VANCOUVER, BRITISH COLUMBIA--(Marketwire - July 19, 2012) - Eastern Platinum Limited ("Eastplats") 
(TSX:ELR)(AIM:ELR)(JSE:EPS) reports operating results from the Crocodile River Mine ("CRM") for the quarter ended June 
30, 2012 ("Q2 2012"). 
 
Production statistics for the current quarter and historical quarters are as follows: 
 
/T/ 
 
=--------------------------------------------------------------------------- 
                           Quarter ended                 Increase (decrease) 
=--------------------------------------------------------------------------- 
                                                           Q2 2012   Q2 2012 
Production   Jun 30,  Mar 31,  Dec 31,  Sep 30,  Jun 30,       vs.       vs. 
 statistics     2012     2012     2011     2011     2011   Q1 2012   Q2 2011 
=--------------------------------------------------------------------------- 
Ounces        26,412   24,474   19,854   26,955   20,528     1,938     5,884 
 produced 
=--------------------------------------------------------------------------- 
Run-of-mine  257,250  247,538  200,919  265,889  203,166     9,712    54,084 
 tonnes 
 hoisted 
=--------------------------------------------------------------------------- 
Run-of-mine  252,883  235,354  194,532  261,280  201,986    17,529    50,897 
 tonnes 
 processed 
=--------------------------------------------------------------------------- 
Development    2,922    3,117    2,929    3,976    3,562     (195)     (640) 
 (meters) 
=--------------------------------------------------------------------------- 
On-reef        1,653    1,704    1,591    2,248    2,090      (51)     (437) 
 development 
 (meters) 
=--------------------------------------------------------------------------- 
Stoping       40,959   39,857   31,767   40,594   31,828     1,102     9,131 
 units 
 (square 
 meters) 
=--------------------------------------------------------------------------- 
Head grade      3.99     4.07     4.05     4.08     3.93    (0.09)      0.06 
 (grams/tonne) 
=--------------------------------------------------------------------------- 
Concentrator     79%      77%      76%      78%      76%        1%        2% 
 recovery 
 from ROM 
 ore(i) 
=--------------------------------------------------------------------------- 
Chrome        56,521   74,920   62,791   77,531   64,913  (18,399)   (8,392) 
 dispatched 
 (tonnes) 
=--------------------------------------------------------------------------- 
(i)  Concentrator recovery has been rounded to the nearest percentage point. 
 
/T/ 
 
There have been encouraging improvements in production at the Crocodile River Mine (CRM), particularly from the 
Zandfontein section, during the second quarter of 2012. However, as a result of continued issues facing the industry, 
the Company has proposed to temporarily suspend stoping at Zandfontein and embark on a 12 to 18 month development 
program, as described in the Company's press release dated June 12, 2012. At the Maroelabult section, the Company has 
proposed to continue "on-reef" mining operations, along with the development of major conveyor development ends, with 
the objective of achieving a sustainable production target of 30,000 tpm. 
 
Should there be a marked improvement in industry conditions in the interim, CRM can react quickly and ramp up production 
at Zandfontein at any time. 
 
In keeping with the South African Labour Relations Act, CRM management is currently carrying out the required 
consultation process with potentially affected employees and their representatives to review the need for possible 
restructuring and the potential implications to staffing levels as a result of the proposed plan. 
 
Following the consultation period and final costing exercise, the Company will be in a position to provide guidance for 
production for both 2012 and 2013. 
 
The qualified person having reviewed the operating results presented in this press release is Mr. Brian Montpellier, 
P.Eng. 
 
Eastplats expects to release its full second quarter results on Tuesday, August 14, 2012. 
 
Total shares issued and outstanding: 928,187,807 
 
Cautionary Statement on Forward-Looking Information 
 
Certain statements included herein constitute "forward-looking statements" within the meaning of applicable Canadian 
securities legislation. These forward-looking statements pertain to the price of PGMs, fluctuations in currency markets 
(specifically the South African Rand and the U.S. dollar), the future development of the Company's projects, and the 
Company's plans for its properties. These forward-looking statements are based on certain assumptions by the Company and 
therefore, readers are cautioned that forward-looking statements are not a guarantee of future performance. There can be 
no assurance that such statements will prove to be accurate and actual results could differ materially from those 
expressed or implied in such forward-looking statements due to factors such as general economic and market conditions, 
changes in government legislation, controls, regulations and political developments. 
 
The Company disclaims any intention or obligation to update or revise any forward-looking statements whether as a result 
of new information, future events or otherwise, except to the extent required by applicable laws. 
 
 
 
-30- 
 
FOR FURTHER INFORMATION PLEASE CONTACT: 
 
Eastern Platinum Limited 
Investor Relations 
1-(604)-685-6851 
1-(604)-685-6493 (FAX) 
info@eastplats.com 
www.eastplats.com 
 
OR 
 
Canaccord Genuity Limited, London - NOMAD 
Rob Collins 
+44 (0) 207 7523 8000 
 
OR 
 
PSG Capital (Pty) Limited - JSE SPONSOR 
Johan Fourie 
+27 21 887 9602 
johanf@psgcapital.com 
 
No stock exchange, securities commission or other regulatory authority has approved or disapproved the information 
contained herein. 
 
 
 
 
Eastern Platinum Limited 
 

Eastern Plat (LSE:ELR)
Historical Stock Chart
Von Jun 2024 bis Jul 2024 Click Here for more Eastern Plat Charts.
Eastern Plat (LSE:ELR)
Historical Stock Chart
Von Jul 2023 bis Jul 2024 Click Here for more Eastern Plat Charts.