study level and have been based
on detailed engineering and vendor or contractor quotations. The probable
mineral reserves in sulphide material are prepared at the pre- feasibility study
level and are based on engineering estimates. Base Case (100% equity) financial
estimates for the stand alone gold oxide project and the stand alone copper/gold
sulphide project are presented on a pre-tax basis as the two projects will share
much of the same infrastructure and will be taxed as one entity; not two
separate entities. Base Case financial estimates for the combined gold oxide and
copper/gold sulphide project are presented on a pre and after tax basis. Metal
prices used in the Base Case financial estimates were $1,000 per oz Au and $2.50
per lb copper.


Gold Oxides Only - Years 1 to 7



--  Base case pre-tax NPV(8) of US$ 140 million and an IRR of 121% 
--  At $1,250/oz Au, pre-tax NPV(8) increases to US$247 million and an IRR
    of 190% 
--  Process rate of 10,000 t/day in year 1 increasing to 24,000 t/day during
    year 2 and continuing until year 7 
--  Start-up capital expenditures of approximately US$44 million (US$51
    million including refundable value added tax) including working capital
    and contingency allowance of US$4.1 million. Approximately US$20 million
    of this has been spent to-date 
--  Life of Mine capital expenditures of US$67 million 
--  Life of mine cash cost of US$508 per oz Au; Life of mine strip ratio
    1.37 : 1 
--  Oxide gold production: In year 1 about 75,000 oz Au; years 2 to 6,
    production is expected to range between 96,000 oz Au to 120,000 oz Au
    per year; year 7 about 35,000 oz Au 



Sulphides (Copper & Gold) - Years 4 to 25



--  Base case pre-tax NPV(8) of US$441 million and IRR of 29% 
--  Process rate of 24,000 t/day mill/flotation 
--  Twenty-one year mine life 
--  Life of mine strip ratio of 1.1 to 1 for open pit to a depth of 450m 
--  Start up capital of approximately US$252 million (net of refundable
    value added tax of US$45 million) 
--  Sulphide copper and gold production: 60 million lbs Cu/yr and 31,200 ozs
    Au/yr for life of mine 
--  Life of mine cash cost of US$1.48 per lb Cu (includes transport and TCRC
    charges and gold credit) 
--  At US$3.00 per lb Cu and gold at US$1,000 per oz pre-tax NPV(8) would
    increase to US$697 million and pre-tax IRR would be 39% 
--  At US$1,250 Au/oz and copper at $3.00 per lb pre-tax NPV(8) would
    increase to US$766 million and pre-tax IRR would be 42% 



Combined (Gold Oxides & Copper / Gold Sulphides) - Years 1 to 25



--  Pre-tax NPV(8) of US$519 million and pre-tax IRR of 54% for base case
    with US$1,000/oz Au and US$2.50/lb Cu 
--  After-tax NPV(8) of US$348 million and after-tax IRR of 40% for base
    case of US$1,000/oz Au and US$2.50/lb Cu 
--  Total Start-up Capital expenditure of US$296 million (with working
    capital and contingency) 
--  Strongly leveraged to price of Au and Cu (based on price range of US$
    2.50 - 3.50/lb Cu, US$ 1,000 - 1,200/oz Au). The after-tax NPV(8) ranges
    from a Base Case of US$348 million to US$694 million at US$3.50/lb Cu
    and US$1,200/oz Au as illustrated in the following table. 

----------------------------------------------------
            After-tax NPV(8) US$ Millions           
----------------------------------------------------
                                                    
----------------------------------------------------
                 Au $1,000    Au $1,100    Au $1,200
----------------------------------------------------
Cu $2.50               348          390          432
----------------------------------------------------
Cu $3.00               480          522          563
----------------------------------------------------
Cu $3.50               611          653          694
----------------------------------------------------



Mining & Processing

Work recently completed by Rio Alto and Coffey Mining elevated the status of the
gold oxide project to feasibility level. The copper / gold sulphide project
remains at the pre-feasibility level. A pre-feasibility study on the La Arena
Project was completed by IAMGOLD in November 2006. Rio Alto plans to complete a
feasibility study on the sulphide project with a current target completion date
of Q4, 2012.


Mining at La Arena is based on a conventional truck and shovel, open-pit mine
design with run of mine dump leaching of gold oxide material during the first 7
years of production. The copper/gold sulphide material would be mined from an
open-pit and be treated by milling, flotation, and sulphide concentration of the
copper / gold during years 4 to 25.


Oxide ore production will commence at the rate of 10,000 tonnes/day increasing
to 24,000 tonnes/day during year 2. Mining is planned to be on a two 12 hour
shift, 7 day per week basis using contract mining. Sulphide ore production was
planned at a constant rate of 24,000 tonnes/day for 21 years. The life of mine
pit shell for both oxides and sulphides used a gold price of US$950/oz and
copper price of US$ 2.30/lb. A smaller initial or "starter" pit design in oxides
was based on a pit shell using a gold price of US$ 500/oz. The starter pit
includes ore with a significantly higher grade which has allowed for production
scheduling of higher head grades for the initial 2 years of the 7-year oxide
mine life during the ramp up of production from 10,000 tonnes / day to 24,000
tonnes/day. Oxide gold production will come from both the Ethel pit and the
significantly larger Calaorco pit and will amount to approximately 634,000 oz
Au. Sulphide copper/gold production will come from a much larger and deeper pit
situated on the eastern flank of the Calaorco oxide pit.


Project Summary

Over the life-of-mine, revenue from gold is estimated to be US$5.50/tonne or
approximately 30% of project revenues. Copper revenue per tonne is anticipated
to be US$12.60 or approximately 70% of total revenue. Operating costs will be
approximately 55% of total revenue while the combined Peruvian government
royalty, worker profit participation and income taxes will be in the order of
14% of total revenue. Life of mine capital costs and mine closure costs will
represent approximately 7.4% of total revenue and offsite general and
administration costs will run about US$0.08 per tonne or approximately 0.4% of
total revenue.


The following tables summarize life-of-mine operating and cost information:



-----------------------------------    -----------------------------------
Gold Dump Leach                        Copper Concentrator                
-----------------------------------    -----------------------------------
                                                                          
-----------------------------------    -----------------------------------
                                US$                                    US$
-----------------------------------    -----------------------------------
Oxide Ore Revenue/Tonne       11.05    Sulphide Ore Revenue per           
                                       Tonne                         20.41
-----------------------------------    -----------------------------------
Oxide Ore Cash Cost/Tonne      5.64    Sulphide Ore Cash Cost             
                                       per Tonne                      8.26
-----------------------------------    -----------------------------------
Pre-tax margin/Tonne           5.41    Pre-tax margin/Tonne          12.14
-----------------------------------    -----------------------------------


---------------------------------------------
Per Tonne Ore - Oxide & Sulphide             
---------------------------------------------
                                             
---------------------------------------------
                                US$  Per Cent
---------------------------------------------
Gold Revenue                   5.50     30.4%
---------------------------------------------
Copper Revenue                12.60     69.6%
---------------------------------------------
                              18.10    100.0%
---------------------------------------------
Opex                          10.05     55.5%
---------------------------------------------
Peru Gov't (Taxes & Royalty)   2.49     13.7%
---------------------------------------------
                                             
---------------------------------------------
Net Profit per Tonne           5.57     30.7%
---------------------------------------------
                                             
---------------------------------------------
Capex                          1.35      7.4%
---------------------------------------------
Corporate & Lima Overhead      0.08      0.4%
---------------------------------------------
                                             
---------------------------------------------
Cash Flow per Tonne            4.14     22.9%
---------------------------------------------



Over the life of the mine expected payable (after processing, treatment, normal
transportation and handling losses and smelter or refinery deductions) metal
production will be approximately 1.285 million ozs of gold and 1.2 billion lbs
of copper from 175 million tonnes of sulphide material and 57 million tonnes of
oxide material.


Payments under the Peruvian tax system are estimated to amount to US$74 million
in royalty payments, US$113 million in worker profit participation and about
US$390 million in income taxes.


Capital Costs

Capital costs for the gold oxide project are based on detailed engineering at
the feasibility study level and definitive vendor and contractor quotes. Capital
costs for the sulphide project are based on pre-feasibility study estimates
prepared by Coffey Mining. Pre-construction activities for the gold oxide
project are underway and to-date US$20 million has been invested. The capital
cost estimates shown in the tables below are inclusive of refundable Peruvian
value added tax of 19% ("IGV") on all expenditures, except Company payroll costs
and the purchase of land. For the oxide project, IGV is estimated to range
between US$6 to US$7 million that will be refunded during the first year of
operation.


The following table sets out the estimated initial capital expenditures for the
gold oxide project.




--------------------------------------------------
Gold Oxide Start up Capital           
--------------------------------------------------
                                                  
--------------------------------------------------
                                       US$ (000's)
--------------------------------------------------
Surface Rights                                 444
--------------------------------------------------
Concession Payments                            284
--------------------------------------------------
Community Relations                            356
--------------------------------------------------
Engineering                                  4,935
--------------------------------------------------
Plant Design                                 1,355
--------------------------------------------------
Mine Engineering                             1,258
--------------------------------------------------
Mine Plan                                      120
--------------------------------------------------
Contract Preparation                           739
--------------------------------------------------
EIA & Permits                                  297
--------------------------------------------------
Power Supply                                   160
--------------------------------------------------
Leach Pad 18ha                               9,077
--------------------------------------------------
Ponds 55000 CuMts                            2,686
--------------------------------------------------
ADR Plant Phase I                            7,941
--------------------------------------------------
Camp Construction                              280
--------------------------------------------------
Effluent Treatment                             120
--------------------------------------------------
Fuel Storage                                    20
--------------------------------------------------
Explosives Storage                              25
--------------------------------------------------
Waste Pad Phase I                            1,841
--------------------------------------------------
Topsoil Storage                                399
--------------------------------------------------
Water Rights/Use                                55
--------------------------------------------------
Water Treatment                                 80
--------------------------------------------------
Civil Work                                  10,229
--------------------------------------------------
Laboratories                                   230
--------------------------------------------------
Owner's Costs                                3,723
--------------------------------------------------
Working Capital & Contingency                4,120
--------------------------------------------------
                                                  
--------------------------------------------------
Total                                       50,774
--------------------------------------------------



Sustaining and expansion capital, inclusive of IGV, over the life of the gold
oxide project is estimated to amount to about US$30 million.


There will be capital expenditure synergies between the gold oxide project and
the sulphide project - for items such as access roads, power supply, water
facilities, maintenance shops and camp facilities - but until a feasibility
study has been completed for the sulphide project such synergies cannot be
quantified. The following table sets out the pre-feasibility estimate of initial
capital costs for the sulphide mine, concentrator and related facilities.




-----------------------------------------------------
Copper / Gold Sulphide            
-----------------------------------------------------
                                              
-----------------------------------------------------
                                  US$ (000's)    
-----------------------------------------------------
                                Yr 3    Yr 4    Total
-----------------------------------------------------
                                              
-----------------------------------------------------
Crushing/Stockpile             9,450   3,150   12,600
-----------------------------------------------------
Grinding                      37,725  12,575   50,300
-----------------------------------------------------
Flotation                     10,725   3,575   14,300
-----------------------------------------------------
Thickening & Tails Storage    10,725   3,575   14,300
-----------------------------------------------------
Water Supply                   8,325   2,775   11,100
-----------------------------------------------------
Reagents                       5,025   1,675    6,700
-----------------------------------------------------
Concentrate Thick & Filter    11,100   3,700   14,800
-----------------------------------------------------
Admin/Workshops                4,275   1,425    5,700
-----------------------------------------------------
First Fill/Capital Spares      5,850   1,950    7,800
-----------------------------------------------------
Power Supply                   5,700   1,900    7,600
-----------------------------------------------------
Infrastructure                 9,900   3,300   13,200
-----------------------------------------------------
Contingency                   25,350   8,450   33,800
-----------------------------------------------------
EPCM                          13,425   4,475   17,900
-----------------------------------------------------
Owner's Costs/Indirects       24,150   8,050   32,200
-----------------------------------------------------
Def Feasibility               10,000       -   10,000
-----------------------------------------------------
Net IGV Payment               34,606  10,934   45,540
-----------------------------------------------------
                                              
-----------------------------------------------------
Total                        226,331  71,509  297,840
-----------------------------------------------------



Metallurgical Test Work

The La Arena Project comprises an oxide portion containing gold mineralisation,
and a sulphide fraction containing both primary and secondary copper
mineralisation. It is proposed that the gold bearing oxide material will be
processed via a dump leach and the copper sulphide ore will be treated via a
conventional grinding and flotation circuit.


Metallurgical Test Work - Oxides

On 8 April, 2010, the Company issued a press release announcing that the series
of metallurgical tests undertaken by Heap Leaching Consulting S.A.C. ("HLC") of
Lima, Peru on a 100 tonne sample of representative material from Rio Alto's La
Arena Gold Oxide Project had been completed several weeks in advance of the
previously anticipated completion timeline.


The metallurgical tests were based on pilot-scale column leach tests analyzing
various mineralized sample sizes from the proposed Calaorco and Ethel oxide pit
areas. Three, six metre high columns containing composited mineralized material
of varying fragment sizes less than 51mm, less than 102mm and greater than 102mm
(less than 2", less than 4" and greater than 4") were leached with sodium
cyanide to determine average recoveries and the average leach cycle in relation
to average cyanide and lime consumption.


The results of this work have been reviewed and verified by Coffey Mining and
the following parameters selected for inclusion in the resource / reserve
estimation process.




Oxide Gold Recovery:          80%                           
Cyanide Consumption:          0.2kg / tonne of ore          
Leach Cycle:                  60 days                       



As a result of this work by HLC and confirmation by Coffey Mining, the La Arena
Gold Oxide Project now has a higher gold recovery rate, a shorter gold leach
cycle and lower processing costs as compared to earlier estimates as set out in
the March 2008 Report.


Metallurgical Test Work - Sulphides

The following results were determined from the work carried out by IAMGOLD and
included in the March 2008 Report.


The copper sulphide mineralisation has been categorized into three types,
Primary High Grade, Primary Average Grade and Secondary ore for the purposes of
metallurgical testing. Extensive metallurgical testwork has been undertaken to
assess the mineralogical, communition and flotation characteristics of the three
sulphide mineralisation types. This testwork focused on copper recovery and
enabled key process design parameters to be established.


Pyrite is the most dominant sulphide mineral present in all cases, while quartz,
phyllosilicates and feldspars account for most of the non-sulphide minerals in
each of the ore types. Copper is present almost entirely as chalcopyrite in the
primary ore types with little to no secondary copper minerals present. The
secondary ore type however includes significant amounts of secondary copper
mineralisation including bornite, covellite and chalcocite, although
chalcopyrite is still the dominant copper-bearing mineral. Trace quantities of
molybdenum as molybdenite were also observed in all three samples. A study of
the grain size distribution indicated the copper bearing and molybdenum minerals
to be relatively fine grained in comparison to the larger pyrite and
non-sulphide gangue materials.


The copper concentrate can be regarded as clean without any major penalty
elements. The results indicate that a concentrate of 28% copper at 88% recovery
is readily achievable from the primary average grade ore.


Gold recovery to concentrate was between 37.6% and 40.9% which is in-line with
mineralogical information that indicated that only approx. 50% of the gold was
associated with the sulphide material. A sulphide gold recovery of 40% was used
in the reserve estimation process.


Preliminary testwork indicates that it is possible to recover approximately 50%
of the gold rejected to the flotation tail with relatively little reagent and
residence time requirements; however, this processing option was not included in
the pre-feasibility study. If demonstrated that flotation tail cyanidation is
suitable this could result in an overall gold recovery of approximately 60% and
could increase gold production by 15,000 ozs per year.


Further investigation into the potential molybdenum recovery and extraction will
be performed to assess its economic viability. Molybdenum recovery to the final
concentrate ranged between 35% and 65% even though the final flowsheet
development did not focus on molybdenum recovery. The reserve estimate assumes
that there is no economic value attributed to the molybdenum.


Environmental and Social Responsibility

La Arena S.A. received approval of the Environmental Impact Study (EIA) for the
development of the La Arena Gold Oxide Project on July 20, 2010. Since that
date, the permitting process has been initiated and pre-construction work has
commenced on site.


The gold oxide project at La Arena will be developed first, which will minimize
the mining footprint in the area. The processing facility and leach pad have
been designed to conform to existing global best practices and are compliant
with the International Cyanide Management Code.


In order to encourage sustainable development, Rio Alto and its civil
construction contractors have hired and trained as many local residents as
possible, with a complement of experienced personnel, to build and operate the
La Arena Gold Oxide Project. Rio Alto is also encouraging and supporting the
development of local businesses at La Arena and surrounding communities.
Education is important to sustainable development and in association with the
local communities, the Company is coordinating the construction of a new school
at La Arena that will serve the educational needs of the youth of the area and
also serve as an after school training centre for workers of the project.


Mineral Resources

The following table outlines the revised resource estimate for the La Arena Project.



--------------------------------------------------------------------------
La Arena Project
Mineral Resource
--------------------------------------------------------------------------
                                                   Au         Cu        Ag
             Cut                      Tonnes    Grade      Grade     Grade
Material     off           Category      (Mt)    (g/t)        (%)     (g/t)
--------------------------------------------------------------------------
Oxide        0.11g/t Au    Indicated    79.6     0.41       0.01      0.08
                           Inferred      9.2     0.19       0.01      0.29
--------------------------------------------------------------------------
Secondary    0.1% Cu       Indicated     225     0.27       0.35
& Primary                  Inferred      178     0.21       0.30
--------------------------------------------------------------------------

--------------------------------------------------------------------------
             Cut                                   Au         Cu        Ag
Material     off           Category          ('000 oz)  ('000 lb) ('000 oz)
--------------------------------------------------------------------------
Oxide        0.11g/t Au    Indicated            1,050      26.46       172
                           Inferred                57        4.4        66
--------------------------------------------------------------------------
Secondary    0.1% Cu       Indicated            1,932  1,721,808
& Primary                  Inferred             1,216  1,170,653
--------------------------------------------------------------------------



The La Arena resource estimate is based on the results of 340 diamond core holes
(58,805m), 11 reverse circulation holes (1,186m), and 60 surface trenches
(4,120m). The deposit has been drilled at a nominal spacing of 50m in the
brecciated sandstone and 65m in the porphyry.


Resources are confined within an optimum undiscounted cash flow pit shell based
on US$1,050/oz Au and US$12/oz Ag for copper-poor mineralisation largely in
oxide sandstone (Cu less than 300ppm) and a shell based on US$3.00/lb Cu and
US$1,050/oz Au for copper-rich mineralisation largely in primary and secondary
porphyry. These metal prices, although current, are higher than the more
conservative prices used for Mineral Reserves estimation and put a suitable
economic constraint to the Resource.


The average molybdenum grade is of the order of 40ppm. Although not included in
the resources, recovery of molybdenum presents an economic opportunity of
interest.


The estimation and classification of the resources by Coffey Mining are in
accordance with the guidelines set out in the Australasian Code for Reporting of
Exploration Results, Mineral Resources and Ore Reserves of December 2004 as
prepared by the Joint Ore Reserves Committee of the Australasian Institute of
Mining and Metallurgy, Australian Institute of Geoscientists and Minerals
Council of Australia (JORC).


The resource classification is also consistent with criteria laid out in the
Canadian National Instrument 43- 101, Standards of Disclosure for Mineral
Projects of December 2005 (the Instrument) and the classifications adopted by
CIM Council in November 2004.


Mineral Reserve

All important physical and financial inputs to the mineral reserve estimation
process have been reviewed by Coffey Mining, which prepared a pit optimisation
using these inputs and Whittle software. The key input parameters used are
outlined in the table below.




-----------------------------------------------------------------------
La Arena Project                             
Coffey Mining Pit Optimisation Economic Parameters            
-----------------------------------------------------------------------
                                                                       
-----------------------------------------------------------------------
Parameter                                Dump Leach                Mill
-----------------------------------------------------------------------
Market Price                    US$950 per ounce Au / US$2.30 per lb Cu
-----------------------------------------------------------------------
Mining cost      Oxides                       $1.74               $1.74
(US$/t mined)    Sulphides                    $1.82               $1.82(i)
-----------------------------------------------------------------------
Processing Cost (US$/t Ore)                   $1.55               $4.77
G & A Cost (US$/t Ore)                        $0.72(ii)           $0.95
-----------------------------------------------------------------------
                 Au                             80%                 40%
Mill Recovery    Cu                              0%                 88%
-----------------------------------------------------------------------
Slope Angles                           38 degrees and 45 degrees       
Royalty                                          1.70%                 
-----------------------------------------------------------------------

(i)  Note that the mining cost was increased by US$0.03/t for every 12m 
     bench mined below elevation 3328mRL. 
(ii) Note the G&A cost assumed an ore processing rate of 8.6Mtpa when 
     Whittle work was done. 



The Mineral Reserve has been estimated including a 2% allowance for ore loss
during mining and the following cut-off grades:




--  For oxide ore with Culess than 300ppm (dump leach feed) 0.11Au g/t 
--  For oxides with Cugreater than 300ppm, secondary and primary sediments
    and porphyry (mill feed) 0.13%Cu. 



The Probable Mineral Reserve, based on the Indicated Resource only, is outlined
below.




---------------------------------------------------------------------------
La Arena Project
La Arena Project Probable Mineral Reserve
---------------------------------------------------------------------------
                        Oxide Ore          Secondary Ore
                    -----------------  ---------------------
Descr-    Ore                g      %            g         %
iption    Type        Mt  Au/t     Cu     Mt  Au/t        Cu
------------------------------------------------------------
Gold      Sediments 57.4  0.44
Oxide     --------------------------------------------------
Pit                 57.4  0.44      0      0     0         0
------------------------------------------------------------

------------------------------------------------------------
Sulphide  Sediments  2.0  0.57   0.11    0.1  0.34      0.32
Pit       --------------------------------------------------
Shell     Porphyry  13.1  0.30   0.20   13.2  0.36      0.52
------------------------------------------------------------
                    15.1  0.34   0.19   13.3  0.36      0.52
------------------------------------------------------------

                        Primary Ore           All Ore
                    -----------------  ---------------------         000's
                                                                  ---------
Descr-    Ore                g      %            g        Oz    %       lbs
iption    Type        Mt  Au/t     Cu     Mt  Au/t        Au   Cu        Cu
---------------------------------------------------------------------------
Gold      Sediments                     57.4  0.44   821,000
Oxide Pit           
---------------------------------------------------------------------------
                       0     0      0   57.4  0.44   821,000    0         0
---------------------------------------------------------------------------

---------------------------------------------------------------------------
Sulphide  Sediments  0.1  0.81   0.60    2.1  0.58    39,000 0.14     7,000
Pit       -----------------------------------------------------------------
Shell     Porphyry 160.1  0.28   0.38  185.2  0.29 1,709,000 0.38 1,567,000
---------------------------------------------------------------------------
                   160.2  0.28   0.38  187.3  0.29 1,748,000 0.38 1,574,000
---------------------------------------------------------------------------



The estimation and classification of the mineral reserves by Coffey Mining are
in accordance with the guidelines set out in the Australasian Code for Reporting
of Exploration Results, Mineral Resources and Ore Reserves of December 2004 as
prepared by the Joint Ore Reserves Committee of the Australasian Institute of
Mining and Metallurgy, Australian Institute of Geoscientists and Minerals
Council of Australia (JORC).


The reserve classification is also consistent with criteria laid out in the
Canadian National Instrument 43-101, Standards of Disclosure for Mineral
Projects of December 2005 (the Instrument) and the classifications adopted by
CIM Council in November 2004. The reporting of reserve classification under the
JORC Code and the Canadian NI 43-101 systems are essentially identical.


Risks and Opportunities

Opportunities to improve the project economics include the following:



--  Continual improvement and optimization of mining activities to minimize
    operating costs 
--  The completion of a Feasibility Study (FS) on the La Arena sulphide
    project 
--  Determine the viability of recovering molybdenum as part of the FS 
--  Determine means to improve the recovery of gold from sulphides as part
    of the FS 
--  Conversion of significant inferred resources into indicated or measured
    resources and hence mineral reserves through definition drilling and
    value engineering 
--  Further exploration and definition drilling around the current limits of
    the La Arena mineral resource for potential inclusion in the future mine
    plan for the project 
--  Exploration for additional gold oxide resources at the nearby Agua
    Blanca, La Florida, Maria Angola and El Alizar prospects which are all
    located within a 10 kilometer radius of the La Arena Project 
--  Exploration for additional copper and molybdenum resources at the
    adjacent Agua Blanca prospect which hosts a large and highly anomalous
    soil geochemistry anomaly for both copper and molybdenum 
--  Additional exploration on the Company's approx 21,000 hectare portfolio
    of mineral concessions 



Risks that may require mitigation include the following:



--  Exchange rate 
--  Weather related risks associated with the onset of the rainy season in
    the Peruvian Andes from October through March. 



Additional risks that may affect the development and operation of the La Arena
Project are set out in Rio Alto's Annual Information Form for the financial year
ended May 31, 2010 that may be accessed within the Company's SEDAR profile at
www.sedar.com.


The qualified person for the La Arena Project, Linton Kirk, Chief Mining
Engineer, Coffey Mining Pty Ltd and a fellow of the Australasian Institute of
Mining and Metallurgy ("AusIMM"), has reviewed and verified the contents of this
release.


Alex Black, President, stated that "La Arena is a project that benefits all
stakeholders: shareholders with an excellent rate of return, government and
local communities with significant tax receipts, meaningful employment in the
local area, sustainable development in the local communities, and an
environmentally responsible project that conforms to global best practices.


The gold oxide development represents a solid foundation upon which we will
build and expand Rio Alto. Potential exists for exploration success at La Arena,
Agua Blanca, La Florida, El Alizar and Maria Angola that will very likely
enhance and expand the production and reserves of the La Arena Project. I want
to thank our Rio Alto team and all the consultants and contractors who have
worked extremely hard to keep the Company on track to achieve its goal of
placing first ore on the leach pad in December 2010."


Rio Alto plans to bring La Arena Gold Oxide Project into production during 2010
and to use cash flow from production to further develop its assets in Peru. To
learn more about Rio Alto, please visit Rio Alto's website or Rio Alto's profile
on SEDAR at www.sedar.com.


Reader Advisory

Certain statements contained herein constitute forward-looking statements, most
particularly the estimated mineral resources and reserves, estimated costs,
metal prices, mining and processing rates, metal production and resulting
financial results for the La Arena Project and the timing for the development of
and production from the La Arena Gold Oxide Project and completion of a
feasibility study for the La Arena Sulphide Project. All statements included
herein, other than statements of historical fact, are forward-looking
information and such information involves various risks and uncertainties. Rio
Alto believes the expectations reflected in these forward looking statements are
reasonable but no assurance can be given that these expectations will prove to
be correct and such forward-looking statements in this press release should not
be unduly relied upon. A description of assumptions used to develop such
forward-looking information and a description of risk factors that may cause
actual results to differ materially from forward-looking information can be
found in Rio Alto's disclosure documents on the SEDAR website at www.sedar.com.
Forward-looking statements included in this press release are made as of the
date of this press release and Rio Alto disclaims any intention or obligation to
update or revise any forward-looking statements, whether as a result of new
information, future events or otherwise, except as expressly required by
applicable securities legislation.


To learn more about Rio Alto Mining Limited, please visit: www.rioaltomining.com.

ON BEHALF OF THE BOARD OF RIO ALTO MINING LIMITED

Alex Black, President & COO

Heartlink Canada (1999) (TSXV:HLC)
Historical Stock Chart
Von Apr 2024 bis Mai 2024 Click Here for more Heartlink Canada (1999) Charts.
Heartlink Canada (1999) (TSXV:HLC)
Historical Stock Chart
Von Mai 2023 bis Mai 2024 Click Here for more Heartlink Canada (1999) Charts.