23% After-tax Internal Rate of
Return
Payback 3.4 years
Net
Present Value $261
million
All amounts are in US dollars, unless
otherwise
indicated.
TORONTO, Oct. 22, 2018 /CNW/ - IAMGOLD Corporation
("IAMGOLD" or the "Company") today announced positive results from
a Feasibility Study ("FS") for its Boto Gold Project (the
"Project") in Senegal,
West Africa. The results outline
an economically robust project with an anticipated low cost of
production and long operating life. The FS demonstrates a
significant economic and operational improvement compared to the
Pre-feasibility Study ("PFS") results announced in February of this
year. The FS will be used to support an application for a mining
concession in the fourth quarter of 2018.
PROJECT HIGHLIGHTS (100% BASIS)
- Proven and Probable Reserves ("P&P") increased by 0.51
million ounces to 1.93 million ounces grading 1.71 g/t Au
versus the P&P Reserves from the PFS
- Indicated Resources (including Reserves) of 2.49 million ounces
grading 1.61 g/t Au
- Mine Life of 12.8 years with
mill throughput of 2.75 million tonnes per annum
- Life of Mine ("LOM") average annual production of 140,000
ounces, averaging 160,000 ounces annually during the first six
years
- LOM cash costs of $714/oz and
all-in sustaining costs of $753/oz
- After-tax Internal Rate of Return of 23%, with a payback period
of 3.4 years
- Net Present Value of $261 million
(6% discount rate) at a gold price of $1,250/oz
- Initial capital expenditures of $254
million
Steve Letwin, President and CEO
of IAMGOLD, said "Boto Gold has
evolved from a grass roots exploration discovery to a robust
development project with nearly 2 million ounces in reserves. I
congratulate the team for their success in improving the project
economics by as much as they have. The 23% after-tax IRR and the
151% increase in the NPV at a lower gold price assumption are
marked improvements from those reported in the pre-feasibility
study. This is a solid, low-cost project which is expected to
deliver 140,000 ounces annually, on average, for nearly 13 years.
While a final investment decision is yet to be made, and there is
still permitting work to be done, we're looking at a high-value
project that adds to IAMGOLD's already impressive growth
profile."
The FS was completed jointly by IAMGOLD and Lycopodium Minerals
Canada Ltd ("Lycopodium"), with inputs from technical studies
completed by Specialist Consultants. The FS represents a
comprehensive study of the technical and economic viability of a
mineral project that has advanced to a stage where a preferred
mining method is established and an effective method of mineral
processing is determined.
A technical report summarizing the FS will be filed on SEDAR
tomorrow.
FS HIGHLIGHTS (100% BASIS)
Project Economics
and Key Parameters
|
|
|
Mining
Capacity
|
18.2 Mtpa
|
Milling
Capacity
|
2.75 Mtpa
|
LOM Average Annual
Gold Production
|
140,000 oz
|
LOM Average Recovery
Rate
|
89.5%
|
Mine Life
|
12.8 years
|
LOM Average Total
Cash Costs
|
$714/oz
|
LOM Average
AISC
|
$753/oz
|
Average
Grade
|
1.71 g/t
Au
|
Average LOM Strip
Ratio
|
5.8:1
|
Estimated Capital
Expenditure
|
|
Initial
Capital
|
$254
million
|
Sustaining Capital
|
$66
million
|
Gold Price Assumption
used in financial analysis
|
$1,250/oz
|
After-tax NPV
(6%)
|
$261
million
|
After-tax
IRR
|
23.0%
|
Payback
Period
|
3.4 years
|
€/US$ exchange rate of 1:1.20; Oil price of
$75 per barrel
MINERAL RESOURCES
The Mineral Resource estimate used as the basis for the study is
summarized below.
Mineral Resource
Statement – May 8, 2018
|
Classification
|
Tonnes
(000)
|
Grade
(g/t
Au)
|
Contained
Ounces
(000)
|
Attributable
Contained
Ounces
(000)
|
Indicated
|
48,045
|
1.61
|
2,487
|
2,238
|
Inferred
|
2,483
|
1.80
|
144
|
130
|
Notes:
|
|
1.
|
CIM Definition
Standards were followed for classification of Mineral
Resources.
|
2.
|
Mineral Resources are
inclusive of Mineral Reserves.
|
3.
|
Cut-off grades used
to report mineral resources vary from 0.37 g/t Au and 0.51 g/t Au
depending on alteration profile.
|
4.
|
Mineralized Resources
are reported within optimized constraining shells.
|
5.
|
Mineral Resources are
estimated using a long-term gold price of $1,500 per
ounce.
|
6.
|
Attributable is a
representation of dividends calculated as 90% for IAMGOLD, with 10%
to the government of Senegal.
|
MINERAL RESERVES
The tonnes, grades, and classification of the Mineral Reserves
captured within the FS mine plan are summarized below.
Mineral Reserve
Statement - Aug 30, 2018
|
Classification
|
Tonnes
(000)
|
Grade
(g/t
Au)
|
Contained
Ounces
(000)
|
Attributable
Contained Ounces
(000)
|
Probable
|
35,060
|
1.71
|
1,926
|
1,733
|
Proven &
Probable
|
35,060
|
1.71
|
1,926
|
1,733
|
|
|
|
|
|
Waste within Designed
Pit
|
204,335
|
|
|
|
Total Tonnage within
Designed Pit
|
239,397
|
|
|
|
Notes:
|
|
1.
|
CIM Definition
Standards were followed for classification of Mineral
Reserves.
|
2.
|
Reserves estimated
assuming open pit mining methods.
|
3.
|
Reserves are based on
a gold price of $1,200/oz.
|
4.
|
Cut-off grades varied
between 0.46 g/t Au and 0.63 g/t Au depending on alteration profile
and pit area.
|
5.
|
Average process
recovery of 89.5%.
|
6.
|
Mining costs ($/t
processed): $13.01/t. Processing costs: $15.04/t.
G&A (Include refining cost): $4.22/t.
|
7.
|
Attributable is a
representation of dividends calculated as 90% for IAMGOLD, with 10%
to the government of Senegal.
|
MINING AND PROCESSING
The FS confirms the preferred development approach to be a
conventional truck and shovel open pit mining operation with a
mineral processing circuit incorporating primary crushing,
grinding, and cyanide leaching, followed by gold recovery using
carbon-in-pulp, stripping and electrowinning.
Open pit mining includes approximately 14 Mt of waste stripping
and 2 Mt of ore stockpiling in pre-production mining during a
fifteen month pre-production period followed by 12.8 years of
production mining along with stockpile reclaim. Maximum
mining rate is 33 Mt per annum. The average ore grade is 1.71
g/t Au and the LOM stripping ratio is 5.8:1.
Future Work
The FS will be used to support an application for a mining
concession to be submitted in the fourth quarter of 2018, with
approval expected in the first half of 2019. In the interim,
the project team will continue to optimize aspects of the project
design and complete an infrastructure condemnation drilling
program. The exploration team has worked to consolidate additional
exploration concessions near the Boto Gold Project, and will
conduct ongoing exploration to expand resources in proximity to the
resource pits, and identify and evaluate high priority exploration
targets for additional mineral resources.
Qualified Persons
The FS was prepared by IAMGOLD and Lycopodium and incorporates
the work of IAMGOLD, Lycopodium and Specialist Consultants
Qualified Persons (QPs) (as defined under National Instrument
43-101). QPs are independent of IAMGOLD and have reviewed and
approved this news release. IAMGOLD QPs are not independent
of IAMGOLD and have reviewed and approved this news release. The
areas of responsibility for each QP involved in preparing the FS,
upon which the technical report will be based, are:
Lycopodium QPs
- N. Lincoln, P. Eng., Summary,
introduction, project infrastructure, reliance on other experts,
metallurgical testing and mineral processing, recovery methods,
overall capital and plant operating costs
- R. McIsaac P. Eng. (Knights Piésold), Tailings and water
management
Specialist Consultants QPs
- P. Daigle, P.Eng. (AGP Mining Consultants) Summary,
accessibility, geological setting, deposit type, exploration,
drilling, sample preparation and analysis and security, data
verification, mineral resource estimate
- G. Zurowski, P. Eng. (AGP Mining Consultants), Summary, mine
design, mine capital and operating costs, reserve estimate
- R. Thomas, MAusIMM CP Geotech (Absolute Geotechnics
Consultant), Open pit geotechnical
IAMGOLD QPs
- M. Lanctot, Ing., Summary, property description, historical
setting, permitting, financial analysis and adjacent
properties
The information in this news release was reviewed and approved
by Craig MacDougall, P.Geo., Senior
Vice President, Exploration for IAMGOLD. Mr. MacDougall is a
Qualified Person as defined by National Instrument 43-101.
CONFERENCE CALL
A conference call will be held on Tuesday, October 23, 2018 at 8:30 a.m. (Eastern Daylight Time) for a
discussion with management regarding the results of the feasibility
study for the Boto Gold Project. A webcast of the conference call
will also be available through IAMGOLD`s website -
www.iamgold.com.
Conference Call Information: North America Toll-Free:
1-800-319-4610 or 1-604-638-5340.
A replay of this conference call will be accessible for one
month following the call by dialing: North America toll-free: 1-800-319-6413 or
1-604-638-9010, passcode: 2697#.
Forward-Looking Information
All Mineral Reserve and Mineral Resources estimates reported by
the Company were estimated in accordance with the Canadian National
Instrument 43-101 and the Canadian Institute of Mining, Metallurgy,
and Petroleum Definition Standards (May 10,
2014). These standards differ significantly from the
requirements of the U.S. Securities and Exchange Commission.
Mineral Resources which are not Mineral Reserves do not have
demonstrated economic viability.
This document contains "forward-looking information" within the
meaning of Canadian securities legislation and "forward-looking
statements" within the meaning of the United States Private
Securities Litigation Reform Act of 1995. This information and
these statements, referred to herein as "forward-looking
statements" are made as of the date of this document.
Forward-looking statements relate to future events or future
performance and reflect current estimates, predictions,
expectations or beliefs regarding future events and include, but
are not limited to, statements with respect to:
(i) the estimated amount and grade
of Mineral Resources and Mineral Reserves;
(ii) the FS representing a viable
development option for the Project;
(iii) estimates of the capital
costs of constructing mine facilities and bringing a mine into
production, of sustaining capital and the duration of financing
payback periods;
(iv) the estimated amount of
future production, both produced and metal recovered; and,
(v) estimates of operating costs
and total costs, net cash flow, net present value and economic
returns from an operating mine.
Any statements that express or involve discussions with respect
to predictions, expectations, beliefs, plans, projections,
objectives or future events or performance (often, but not always,
using words or phrases such as "expects", "anticipates", "plans",
"projects", "estimates", "envisages", "assumes", "intends",
"strategy", "goals", "objectives" or variations thereof or stating
that certain actions, events or results "may", "could", "would",
"might" or "will" be taken, occur or be achieved, or the negative
of any of these terms and similar expressions) are not statements
of historical fact and may be forward-looking statements.
All forward-looking statements are based on IAMGOLD's or its
consultants' current beliefs as well as various assumptions made by
them and information currently available to them. The most
significant assumptions are set forth above, but generally these
assumptions include:
(i) the presence of and continuity
of metals at the Boto Project at estimated grades;
(ii) the geotechnical and
metallurgical characteristics of rock conforming to sampled
results; including the quantities of water and the quality of the
water that must be diverted or treated during mining
operations;
(iii) the capacities and
durability of various machinery and equipment;
(iv) the availability of
personnel, machinery and equipment at estimated prices and within
the estimated delivery times;
(v) currency exchange rates;
(vi) metals sales prices and
exchange rate assumed;
(vii) appropriate discount rates
applied to the cash flows in the economic analysis;
(viii) tax rates and royalty rates
applicable to the proposed mining operation;
(ix) the availability of
acceptable financing under assumed structure and costs;
* anticipated mining losses and
dilution;
(xi) metallurgical
performance;
(xii) reasonable contingency
requirements;
(xiii) success in realizing
proposed operations;
(xiv) receipt of permits and other
regulatory approvals on acceptable terms; and
(xv) the fulfillment of
environmental assessment commitments and arrangements with local
communities.
Although management considers these assumptions to be reasonable
based on information currently available to it, they may prove to
be incorrect. Many forward-looking statements are made assuming the
correctness of other forward looking statements, such as statements
of net present value and internal rates of return, which are based
on most of the other forward-looking statements and assumptions
herein. The cost information is also prepared using current values,
but the time for incurring the costs will be in the future and it
is assumed costs will remain stable over the relevant period.
By their very nature, forward-looking statements involve
inherent risks and uncertainties, both general and specific, and
risks exist that estimates, forecasts, projections and other
forward-looking statements will not be achieved or that assumptions
do not reflect future experience. We caution readers not to place
undue reliance on these forward-looking statements as a number of
important factors could cause the actual outcomes to differ
materially from the beliefs, plans, objectives, expectations,
anticipations, estimates assumptions and intentions expressed in
such forward-looking statements. These risk factors may be
generally stated as the risk that the assumptions and estimates
expressed above do not occur as forecast, but specifically include,
without limitation: risks relating to variations in the mineral
content within the material identified as Mineral Resources and
Mineral Reserves from that predicted; variations in rates of
recovery and extraction; the geotechnical characteristics of the
rock mined or through which infrastructure is built differing from
that predicted, the quantity of water that will need to be diverted
or treated during mining operations being different from what is
expected to be encountered during mining operations or post
closure, or the rate of flow of the water being different;
developments in world metals markets; risks relating to
fluctuations in the Canadian dollar relative to the US dollar;
increases in the estimated capital and operating costs or
unanticipated costs; difficulties attracting the necessary work
force; increases in financing costs or adverse changes to the terms
of available financing, if any; tax rates or royalties being
greater than assumed; changes in development or mining plans due to
changes in logistical, technical or other factors; changes in
project parameters as plans continue to be refined; risks relating
to receipt of regulatory approvals; delays in stakeholder
negotiations; changes in regulations applying to the development,
operation, and closure of mining operations from what currently
exists; the effects of competition in the markets in which IAMGOLD
operates; operational and infrastructure risks and the additional
risks described in IAMGOLD's Annual Information Form filed with
SEDAR in Canada (available at
www.sedar.com ) for the year ended December
31, 2017 and in the Corporation's Annual Report Form 40-F
filed with the U.S. Securities and Exchange Commission on EDGAR
(available at
https://www.sec.gov/edgar/searchedgar/companysearch.html. IAMGOLD
cautions that the foregoing list of factors that may affect future
results is not exhaustive.
When relying on our forward-looking statements to make decisions
with respect to IAMGOLD, investors and others should carefully
consider the foregoing factors and other uncertainties and
potential events. IAMGOLD does not undertake to update any
forward-looking statement, whether written or oral, that may be
made from time to time by IAMGOLD or on our behalf, except as
required by law.
About IAMGOLD
IAMGOLD (www.iamgold.com) is a mid-tier mining company with four
operating gold mines on three continents. A solid base of strategic
assets in North and South America
and West Africa is complemented by
development and exploration projects and continued assessment of
accretive acquisition opportunities. IAMGOLD is in a strong
financial position with extensive management and operational
expertise.
For further information please contact:
Ken Chernin, VP Investor
Relations, IAMGOLD Corporation
Tel: (416) 360-4743 Mobile: (416) 388-6883
Laura Young, Director,
Investor Relations, IAMGOLD Corporation
Tel: (416) 933-4952 Mobile: (416) 670-3815
Martin Dumont, Senior
Analyst Investor Relations, IAMGOLD Corporation
Tel: (416) 933-5783 Mobile: (647) 967-9942
Toll-free: 1-888-464-9999 info@iamgold.com
Please note:
This entire news release may be accessed via fax, e-mail,
IAMGOLD's website at www.iamgold.com and through CNW Group's
website at www.newswire.ca. All material information on IAMGOLD can
be found at www.sedar.com or at www.sec.gov.
Si vous désirez obtenir la version française de ce communiqué,
veuillez consulter le
http://www.iamgold.com/French/accueil/default.aspx.
View original
content:http://www.prnewswire.com/news-releases/iamgolds-feasibility-study-for-boto-gold-delivers-significantly-improved-project-economics-300735166.html
SOURCE IAMGOLD Corporation