Lithium Americas Corp. (TSX: LAC) (NYSE: LAC) (“Lithium
Americas” or the “Company”) has reported unaudited
financial and operating results for the third quarter ended
September 30, 2021.
HIGHLIGHTS
Caucharí-Olaroz
- Construction activities at
Caucharí-Olaroz continue to advance, targeting first production by
mid-2022 on the initial 40,000 tonnes per annum (“tpa”) lithium
carbonate equivalent (“LCE”) operation.
- As of September 30, 2021, $519
million has been spent or 81% of the $641 million budget, with the
majority of remaining budget committed.
- Over 1,200 workers
are on site, with over 97% of the total workforce having received
at least their first COVID-19 vaccine dose and over 60% have
received two doses.
- With all major
equipment on site, focus is on construction of the chemical and
processing plants.
- In early October,
commissioning of the lime plant started to lime concentrated brine
to support production ramp up. The project has sufficient brine
inventory to support production ramp up.
- Development planning for a second
stage expansion of at least 20,000 tpa LCE continues to
advance.
Thacker Pass
- In October 2021, Nevada Department
of Environmental Protection made a preliminary determination to
issue three remaining key state-level permits: Water Pollution
Control Permit, Mine Reclamation Permit and Class II Air Permit.
The Record of Decision appeal process remains on track with the
hearing date set for Q1 2022.
- Phase 1 of the Feasibility Study
was increased to target 40,000 tpa lithium carbonate (from
30,000-35,000 tpa). A potential Phase 2 expansion scenario to
target total capacity of 80,000 tpa is being incorporated.
- Updated the Measured and Indicated
(“M&I”) Resource estimate to 13.7 million tonnes (“Mt”) LCE at
2,231 parts per million lithium (“ppm Li”).
- Early-works construction expected
to commence in H1 2022, includes site access, site preparation,
water line and additional infrastructure to condense and de-risk
the overall construction schedule.
- Discussions continue with potential
strategic partners and customers.
- An integrated pilot plant to
support increased scale and ongoing optimization work and to
provide product samples for potential customers is expected to be
operational in the first half of 2022.
Corporate:
- As at September 30, 2021, the
Company had $482 million in cash and cash equivalents.
- As at September 30, 2021, the
Company had $134 million in available credit, with $146 million
drawn from the $205 million senior credit facility and $25 million
drawn from its $100 million unsecured, limited recourse,
subordinated loan facility. This available credit is expected to
fully fund the Company’s share of the remaining capital expenditure
at Caucharí-Olaroz.
- In July, the Company completed a
strategic investment in Arena Minerals Inc. (TSX-V: AN) of $5
million for an approximate 12.9% equity interest (14.6% on a fully
diluted basis).
- In early September, the Company was
approved as an IRMA (Initiative for Responsible Mining Assurance)
Pending Member which means that the Company commits to have the
proposed project audited against the new draft IRMA Ready Standard
for exploration and development within 12 months of its
availability for application.
- In September, the Company was
recognized on the TSX30 2021 as one of the top 30 performers on the
TSX.
- On October 1, 2021 Jose Francesconi
joined the team and is responsible for overseeing projects and
technical services in Argentina. Mr. Francesconi brings over thirty
years of execution experience for large capital projects and was
previously the Operations Director, Argentina for Worley, and the
Associate Engineering Director of Dow Engineering.
- On November 1,
the Company submitted an unconditional offer to acquire all
outstanding shares of Millennial Lithium Corp. (“Millennial”) at a
price of C$4.70 per share, payable in Lithium Americas common
shares and cash of C$0.001 per Millennial share for total
consideration of approximately US$400 million.
TECHNICAL INFORMATION
The Technical Information in this news release
has been reviewed and approved by Rene LeBlanc, PhD, SME, Chief
Technical Officer of Lithium Americas, and a Qualified Person as
defined by National Instrument 43-101.
FINANCIAL RESULTS
Selected consolidated
financial information is presented as follows:
(in US$ million except per share information) |
Quarter ended September 30, |
|
2021 |
|
|
2020 |
|
|
$ |
|
|
$ |
|
Expenses |
(16.6 |
) |
|
(5.7 |
) |
Net loss |
(17.2 |
) |
|
(6.5 |
) |
(Loss)/income per share – basic |
(0.14 |
) |
|
0.07 |
|
(in US$ million) |
As at September 30, 2021 |
|
|
As at December 31, 2020 |
|
|
$ |
|
|
$ |
|
Cash and cash equivalents |
482.1 |
|
|
148.1 |
|
Total assets |
716.2 |
|
|
326.7 |
|
Total long-term liabilities |
(180.3 |
) |
|
(127.3 |
) |
During the nine months
ended September 30, 2021, total assets and cash increased primarily
due to the $377.4 million net proceeds raised from the underwritten
public offering of common stock, partially offset by expenditures
in the period. Total long-term liabilities increased primarily as a
result of drawdowns on the Company’s senior credit facility of
$50.1 million.
The higher net loss in
Q3 2021 compared to Q3 2020 is primarily attributable to higher
Thacker Pass expenditures.
Click here to view the
Company’s third quarter results for 2021.
About Lithium Americas:
Lithium Americas is a development-stage company
focused on advancing to production a lithium brine operation in
Jujuy, Argentina and a sedimentary lithium clay project in Nevada,
United States. The Company trades on both the Toronto Stock
Exchange and on the New York Stock Exchange, under the ticker
symbol “LAC”.
For further information contact:
Investor RelationsTelephone: 778-656-5820Email:
ir@lithiumamericas.comWebsite: www.lithiumamericas.com
FORWARD-LOOKING
STATEMENTS
This news release contains “forward-looking
information” and “forward-looking statements” (which we refer to
collectively as forward-looking information) under the provisions
of applicable securities legislation. All statements, other than
statements of historical fact, are forward-looking information.
Examples of forward-looking information in this news release
include, among other things, statements related to: successful
development of the Caucharí-Olaroz project and the Thacker Pass
project, including timing, progress, construction, milestones,
anticipated production and results thereof; expectations and
anticipated impact of COVID-19 on the Company and its mineral
properties; capital expenditures and programs, and the Company’s
ability to fund such programs; government regulation of mining
operations and treatment under governmental and taxation regimes;
the timing, amount and type of future production; the estimated
amount and grade of mineral resources for the Thacker Pass project;
expected outcome and timing of environmental surveys and analysis,
permit applications and other environmental matters; expected
environmental impact of the project, and quality of the technology
utilized to minimize such impact; expected timing and outcome of
litigation concerning the Thacker Pass project; expected
expenditures to be made by the Company on its properties; the
timing, cost, quantity, capacity, product quality of production and
sufficiency of brine inventory of the Caucharí-Olaroz project,
which is held and operated through an entity in Argentina co-owned
by the Company, Ganfeng Lithium Co. Ltd. (“Ganfeng”) and Jujuy
Energia y Mineria Sociedad del Estado (JEMSE); successful operation
of the Caucharí-Olaroz project under the co-ownership structure,
and expectations concerning proposed expansion plans for the
project; results of the Company’s engineering, design and
permitting program at the Thacker Pass project, including the
Company meeting deadlines and receiving and maintaining permits as
anticipated; timing, results and completion of a feasibility study
and to make a construction decision for the Thacker Pass project;
the Company’s share of the expected capital expenditures for the
construction of the Caucharí-Olaroz project; Company expectations
as to feasibility study activities at the Thacker Pass project,
including timing for pilot plant operations and expectations
concerning the outcome of such operations; the timing and extent of
early works construction for the Thacker Pass project; the
potential for partnership and financing scenarios for the Thacker
Pass project; expected benefits of the Arena Minerals investment;
and expectations concerning the offer to Millennial.
Forward-looking information is based upon a
number of factors and assumptions that, if untrue, could cause the
actual results, performances or achievements of the Company to be
materially different from future results, performances or
achievements expressed or implied by such information. Such
information reflects the Company’s current views with respect to
future events and is necessarily based upon a number of assumptions
that, while considered reasonable by the Company today, are
inherently subject to significant uncertainties and contingencies.
These assumptions include, among others, the following: current
technological trends; a cordial business relationship between the
Company and Ganfeng for the Caucharí-Olaroz project; ability of the
Company to fund, advance and develop the Caucharí-Olaroz project
and the Thacker Pass project, and raise additional capital as
needed, and the respective impacts of the projects when production
commences; the Company’s ability to operate in a safe and effective
manner; uncertainties relating to receiving and maintaining mining,
exploration, environmental and other permits or approvals in Nevada
and Argentina, and resolving any complaints or litigation
concerning such environmental permitting processes; realizing on
the expected benefits from previous transactions with existing or
new partners, or for debt financing; demand for lithium, including
that such demand is supported by growth in the electric vehicle
market; the Company’s ability to produce high purity battery grade
lithium products; the impact of increasing competition in the
lithium business, and LAC’s competitive position in the industry;
currency exchange and interest rates; general economic conditions;
a stable and supportive legislative, regulatory and community
environment in the jurisdictions where the Company operates;
stability and inflation of the Argentinian peso, including any
foreign exchange or capital controls which may be enacted in
respect thereof, and the effect of current or any additional
regulations on the Company’s operations; the impact of unknown
financial contingencies, including litigation costs, on the
Company’s operations; gains or losses, in each case, if any, from
short-term investments in Argentine bonds and equities; estimates
of and unpredictable changes to the market prices for lithium
products; exploration, development and construction costs for the
Caucharí-Olaroz project and the Thacker Pass project; the timing,
cost, quantity, capacity and product quality of production at the
Thacker Pass project; successful results from the Company’s testing
facility and third-party tests related thereto for the Thacker Pass
project; capital costs, operating costs, and sustaining capital
requirements of the Caucharí-Olaroz project and the Thacker Pass
project; technological advancements and changes; estimates of
mineral resources and mineral reserves, including whether mineral
resources will ever be developed into mineral reserves; reliability
of technical data; anticipated timing and results of exploration,
development and construction activities, including the impact of
COVID-19 on such timing; timely responses from governmental
agencies responsible for reviewing and considering the Company’s
permitting activities at the Thacker Pass project; the Company’s
ability to obtain additional financing, including pursuant to an
additional debt funding commitment, on satisfactory terms or at
all; the ability to develop and achieve production at any of the
Company’s mineral exploration and development properties; the
impact of COVID-19 on the Company’s business; that pending patent
applications are approved; the Company’s anticipated ownership
interest in holdings of shares, warrants and other securities
issued by third parties; accuracy of development budget and
construction estimates; preparation of a development plan and
feasibility study for lithium production at the Thacker Pass
project; CATL not exercising the Match Right under the CATL
Agreement; the performance of the Company’s shares through to
completion of the transactions contemplated by the Offer being
stable; the approval of Millennial shareholders of the transaction;
changes to the Company’s current and future business plans and the
strategic alternatives available to the Company; favourable
treatment of the transaction under applicable anti-competition
laws; and stock market conditions generally.
Forward-looking information also involves known
and unknown risks that may cause actual results to differ
materially. These risks include, among others, inherent risks in
the development of capital intensive mineral projects (including as
co-owners), variations in mineral resources and mineral reserves,
global demand for lithium, recovery rates and lithium pricing,
risks associated with successfully securing adequate financing,
changes in project parameters and funding thereof, risks related to
growth of lithium markets and pricing for products thereof, changes
in legislation, governmental or community policy, changes in public
perception concerning mining projects generally, political risk
associated with foreign operations, permitting risk, including
receipt of new permits and maintenance of existing permits,
outcomes of litigation concerning the Company’s mineral properties,
title and access risk, cost overruns, unpredictable weather and
maintenance of natural resources, unanticipated delays,
intellectual property risks, currency and interest rate
fluctuations, operational risks, health and safety risks, and
general market and industry conditions. Additional risks,
assumptions and other factors are set out in the Company’s most
recent annual management discussion analysis and annual information
form, copies of which are available under the Company’s profile on
SEDAR at www.sedar.com and on the SEC website at www.sec.gov.
Although the Company has attempted to identify
important risks and assumptions, given the inherent uncertainties
in such forward-looking information, there may be other factors
that cause results to differ materially. Forward-looking
information is made as of the date hereof and the Company does not
intend, and expressly disclaims any obligation to, update or revise
the forward-looking information contained in this news release,
except as required by law. Accordingly, readers are cautioned not
to place undue reliance on such forward-looking information.
Arena Minerals (TSXV:AN)
Historical Stock Chart
Von Dez 2024 bis Jan 2025
Arena Minerals (TSXV:AN)
Historical Stock Chart
Von Jan 2024 bis Jan 2025