Commerce Resources Corp. Provides Update on 2012 Programs for the
Blue River Tantalum-Niobium Project, Blue River, British Columbia
Highlights
- Completion of Phase 2 metallurgical test work to optimize the
use of desliming and carbonate rejection flotation, as well as
chemical reagent dosages to increase the efficiency of
rougher/cleaner Ta/Nb flotation and to finalize the preliminary
process flow sheet developed in Phase 1 which formed the basis of
the PEA.
- Mineral Resource update underway at AMEC to include results of
exploration in 2012, as well as 34 additional drill holes
(totalling 8,715 m) of infill drilling completed in 2011.
VANCOUVER, Dec. 3, 2012 /PRNewswire/ - Commerce Resources
Corp. (TSXv: CCE, FSE: D7H, OTCQX: CMRZF) (the "Company" or
"Commerce") is pleased to provide an update on recent work
completed at its Blue River
Project since release of the National Instrument (NI) 43-101
compliant Mineral Resource update (effective date June 22, 2012 - see Commerce news release dated
July 6, 2012) for the Upper Fir
Deposit.
The geological, engineering, metallurgical and
environmental programs carried out to date in 2012 broadly support
the advancement of exploration and development at the Company's
wholly owned Blue River Project,
east-central British Columbia.
These results continue to strengthen the foundation of broadly
based technical knowledge developed in 2011, and following
completion of the mineral resource update currently in progress by
independent consultants AMEC Americas Ltd. ("AMEC"), will be
sufficient to support the initiation of a pre-feasibility study
(PFS).
The Blue River Property is host to the Upper Fir
Tantalum and Niobium Deposit, which was discovered in 2002 and
which has been the focus of the Company's activities since 2005. In
fiscal 2012 year to date Commerce has spent approximately
$3.7M (to October 31, 2012).
Metallurgical Test Work in 2012
Metallurgical work in 2012 has continued to update and optimize the
process flow sheet described in the NI 43-101 compliant Preliminary
Economic Assessment ("PEA") study completed by AMEC on the Blue
River Project (effective date of September
29, 2011; see Commerce news release dated November 3, 2011). The process flow sheet
for the recovery of the tantalum and niobium described in the PEA
was developed in 2011 based on Phase 1 studies and is available on
the corporate website at http://www.commerceresources.com.
In April 2012,
Commerce commissioned Acme Metallurgical Ltd ("Acme Met") of
Vancouver, BC to initiate a Phase
2 investigation. This was designed to follow-up the successful
results of the earlier program which had tested flotation as the
preferred method to remove the larger portion of fine slimes and
carbonatite minerals early in the process. Subsequent process steps
could then focus on material containing Ta and Nb.
The objectives of the Phase 2 testing were three
fold: 1). to optimize the use of desliming and carbonate rejection
flotation; 2). to optimize chemical reagent dosages to increase the
efficiency of rougher/cleaner Ta/Nb flotation; and 3). to finalize
the process flow sheet developed in Phase 1 which was based on
composite samples BS-2F and BS 2G. All Phase 2 work was conducted
on these same composites and all tests were conducted at a grind
size of 80% passing 130 microns.
Key Areas of Investigation and
Results:
Desliming and Mass Removal
Approximately 50 to 55% of the mass containing only 10-15% of the
Ta and Nb can be rejected prior to Ta/Nb flotation using desliming
and carbonate flotation. Reagent Na2SiO3 has been eliminated from
the desliming process while the flotation conditions in the
carbonate flotation process have been optimized to provide
sufficient carbonate mineral removal.
Rougher Flotation
Rougher flotation of Ta/Nb has also been optimized to yield total
rougher Ta/Nb recoveries of 85% and 90% on composites BS-2G and
BS-2F, respectively with a mass pull of 20-25% from the original
mass being recovered into the Ta-Nb minerals rougher
concentrate.
In addition, effective flotation of carbonate
from the BS-2F and BS-2G samples was accomplished using 400 and 500
g/t of Oleic Acid respectively. Na2SiO3 is added during
conditioning to target a pH of 10.5.
Lastly, H2SiF6 acid is used to condition the
pulp to the pH 7 while 400 g/t and 500 g/t of Duomac T collector
were used for composites BS- 2F and BS-2G respectively.
Cleaner Flotation
Initial cleaner flotation testing on the Ta/Nb rougher concentrate
has generated promising results, showing a strong correlation
between the dosage of reagent, H2SiF6, as a silicate minerals
depressant/pH regulator, and the final Ta-Nb grade and recovery has
been determined.
For example, if insufficient H2SiF6 is added to
the cleaning process, the Ta/Nb minerals will not selectively
separate from the gangue minerals, while an excessive amount of
H2SiF6 can lead to a decrease in the Ta/Nb recovery.
Magnetic Separation
Though additional study is required, magnetic separation of the
final Ta/Nb flotation concentrate appears to show potential to
further enhance the Ta/Nb grades, with approximately 50% of the
final concentrate mass being removed with minimal Ta/Nb loss.
Acme Metallurgical recommends future investigation as
follows:
- focused testwork on the optimization of the cleaner flotation
circuit, in particular the addition of H2SiF6 addition in each of
the cleaning stages;
- following optimization of the cleaner circuit, locked-cycle
testing to determine the impact of recycling various process
streams where improved recoveries are expected; and
- additional studies to verify the potential success achieved
with magnetic separation including work on recoveries from magnetic
tails.
Results are nearing completion for Phase 3 of
metallurgical investigations which considered the effects of
variable tantalum and niobium grades, mineralogy and lithological
textures. This work will be reported once results are
received and reviewed.
2012 Field Exploration and Results
The 2012 field exploration program commenced in May and was
completed in late August.
A structural geology review of outcrop, core and
previous data refined concepts of "faults" versus "fractures" and
confirmed the previously held view that most faults have low
displacement, likely resulting from tectonic uplift and expansions.
Successful completion of an updated structural map supports the
overall development of the three dimensional structural model of
the Upper Fir deposit.
The Company also re-logged selected diamond
drill core from 2005-2009 with a particular focus on rock types,
structures and carbonatite textures to ensure conformity of these
aspects over time. The work provided only minor changes, but added
considerable structural detail. This will increase the level of
confidence in structural model interpretation and therefore better
support for the resource block model.
An independent structural geology review of
2005-2010 data was conducted to support use of the carbonatite
model in resource definition. The review verified the structural
data previously collected and broadly supported the structural
constraints in the 2011 block model, as well as the new model which
will be used in the Mineral Resource Update.
Key results are as follows:
- isosurfaces show a south-east trend in grade continuity similar
to the preferred orientation of fold hinges in the Upper Fir
Deposit. These patterns were defined using the software
program, Leapfrog, which analyzes grade continuity in three
dimensions;
- all data collected have been subject to a successful review
under AMEC-defined QA/QC (quality analysis/quality control)
protocols;
- an updated solids model in Gemcom has been provided to AMEC to
initiate the upcoming Mineral Resource Update.
Upcoming Mineral Resource Update
A Mineral Resource Update and subsequent technical report which
will incorporate all data from 2005 through 2012 is currently
underway by AMEC with completion targeted for the first quarter of
2013. This work will build from the previous Mineral Resource
Update technical report (effective date June
22, 2012) in which AMEC compared results from the 34 holes
totalling 8,715m drilled in 2011, after the closure of the resource
database to the updated resource model and found them to be
reasonably consistent with the geology predicted by the model.
2011 PEA Outcomes and Subsequent Resource Update
(July 6. 2012)
The Preliminary Economic Assessment ("PEA) was prepared to define
an overall proof of concept for further development of the Blue
River Project. The PEA (effective date September 29, 2011) indicated that the deposit
can be developed economically as an underground mine and
recommended future studies to support a pre-feasibility level
assessment of the project. The assessment included geological
and mineral resource modeling, preliminary mine planning, a
description of metallurgical test work and process design, a
summary of environmental baseline work to date, and estimates for
capital and operating costs. As well, it determined the
economics to develop the project as an underground mine with
process facility, and included an estimate of the direct cash costs
to produce tantalum contained in a technical grade oxide
product.
The resource on which the PEA was based
considered only assay results and drilling to the end of 2009.
Commerce completed additional drilling in 2010 and 2011. AMEC
updated the original resource model on which the PEA had been based
with the data to the end of 2010 drilling using a total of 237
holes comprising 50,395m of HQ diameter core and 12,736
samples. Most holes were at a nominal spacing of 50m with
dips typically between -60 degrees to sub-vertical.
The composite body extends more than 1,450m in a
north-south direction and as much as 800m in an east-west
direction. Tantalum and niobium are contained in the minerals
ferrocolumbite and pyrochlore. The first of what will eventually be
two subsequent Mineral Resource Update technical reports (effective
date June 22, 2012) was released on
July 6, 2012. Readers are encouraged
to review both the entire PEA Technical Report and the Mineral
Resource Update Report which are available for viewing at
http://www.sedar.com. A link is also available on the
corporate website at http://www.commerceresources.com.
"We are proud to have accomplished a significant
amount of work in 2012 despite a very tough financing climate. We
are again extremely pleased with the results of the metallurgical
study which provides an update to testwork previously reported in
the PEA, a major milestone in our progress to develop the Upper
Fir. The improved results and 2012 exploration reported today
reinforce Commerce's belief that we are in the process of building
a very important long-term source of conflict free and ethical
tantalum which could potentially supply 10% of the current world's
market for the long term." said Dave
Hodge, Commerce's President. "Results of the additional
drilling completed in 2011 and our ongoing field work in 2012 have
been compiled by our geologists and supplied to AMEC to support the
next resource update which will be based on all work to the end of
the 2012 field season. All indications are that we will be
able to enhance even further the quality of the resource."
"Of necessity, our previous resource update was
completed based on an assumed long term pricing which may prove to
be conservative. Recent developments in global tantalum and niobium
markets provide indication of substantially higher prices than
those used to define the resource. For example, information
available through Asian Metals provides early June 2012 pricing (CAD=0.9825 US) for average
grade Nb205 (99.5%) of $US59-61/kg, and for average grade
Ta205 (99.95% min) of $US483/kg. Such prices may provide an opportunity
for the ongoing resource update to the end of 2011 to be based on
higher, though still conservative, pricing."
Property
The Blue River Project is located near the village of Blue River, which is approximately 250 km
north of the city of Kamloops and
approximately 90 km south of the town of Valemount. The Project comprises 105,373
hectares (1,000 km2) of mineral claims. Power
transmission lines, rail, and paved and gravel roads are all
adjacent to, or within the property boundaries. Transalta Corp.'s
18 MW Bone Creek run-of-river hydroelectricity project near the
project was commissioned in June
2011.
NI 43-101 Disclosure
Ms. Jenna Hardy, M.Sc., P.Geo.,
Commerce Resources Corp., is a Qualified Person as defined by
National Instrument 43-101, read and approved the disclosure of the
technical information in this news release.
About Commerce Resources Corp.
Commerce Resources Corp. is an exploration and development company
with a particular focus on tantalum, niobium and rare metal
deposits with potential for economic grades and large tonnages. The
Company is specifically focused on the development of its Upper Fir
Tantalum and Niobium Deposit in British
Columbia and its Ashram Rare Earth Element Project in
northern Quebec.
On Behalf of the Board of Directors
COMMERCE RESOURCES CORP.
"David Hodge"
David Hodge
President and Director
Tel: 604.484.2700
Email: dhodge@commerceresources.com
Neither TSX Venture Exchange nor its
Regulation Services Provider (as that term is defined in the
policies of the TSX Venture Exchange) accepts responsibility for
the adequacy or accuracy of this release.
Forward-Looking Statements
This news release contains forward-looking
information which is subject to a variety of risks and
uncertainties and other factors that could cause actual events or
results to differ from those projected in the forward-looking
statements. Forward looking statements in this press release
include that our results will be sufficient to support the
initiation of a pre-feasibility study; that we are in the process
of building a very important long-term source of tantalum which
could potentially supply 10% of the current world's market for the
long term; that we will be able to enhance even further the quality
of the resource; and that prices for our potential products are
conservatively estimated and may trend upwards. These
forward-looking statements are based on the opinions and estimates
of management and its consultants at the date the information is
disseminated. They are subject to a variety of risks and
uncertainties and other factors that could cause actual events or
results to differ materially from those projected in the
forward-looking information. Risks that could change
or prevent these statements from coming to fruition include
changing costs for mining and processing and their impact on the
cut off value established; increased capital costs; changing
forecasts of mine production rates; the timing and content of
upcoming work programs; geological interpretations based on
drilling that may change with more detailed information; potential
process methods and mineral recoveries assumption based on limited
test work and by comparison to what are considered analogous
deposits that with further test work may not be comparable; the
availability of labour, equipment and markets for the products
produced; market pricing for the products produced; and despite the
current expected viability of the project, conditions changing such
that the minerals on our property cannot be economically mined, or
that the required permits to build and operate the envisaged mine
can be obtained. The forward-looking information contained herein
is given as of the date hereof and the Company assumes no
responsibility to update or revise such information to reflect new
events or circumstances, except as required by law.
SOURCE Commerce Resources Corp.