Sabina Gold & Silver Corp. (“Sabina”) or (the “Company”) (SBB –
TSX/ SGSVF - OTCQX) provides an update on advancements of the Goose
Mine development at the Company’s 100% owned Back River Gold
District in Nunavut, Canada. The Goose Mine is the Company’s first
mine on the 80 km long Back River Gold District, a
multi-generational mining district already with a high-grade world
class gold endowment.
Over the past few years, Sabina has been
steadily advancing logistics, civil works, engineering and
procurement. All pre-development activities are now completed and
we are ready for full construction to commence in 2023. All major
equipment and materials required for construction have been either
procured, marshalled at our east and west transportation hubs, have
been delivered or are in transit to the Port Facility in Bathurst
Inlet, Nunavut. In addition, the underground ramp has been
progressed to our first ore access sublevel and will be
sufficiently completed to enable underground drilling of the V2
zone in the 4th quarter of this year. With financing in
hand and these significant activities completed, the Board of
Directors of the Company has made a formal construction decision
for the Goose Mine.
“This is a milestone decision for the Company,”
said Bruce McLeod, President & CEO “We are excited to formally
commit to becoming a significant Canadian gold producer. In the
meantime, we have been steadily advancing the project to be in a
position to commence full construction in early 2023 with first
production expected in Q1, 2025. Our recruitment efforts continue
to be successful with considerable additions to the roster (from 30
personnel in March to 142 to-date and still adding), including many
key positions.”
“Additionally, we are fortunate that our
strategy of pre-planning and accelerating procurement efforts has
reduced our exposure to inflationary impacts and supply chain
issues, and we are sufficiently funded for construction. This is an
exciting time for the Company as we move to develop what we believe
will be the first mine on this prolific gold district,” he
said.
After the Company arranged over ~C$800 million
of project financing package earlier this year, significant
procurement, engineering and civil work has been completed at both
the Goose site and the Port facility.
Of the C$610 million CAPEX estimated,
approximately C$218 million was identified as direct equipment and
materials purchases. Sabina has procured, or has committed
agreements to procure, just over 75% of these identified
purchases. Reconciliation on purchases have seen an average
overall inflationary escalation of 14% since March of 2021, with a
20% escalation on the purchases made in 2022. The Company
continues to monitor, with a strategy of pre-planning and
accelerating procurement efforts to reduce exposure to inflationary
impacts. Efforts now focus on securing the remaining 25% of
materials required.
Advancement Highlights and
Schedule
Engineering
- FLSmidth (“FLS”) has been selected
to supply the key process equipment for the Goose Mine. The
equipment package is valued at approximately US$39 million and has
been fabricated or is in the production queue for delivery on or
before the 2023 sealift to ensure installation prior to the mine
start-up date, scheduled for Q1, 2025.
- The design for the Echo open pit,
which is to be pre-mined to enable initial tailings storage was
completed and pre-stripping is now underway. The early mining of
the Echo and Umwelt pits, will ensure approximately two years’
worth of stock-piled feed for the mill, will be available prior to
commencement of operations; and
- Detailed engineering is approaching
85% completion for the overall project and approximately 95% for
the process plant design. The remaining engineering activities are
focused on updating vendor data, as the procurement activities
progress on miscellaneous equipment.
- Issued For Construction drawings
(“IFC”) for all structures are complete with engineering on IFC
secondary steel structures expected during the 3rd quarter of this
year. Additionally, the IFC drawings for the process plant piping
are also near completion.
Procurement
All major items for construction have been procured.
Items include:
- 24 MW (N+2 configuration) Power plant co-generation system with
boilers and ancillary equipment (prime power generators) have
already been delivered to our Port;
- 95% of the planned mining fleet;
- All major process plant components (for a plant with a capacity
of 4000 TPD);
- Permanent accommodation complex (500 units) with kitchen and
recreation center;
- 95% of building envelope steel and cladding;
- 100% of project explosives required for construction
phase;
- Mobile cranes and major construction support equipment;
- Allof the project cement & rebar requirements – with
concrete batch plant available on site;
- 80% of secondary structural steel for the process plant and
Process piping;
- 100% of all tailing, reclaim and freshwater piping for the
project (~11.5Km of piping).
- All conveyor galleries and arctic corridors.
- All electrical E-houses.
- Electrical switch gear for the Powerhouse.
- Water and sewage treatment plant.
- HVAC unit and Dust collections systems.
- Fuel dispensing and offloading system for Goose and the port
site.
- All the construction and mobile equipment required for the
winter ice road construction (construction on both ends of the road
to commence simultaneously).
- Crushing/screening unit and washer plant on site for concrete
aggregate;
- Additional 15 million liter tank storage for both Goose and
Port sites; and
- Liner material for all water management structures.
There is approximately C$62 million of remaining
items to be procured. Financing is in hand for these items which
include:
- Remaining platework, pumps and tank insulation - materials for
which engineering is completed and quotes are being finalized;
- Electrical bulks and cable tray;
- Electrical miscellaneous equipment (process plant and
powerplant);
- PLC controls systems;
- Instrumentation for the project;
- Communication systems; and
- Balance of fuel storage at Goose and Port Sites.
Civil Works & Logistics
Considerable pre-development activities have already been
completed at the Goose and Port sites.
Port Facility and 2022 Sealift
At the Port Facility an additional 25,000m2 of laydown area for
equipment and supply storage has been completed.
To reduce the length of the Winter Ice Road
(“WIR”) route and improve alignment, an additional 1.9 km of
permanent road was constructed to better align and improve traffic
flow through the port site.
Port Facility Work Completed in
2022: https://www.globenewswire.com/NewsRoom/AttachmentNg/6671b636-078a-47e9-a2ca-bc3d935ed740
Additionally, 1.7 km of fuel transfer conduit and road was
constructed and installed to safely and efficiently facilitate this
year’s fuel delivery.
Completed Fuel Transfer Conduit at Port
Facility: https://www.globenewswire.com/NewsRoom/AttachmentNg/d94ec9f4-9530-48ea-99d1-22e6af1e28bc
The first vessel from the east arrived at the
Port Facility on August 24 with approximately $67.5 million of
equipment and supplies to be offloaded. The vessel has been
successfully off-loaded and has departed our port.
First Vessel received, off-loaded and departed September 6th,
2022: https://www.globenewswire.com/NewsRoom/AttachmentNg/8154a211-7efe-4de5-8661-5e5ba703ebee
The first barge with equipment & supplies from the west is
expected to depart Tuktoyaktuk on September 7, 2022 with
scheduled arrival at the Port Facility on September
12th. The second sailing from the west is expected to
depart on September 9th. The fuel delivery vessel arrived at the
Port Facility on September 5th and is scheduled to be
off-loaded.
Goose Site Civil Works
At Goose, approximately 45% of overall project and ~98% of plant
site civil works have been completed or are underway including:
- All building bedrock preparations are nearing completion to be
ready for concrete civil crews next year;
- 25M liter fuel berm containment is complete;
- 10M liter fuel tank is being prepared for the WIR fuel
offload;
- Fresh and potable water systems are being constructed for
permanent camp use;
- Plant site dump pond lining placement is underway; and
- Exploration camp upgrades have been completed.
Aerial View of Process and Accommodation Pad &
Road
Network: https://www.globenewswire.com/NewsRoom/AttachmentNg/341d7963-69b4-4ce5-8176-418136053913
Arial View Of Plant and Accommodation
Pad: https://www.globenewswire.com/NewsRoom/AttachmentNg/59384730-028e-44eb-b681-87e48473a282
10M Liter Fuel Tank and Berm and
plant/accommodation pad construction
2022: https://www.globenewswire.com/NewsRoom/AttachmentNg/32352b10-299f-4fae-887a-569c373cb188
Additionally, Echo Pit pioneering work is
underway with initial stripping completed and approximately
40,000m3 of material broken. The Echo pit haul road and non-contact
water diversion is also under construction.
Pre-Stripping at Echo
Pit: https://www.globenewswire.com/NewsRoom/AttachmentNg/ca2ff9bf-794d-42f3-b035-09b1a42a47fe
Development of the underground portal has progressed with
approximately 992m completed. With first underground exploration
drilling expected to commence in the 4th quarter.
Umwelt Underground Portal September
2022: https://www.globenewswire.com/NewsRoom/AttachmentNg/bc1b3b0d-e8fa-4d5f-94ce-021eef224437
Human Resources and
Recruitment
Upon completion of the project financing package
earlier this year, the Company established a Human Resources team
with a focus on recruiting and enhancing exiting policies and
protocols to enable successful development into a producer. The HR
team has been very successful in adding key personnel to the
Company roster increasing from 30 full-time employees in March of
this year to 142 full-time employees to-date.
Alternative Energy
Initiative
Sabina has submitted a regulatory package to the
Nunavut Planning Commission and the Nunavut Impact Review Board
focused on the advancement of the Back River Alternate Energy
Center. This proposal could allow Sabina to install up to 13
wind turbines, each with a power capacity of up to 4.5 megawatts, a
solar panel array with a power capacity of approximately 5
megawatts and a battery storage system with a capacity of
approximately 50 megawatt-hours. If approved and constructed the
Back River Alternate Energy Center will significantly reduce
Project greenhouse gases emissions, reduce traffic on the Winter
Ice Road, and reduce the number of ships required. Sabina
anticipates further direction on process from the Nunavut Impact
Review Board in the coming months.
SABINA GOLD & SILVER
CORP
Sabina Gold & Silver Corp. is an emerging
gold mining company that owns 100% of the district scale, advanced,
high grade Back River Gold District in Nunavut, Canada.
Sabina filed an Updated Feasibility Study (the
“UFS”) on its first mine on the district, the Goose Mine, which
presents a project that will produce ~223,000 ounces of gold a year
(first five years average of 287,000 ounces a year with peak
production of 312,000 ounces in year three) for ~15 years with a
rapid payback of 2.3 years, with a post-tax IRR of ~28% and NPV5%
of C$1.1B at a gold price of $1,600 USD. See “National Instrument
(NI) 43-101 Technical Report – 2021 Updated Feasibility Study for
the Goose Project at the Back River Gold District, Nunavut, Canada”
dated March 3, 2021.
The Project has received all major permits and
authorizations for construction and operations.
The Company has arranged a comprehensive project
financing package comprised of:
- A US$425 million senior secured
debt facility, gold prepay and stream package with Orion Mine
Finance and Wheaton Precious Metals Corp.; and
- US$221 million in equity including
Zhaojin’s participation.
The Company is also very committed to its Inuit
stakeholders, with Inuit employment and opportunities a focus.
The Company has signed a 20-year renewable land use agreement
with the Kitikmeot Inuit Association and has committed to
various sustainability initiatives under the agreement.
The Company continues to advance exploration and
project optimization, including advancing the planned plant
expansion to 4,000 tpd from Year two to initial startup.
All news releases and further information can be
found on the Company’s website at www.sabinagoldsilver.com or on
SEDAR at www.sedar.com. All technical reports have been
filed on www.sedar.com
For further information please contact:
Nicole Hoeller, Vice-President,
Communications: 1 888
648-4218
nhoeller@sabinagoldsilver.com
Forward Looking InformationThis
news release contains “forward-looking information” within the
meaning of applicable securities laws (the “forward-looking
statements”), including, but not limited to, statements
related to the expected use of proceeds of the Offering and the
projections and assumptions of the results of the UFS. These
forward-looking statements are made as of the date of this news
release. Readers are cautioned not to place undue reliance on
forward-looking statements, as there can be no assurance that the
future circumstances, outcomes or results anticipated in or implied
by such forward-looking statements will occur or that plans,
intentions or expectations upon which the forward-looking
statements are based will occur. While we have based these
forward-looking statements on our expectations about future events
as at the date that such statements were prepared, the statements
are not a guarantee that such future events will occur and are
subject to risks, uncertainties, assumptions and other factors
which could cause events or outcomes to differ materially from
those expressed or implied by such forward-looking statements. Such
factors and assumptions include, among others, the uncertainty of
production, development plans and costs estimates for the Back
River Gold Project; discrepancies between actual and estimated
mineral reserves and mineral resources, between actual and
estimated development and operating costs; the interpretation of
drill, metallurgical testing and other exploration results; the
ability of the Company to retain its key management employees and
skilled and experienced personnel; exploration, development and
mining risks and the inherently dangerous nature of the mining
industry, and the risk of inadequate insurance or inability to
obtain insurance to cover these risks and other risks and
uncertainties; property and mineral title risks including defective
title to mineral claims or property; the effects of general
economic conditions, commodity prices, changing foreign exchange
rates and actions by government and regulatory authorities; and
misjudgments in the course of preparing forward-looking statements.
In addition, there are known and unknown risk factors which could
cause our actual results, performance or achievements to differ
materially from any future results, performance or achievements
expressed or implied by the forward-looking statements. Known risk
factors include risks associated with exploration and project
development; the need for additional financing; the calculation of
mineral resources and reserves; operational risks associated with
mining and mineral processing; fluctuations in metal prices; title
matters; government regulation; obtaining and renewing necessary
licenses and permits; environmental liability and insurance;
reliance on key personnel; the potential for conflicts of interest
among certain of our officers or directors; the absence of
dividends; currency fluctuations; labour disputes; competition;
dilution; the volatility of the our common share price and volume;
future sales of shares by existing shareholders; and other risks
and uncertainties, including those relating to the Back River
Project and general risks associated with the mineral exploration
and development industry described in our Annual Information Form,
financial statements and MD&A for the fiscal period ended
December 31, 2021 filed with the Canadian Securities Administrators
and available at www.sedar.com. Although we have attempted to
identify important factors that could cause actual actions, events
or results to differ materially from those described in
forward-looking statements, there may be other factors that cause
actions, events or results not to be as anticipated, estimated or
intended. There can be no assurance that forward-looking statements
will prove to be accurate, as actual results and future events
could differ materially from those anticipated in such statements.
Accordingly, readers should not place undue reliance on
forward-looking statements. We are under no obligation to update or
alter any forward-looking statements except as required under
applicable securities laws.
Bruce McLeod, President & CEO1800-555 Burrard
Street, Two Bentall CentreVancouver, BC V7X 1M9Tel 604
998-4175 Fax 604
998-1051http://www.sabinagoldsilver.com
Sabina Gold and Silver (TSX:SBB)
Historical Stock Chart
Von Dez 2024 bis Jan 2025
Sabina Gold and Silver (TSX:SBB)
Historical Stock Chart
Von Jan 2024 bis Jan 2025