K92 Mining Inc. (“
K92” or the
“
Company”) (TSX
: KNT;
OTCQX
: KNTNF) is pleased to announce quarterly
production results for the first quarter (“
Q1”) of
2024 at its Kainantu Gold Mine in Papua New Guinea, of 27,462
ounces AuEq or 24,389 oz gold, 1,443,300 lbs copper and 35,650 oz
silver. Sales during the quarter were 27,996 oz gold, 1,582,668 lbs
copper and 38,812 oz silver.
Production for Q1 exceeded budget, even with the
temporary suspension of underground operations on March 10, 2024
that impacted the remaining 22 days of the quarter, after a
non-industrial incident and the issuance of a Form 29 from the
Mineral Resources Authority (see March 19, 2024 press release). As
announced on April 8, 2024, the Form 29 has been vacated.
Underground operations are now fully operational and K92 reiterates
its 2024 Operational Guidance.
During the first quarter, the process plant
delivered tonnes processed of 130,632 tonnes or 1,436 tpd, an
increase of 11% from Q1 2023 and 5% greater than the Stage 2A
Expansion plant design of 1,370 tpd or 500,000 tpa. During the
quarter, multiple throughput records were achieved, with the latest
daily throughput record achieved on January 21st of 2,389 tonnes
processed, monthly throughput record achieved in January of 57,144
tonnes processed or 1,843 tpd, and a 7-day throughput record
achieved in January averaging 2,149 tpd(2), exceeding the Stage 2A
Expansion design throughput by 74%, 34% and 57%, respectively. The
strong performance of the plant has been consistently better than
the Stage 2A Expansion plant design rates, exceeding those rates
for 95% of the operational days in January and February. The
outstanding plant performance to date continues to demonstrate a
meaningful immediate opportunity of having significantly greater
plant capacity than expected. Since the Stage 2A Expansion and
Stage 3 Expansion plant designs utilize the same conservative
design parameters, these records also demonstrate that the design
of the Stage 3 Expansion process plant currently under construction
has the potential for significantly greater capacity than its 1.2
million tonnes per annum design.
For the quarter, the process plant delivered
metallurgical recoveries of 90.7% for gold and 91.9% for copper.
Head grades during the quarter averaged 7.2 g/t AuEq or 6.4 g/t
gold, 0.55% copper and 10.6 g/t silver. Grade was lower than
planned due to the temporary suspension of underground operations
as noted above, resulting in a significantly larger amount of
stockpiles processed in March.
During the quarter, 10 levels were mined, with
mining on Kora conducted on the 1110, 1150, 1185, 1225, 1285 and
1305 levels, and Judd on the 840, 1205, 1305, 1325, and 1345
levels. Long hole open stoping performed to design.
In the first quarter, the mine delivered 111,054
tonnes of ore mined. Overall mine development achieved a total of
1,682 metres. Material movements and underground development were
lower than planned due to the temporary suspension of underground
operations as noted above, in addition to reduced contractor
surface haulage availability for approximately 10 weeks (second
half of Q4 to mid-February 2024), and a wetter than average rainy
season.
See Figure 1: Quarterly Production, Cash Cost and
AISC ChartSee Figure 2: Process Plant Throughput Performance and
Daily Records and Near-Records
Table 1 – 2024 & 2023 Annual Production
Data
|
|
Q1 2023 |
Q2 2023 |
Q3 2023 |
Q4 2023 |
2023 |
Q1 2024 |
Tonnes Processed |
T |
117,903 |
112,471 |
121,201 |
151,908 |
503,484 |
130,632 |
Feed Grade Au |
g/t |
5.2 |
8.2 |
6.2 |
7.4 |
6.8 |
6.4 |
Feed Grade Cu |
% |
0.70% |
0.66% |
0.72% |
0.87% |
0.75% |
0.55% |
Recovery (%) Au |
% |
89.1% |
92.4% |
92.0% |
91.7% |
91.5% |
90.7% |
Recovery (%) Cu |
% |
91.3% |
92.8% |
93.0% |
93.6% |
92.8% |
91.9% |
Metal in Conc & Doré Prod Au |
oz |
17,593 |
27,405 |
22,227 |
33,309 |
100,533 |
24,389 |
Metal in Conc Prod Cu |
T |
749 |
692 |
809 |
1,238 |
3,488 |
655 |
Metal in Conc Prod Ag |
oz |
29,891 |
34,001 |
40,233 |
56,502 |
160,628 |
35,650 |
Gold Equivalent Production |
oz |
21,488 |
30,794 |
26,225 |
39,101 |
117,607 |
27,462 |
Notes – Gold equivalent for Q1 2024 is calculated
based on: gold $2,070 per ounce; silver $23.34 per ounce; and
copper $3.83 per pound.
Gold equivalent for Q4 2023 is calculated based on:
gold $1,974 per ounce; silver $23.20 per ounce; and copper $3.71
per pound.
Gold equivalent for Q3 2023 is calculated based on:
gold $1,928 per ounce; silver $23.57 per ounce; and copper $3.79
per pound.
Gold equivalent for Q2 2023 is calculated based on:
gold $1,976 per ounce; silver $24.13 per ounce; and copper $3.85
per pound.
Gold equivalent for Q1 2023 is calculated based on:
gold $1,890 per ounce; silver $22.55 per ounce; and copper $4.05
per pound.
Qualified Person
K92 Mine Geology Manager and Mine Exploration
Manager, Andrew Kohler, PGeo, a qualified person under the meaning
of Canadian National Instrument 43-101 – Standards of Disclosure
for Mineral Projects, has reviewed and is responsible for the
technical content of this news release. Data verification by Mr.
Kohler includes significant time onsite reviewing drill core, face
sampling, underground workings, and discussing work programs and
results with geology and mining personnel.
Technical Report
The Integrated Development Plan (“IDP”) for the
Kainantu Gold Mine Project in Papua New Guinea that contains
information on the Definitive Feasibility Study and Preliminary
Economic Assessment is included in a technical report, titled,
“Independent Technical Report, Kainantu Gold Mine Integrated
Development Plan, Kainantu Project, Papua New Guinea” dated October
26, 2022, with an effective date of January 1, 2022.
About K92
K92 Mining Inc. is engaged in the production of
gold, copper and silver at the Kainantu Gold Mine in the Eastern
Highlands province of Papua New Guinea, as well as exploration and
development of mineral deposits in the immediate vicinity of the
mine. The Company declared commercial production from Kainantu in
February 2018 and is in a strong financial position. A maiden
resource estimate on the Blue Lake copper-gold porphyry project was
completed in August 2022. K92 is operated by a team of mining
company professionals with extensive international mine-building
and operational experience.
On Behalf of the Company,
John Lewins, Chief Executive Officer and
Director
For further information, please contact David
Medilek, P.Eng., CFA, President and Chief Operating Officer at
+1-604-416-4445
CAUTIONARY STATEMENT REGARDING FORWARD-LOOKING
INFORMATION: This news release includes certain “forward-looking
statements” under applicable Canadian securities legislation. Such
forward-looking statements include, without limitation: (i) the
results of the Kainantu Mine Definitive Feasibility Study, and the
Kainantu 2022 Preliminary Economic Assessment, including the Stage
3 Expansion, a new standalone 1.2 mtpa process plant and supporting
infrastructure; (ii) statements regarding the expansion of the mine
and development of any of the deposits; (iii) the Kainantu Stage 4
Expansion, operating two standalone process plants, larger surface
infrastructure and mining throughputs; and (iv) the potential
extended life of the Kainantu Mine.
All statements in this news release that address
events or developments that we expect to occur in the future are
forward-looking statements. Forward-looking statements are
statements that are not historical facts and are generally,
although not always, identified by words such as “expect”, “plan”,
“anticipate”, “project”, “target”, “potential”, “schedule”,
“forecast”, “budget”, “estimate”, “intend” or “believe” and similar
expressions or their negative connotations, or that events or
conditions “will”, “would”, “may”, “could”, “should” or “might”
occur. All such forward-looking statements are based on the
opinions and estimates of management as of the date such statements
are made. Forward-looking statements are necessarily based on
estimates and assumptions that are inherently subject to known and
unknown risks, uncertainties and other factors, many of which are
beyond our ability to control, that may cause our actual results,
level of activity, performance or achievements to be materially
different from those expressed or implied by such forward-looking
information. Such factors include, without limitation, Public
Health Crises, including the COVID-19 virus; changes in the price
of gold, silver, copper and other metals in the world markets;
fluctuations in the price and availability of infrastructure and
energy and other commodities; fluctuations in foreign currency
exchange rates; volatility in price of our common shares; inherent
risks associated with the mining industry, including problems
related to weather and climate in remote areas in which certain of
the Company’s operations are located; failure to achieve
production, cost and other estimates; risks and uncertainties
associated with exploration and development; uncertainties relating
to estimates of mineral resources including uncertainty that
mineral resources may never be converted into mineral reserves; the
Company’s ability to carry on current and future operations,
including development and exploration activities at the Arakompa,
Kora, Judd and other projects; the timing, extent, duration and
economic viability of such operations, including any mineral
resources or reserves identified thereby; the accuracy and
reliability of estimates, projections, forecasts, studies and
assessments; the Company’s ability to meet or achieve estimates,
projections and forecasts; the availability and cost of inputs; the
availability and costs of achieving the Stage 3 Expansion or the
Stage 4 Expansion; the ability of the Company to achieve the inputs
the price and market for outputs, including gold, silver and
copper; failures of information systems or information security
threats; political, economic and other risks associated with the
Company’s foreign operations; geopolitical events and other
uncertainties, such as the conflicts in Ukraine, Israel and
Palestine; compliance with various laws and regulatory requirements
to which the Company is subject to, including taxation; the ability
to obtain timely financing on reasonable terms when required; the
current and future social, economic and political conditions,
including relationship with the communities in Papua New Guinea and
other jurisdictions it operates; other assumptions and factors
generally associated with the mining industry; and the risks,
uncertainties and other factors referred to in the Company’s Annual
Information Form under the heading “Risk Factors”.
Estimates of mineral resources are also
forward-looking statements because they constitute projections,
based on certain estimates and assumptions, regarding the amount of
minerals that may be encountered in the future and/or the
anticipated economics of production. The estimation of mineral
resources and mineral reserves is inherently uncertain and involves
subjective judgments about many relevant factors. Mineral resources
that are not mineral reserves do not have demonstrated economic
viability. The accuracy of any such estimates is a function of the
quantity and quality of available data, and of the assumptions made
and judgments used in engineering and geological interpretation,
Forward-looking statements are not a guarantee of future
performance, and actual results and future events could materially
differ from those anticipated in such statements. Although we have
attempted to identify important factors that could cause actual
results to differ materially from those contained in the
forward-looking statements, there may be other factors that cause
actual results to differ materially from those that are
anticipated, estimated, or intended. There can be no assurance that
such statements will prove to be accurate, as actual results and
future events could differ materially from those anticipated in
such statements. Accordingly, readers should not place undue
reliance on forward-looking statements. The Company disclaims any
intention or obligation to update or revise any forward-looking
statements, whether as a result of new information, future events
or otherwise, except as required by law.
Figure 1: Quarterly Production, Cash Cost and AISC
Chart
Figure 2: Process Plant Throughput Performance,
Daily Records and Near-Records
Photos accompanying this announcement are available at:
https://www.globenewswire.com/NewsRoom/AttachmentNg/d5db7dfd-3c1e-4eeb-84ad-a96d0166eab6
https://www.globenewswire.com/NewsRoom/AttachmentNg/44d8d19d-579e-4e72-a31c-ff202ee3ac17
K92 Mining (TSX:KNT)
Historical Stock Chart
Von Dez 2024 bis Jan 2025
K92 Mining (TSX:KNT)
Historical Stock Chart
Von Jan 2024 bis Jan 2025