All dollar amounts shown in United States dollars unless otherwise
noted
VANCOUVER, BC , Jan. 25,
2023 /PRNewswire/ - Equinox Gold Corp. (TSX:
EQX) (NYSE American: EQX) is pleased to provide an update on
construction progress at its Greenstone Project in Ontario, Canada. The Greenstone Project is
being developed as a 60/40 partnership, respectively, by Equinox
Gold and Orion Mine Finance Group and will be one of the largest
gold mines in Canada, producing
more than 400,000 ounces of gold annually for the first five years
and more than five million ounces of gold over its initial 14-year
mine life.
Greenstone construction progress is documented weekly in a photo
gallery on Equinox Gold's website at www.equinoxgold.com and
select photos are included in this news release.
Recent Highlights (at January
13, 2023 unless otherwise noted)
- On schedule – The Greenstone Project is over 66%
complete and on schedule to pour gold in the first half of
2024.
- On budget – The Greenstone Project remains on budget. At
December 31, 2022, 71% of total
capital costs had been contracted and $680
million (55%) of the $1.23
billion construction budget had been spent (100% basis).
Inflationary pressures have been mitigated through offsetting
savings opportunities or absorbed through the $177 million contingency included in the
construction budget.
- Facilities completed – The construction team has
completed the Ministry of Transportation (MTO) Patrol Yard, the
Goldfield Creek diversion and the permanent effluent water
treatment plant. The first four bays of the truck shop are complete
and in use. The 14-km natural gas pipeline is complete and ready
for commissioning in Q2 2023.
- Equipment delivery continues to support the construction
schedule, with key equipment on site or enroute.
- Pre-production mining commenced ahead of schedule – The
first four mining haul trucks and the first shovel were
commissioned during Q3 2022 and mine pre-production activities got
underway in September, ahead of schedule, with more than 2.5
million tonnes of material (ore, waste and overburden) mined to
year-end 2022.
Greg Smith, President & CEO
of Equinox Gold, commented: "The Greenstone Project is now more
than two-thirds complete and remains on budget and on schedule.
With key equipment on site or enroute, building infrastructure
essentially complete and most buildings enclosed and heated, the
construction effort is shifting to interior mechanical, electrical
and piping installation during the winter months. Detailed
commissioning and operation readiness planning is well underway to
prepare for first gold pour in the first half of 2024."
Greenstone Project
Progress
Area
|
Progress to Date
(at January 13, 2023 unless otherwise noted)
|
Total Overall
Progress
|
- Overall project 66%
complete and on schedule to pour gold in the first half of
2024
- Detailed engineering complete - Procurement 77%
complete - Construction 56% complete
|
Safety
|
- More than 2
million work hours completed with
no lost-time injuries
- Project to date,
Total Recordable Injury Frequency Rate at December 31, 2022 of 3.57
per million hours worked
|
Budget
|
- Project remains on
budget. At December 31, 2022:
- 55% of total cost
spent - 71% of total cost
contracted -
30% of total cost awarded on a fixed cost
basis
|
Earthworks, Concrete
and Steel
|
- Earthworks 73%
complete (including plant site, tailings storage facility (TSF),
Goldfield Creek diversion, Highway 11 realignment, water management
infrastructure). Remaining earthworks include the TSF, which is
ongoing, and the highway realignment and crushing area, which will
recommence after the spring melt
- Concrete 77%
complete. Remainder includes the primary crusher slab on deck,
high-pressure grinding roll (HPGR) pump box, west end process plant
slab on grade and pre-leach thickening area
- Structural steel
62% complete. Remainder includes the east end process plant and the
HPGR building internal steel
|
Process
Plant
|
- Process plant 41%
complete
- Building enclosure
and heating completed as planned for the process plant west end,
power plant, secondary crusher and the ore bin tower portion of the
HPGR building. The remainder of the HPGR building and east end
process plant buildings are on schedule for enclosure in Q1 2023,
which maintains the schedule
- All mechanical,
piping and electrical installation contracts awarded, installations
underway
- All eight leach
tanks erected, mechanical installations underway
|
Equipment
Delivery
|
- All overseas and
major equipment deliveries on track, including the primary and
secondary crusher components, the apron feeder, conveyors,
thickener and remaining prefabricated electrical rooms
- All power plant
equipment received
- Ball mill delivery
timing on track to start installation in March
|
Tailings Facility and
Water Management
|
- TSF 47% complete,
south dams complete to the required elevation of 335.0
metres
- Goldfield Creek
diversion complete
- Permanent effluent
water treatment plant complete and commissioned
|
Power Plant and
Electrical
|
- Power plant 54%
complete with all six gensets installed
- Internal structural
steel, walkways and platforms 86% complete; electrical and cable
trays 30% complete
- Natural gas
pipeline complete and ready for commissioning
|
Site
Infrastructure
|
- Administration
office, plant site fuel station and reagent cold storage buildings
complete and operational
- Sewage treatment
plant complete and will be released to operations in Q1 2023; truck
shop and warehouse 62% complete, first four bays of the truck shop
are in use by the mine
|
Mobile Equipment
and Mining
|
- Mine pre-production
activities operating 24/7 with more than 2.5 million tonnes of
material moved in 2022
- Four
250-tonne CAT 793F
trucks, two Epicron D65 drills,
one Komatsu PC5500
shovel and two Komatsu D475A-8 bulldozers
were in use at year-end 2022
- Commitment agreed
on mobile equipment lease financing for $78 million, deferring
approximately $53 million of initial capital spend (100%
basis)
|
Infrastructure
Repositioning
|
- Highway 11
relocation 74% complete and progressing ahead of plan
- New MTO Patrol Yard
completed on time and handed over to the Ministry; demolition of
the old facility is underway
|
Important Milestones
Construction during Q1 2023 will focus on completing enclosure
of the HPGR and process plant east end buildings, receiving the
majority of the remaining equipment, advancing mechanical, piping
and electrical installations in the process plant and power plant
buildings, and progressing the crushed ore storage and reclaim
facilities. Four additional CAT 793F haul trucks, another Komatsu
PC5500 shovel and another Komatsu D475A-8 bulldozer will be
commissioned during Q1 2023, and the sewage treatment plant,
potable water treatment plant and pit fuel station for mobile
equipment will be commissioned and released to operations.
Important construction milestones include:
- Independent QRA review of schedule and budget: June 2022
- Process plant steel erection underway: June 2022
- Administration building complete: July
2022
- Delivery and assembly of pre-production fleet of four trucks
and excavators: Q2-Q3 2022
- Start of pre-production mining: September 2022
- Permanent water effluent treatment commissioned: October 2022
- Commence installation of gensets in power plant, power building
enclosed: November 2022
- Process plant west end, truck shop and SME plant building
enclosed: December 2022
- Leach tank erection and mechanical installations complete: Q1
2023
- Ball mills received, commence installation: Q1 2023
- Crushers installed, commence pre-commissioning of crushing
circuit: Q3 2023
- TSF complete and ready for use: Q4 2023
- Highway 11 realignment complete: Q4 2023
- Commence hot commissioning: Q1-Q2 2024
- Gold pour: H1 2024
Equinox Gold Contacts
Greg Smith, President &
CEO
Rhylin Bailie, Vice President,
Investor Relations
Tel: +1 604-558-0560
Email: ir@equinoxgold.com
Construction Photos
Site overview.
West end process plant with e-room.
West end process plant – interior.
East end process plant – steelwork and cladding.
Leach tanks and process plant.
HPGR exterior.
Primary (right) and secondary (left) crushers –
exterior.
Secondary crusher – interior.
Reclaim tunnel with conveyor and chute.
Truck shop.
Power plant – exterior.
Power plant – interior.
Cautionary Notes
This news release contains certain forward-looking
information and forward-looking statements within the meaning of
applicable securities legislation. Forward-looking statements and
forward-looking information in this news release relate to, among
other things: the Company's ability to successfully advance
construction and achieve production at Greenstone; the Company's
expectations regarding construction timelines and costs for
Greenstone, including its ability to manage inflationary pressures;
the Company's expectations for the operation of Greenstone,
including production capabilities and future financial or operating
performance; and the Company's ability to work effectively with its
joint venture partner. Forward-looking statements or information
generally identified by the use of the words "will", "advance",
"progress", "on track", "on schedule", "on budget", "remain",
"focus", and similar expressions and phrases or statements that
certain actions, events or results "could", "would" or "should", or
the negative connotation of such terms, are intended to identify
forward-looking statements and information. Although the Company
believes that the expectations reflected in such forward-looking
statements and information are reasonable, undue reliance should
not be placed on forward-looking statements since the Company can
give no assurance that such expectations will prove to be correct.
The Company has based these forward-looking statements and
information on the Company's current expectations and projections
about future events and these assumptions include: construction and
development at Greenstone being completed and performed in
accordance with current expectations, including estimated capital
costs; prices for energy inputs, labour, materials, supplies and
services, and the impact of inflation on the same, remaining as
expected; the timely delivery and commissioning of equipment;
availability of funds for the Company's projects and future cash
requirements; capital, decommissioning and reclamation estimates;
Greenstone Mineral Reserve and Mineral Resource estimates and the
assumptions on which they are based; the ability to realize cost
savings through leasing of mobile equipment; prices for gold
remaining as estimated; no labour-related disruptions and no
unplanned delays or interruptions in scheduled construction,
development and production, including by blockade; all necessary
permits, licenses and regulatory approvals are received in a timely
manner; successful relationships between the Company and
Orion and between the Company and its Indigenous partners at
Greenstone; and the Company's ability to comply with
environmental, health and safety laws. While the Company considers
these assumptions to be reasonable based on information currently
available, they may prove to be incorrect. Accordingly, readers are
cautioned not to put undue reliance on the forward-looking
statements or information contained in this news release.
The Company cautions that forward-looking statements and
information involve known and unknown risks, uncertainties and
other factors that may cause actual results and developments to
differ materially from those expressed or implied by such
forward-looking statements and information contained in this news
release and the Company has made assumptions and estimates based on
or related to many of these factors. Such factors include, without
limitation: fluctuations in gold prices; fluctuations in prices for
energy inputs, labour, materials, supplies and services;
fluctuations in currency markets; operational risks and hazards
inherent with the business of mining (including environmental
accidents and hazards, industrial accidents, equipment breakdown,
unusual or unexpected geological or structural formations,
cave-ins, flooding and severe weather); inadequate insurance, or
inability to obtain insurance to cover these risks and hazards;
employee relations; relationships with, and claims by, local
communities and Indigenous partners; the Company's ability to
obtain all necessary permits, licenses and regulatory approvals in
a timely manner or at all; changes in laws, regulations and
government practices, including environmental, export and import
laws and regulations; the ability of Equinox Gold to work
productively with its joint venture partner and Indigenous partners
at Greenstone; legal restrictions relating to mining; increased
competition in the mining industry; and those factors identified in
the section titled "Risks and Uncertainties" in Equinox
Gold's MD&A dated March 23, 2022
for the year ended December 31, 2021,
and in the section titled "Risks Related to the Business" in
Equinox Gold's Annual Information Form dated March 24, 2022 for the year ended December 31, 2021, both of which are available on
SEDAR at www.sedar.com and on EDGAR at www.sec.gov/edgar.
Forward-looking statements and information are designed to help
readers understand management's views as of that time with respect
to future events and speak only as of the date they are made.
Except as required by applicable law, Equinox Gold assumes no
obligation to update or to publicly announce the results of any
change to any forward-looking statement or information contained or
incorporated by reference to reflect actual results, future events
or developments, changes in assumptions or changes in other factors
affecting the forward-looking statements and information. If
Equinox Gold updates any one or more forward-looking statements, no
inference should be drawn that Equinox Gold will make additional
updates with respect to those or other forward-looking statements.
All forward-looking statements and information contained in this
news release are expressly qualified in their entirety by this
cautionary statement.
View original content to download
multimedia:https://www.prnewswire.com/news-releases/equinox-golds-greenstone-project-on-schedule-on-budget-301730073.html
SOURCE Equinox Gold Corp.