VANCOUVER, May 15, 2012 /PRNewswire/ - Great Basin Gold Ltd.
("Great Basin Gold" or the "Company"), (TSX: GBG) (NYSE: GBG)
(Amex: GBG) (JSE: GBG) announces that its interim consolidated
financial statements and Management Discussion and Analysis for the
quarter ended March 31, 2012 have
been filed, and the Company refers the reader to those materials
for further information. All currency values in this release
are stated in Canadian dollars unless otherwise indicated.
The Company will review the results during an investor conference
call scheduled for May 15, 2012.
|
3 months ended |
March 31 2012 |
March 31 2011 |
Recovered Au eqv oz |
22,911 |
29,593 |
Au eqv oz sold |
21,555 |
20,118 |
Realized Au eqv price |
$1,548 |
$1,309 |
Revenue ($'000) |
$33,373 |
$26,343 |
Loss from operating activities ($'000) |
($7,650) |
($377) |
Net loss for the quarter ($'000) |
($17,770) |
($20,341) |
Cash generated from (utilized by) operations
($'000) |
$565 |
($9,482) |
Adjusted loss per share |
($0.03) |
($0.02) |
Hollister
The Nevada operations produced
16,240 Au eqv oz1 for the quarter (Q1 2011:
24,082 Au eqv oz), compared to the forecast of 19,749 Au eqv oz.
Ineffective carbon stripping, while the final upgrade to the acid
wash and carbon regeneration circuit was being completed, resulted
in lower than planned Au (87%) and Ag (62%) recoveries at the
Esmeralda mill during the quarter. The upgrade to this
circuit was completed in late April
2012. All doré will be poured on site starting May 2012.
Although lower than Q1 2011, Au and Ag grades as well as tonnes
extracted from trial mining were in-line with the production plan
and good progress has been made in improving mining flexibility
through additional focus on ore development. 15,357 Au eqv oz
were sold during the quarter (Q1 2011: 17,324) with the amount of
Au eqv oz locked up in carbon and awaiting processing through third
party refiners increasing by 1,352 to 14,447 Au eqv oz on
March 31, 2012. It is expected that
this carbon will be treated during Q2 2012 and inventory levels
will return to normalized levels by the end of Q2 2012. Cash costs
per ounce of $850/oz were recorded
for the quarter (Q1 2011: $670);
costs were impacted by the lower recoveries achieved as well as the
additional transportation costs incurred to process the carbon at
the Rand Refinery in South Africa.
Following the recent receipt of the Dam Safety Permit (which
authorizes the impounding of tails, slimes and water on the TSF)
and the updated reclamation bond, construction commenced on the
three-phase expansion of the tailings storage facility (TSF). At
the currently planned production rates, Phase 1 and 2 will provide
tailings storage capacity for the next 6 years and the completion
of Phase 3 can extend this to 25 years. The current facility has
sufficient capacity for the impoundment of tails until the planned
completion of the expanded tailings facility.
Burnstone
The Burnstone operations produced 6,671 Au oz for the
quarter (Q1 2011: 5,511 Au oz), compared to the forecast of 6,327
Au oz. Production volumes were generally in-line with the
production plan with a slightly higher stoping Au grade
compensating for minor volume variances. Square meters available
for stoping more than doubled from December
31, 2011 with over 14,000 square meters being available at
March 31, 2012. Available square
meters has increased further since that time with approximately
16,200 square meters being available for stoping at the end of
April 2012. Good progress was made
during the quarter on infrastructure upgrades that will enable the
mine to maintain its momentum to meet increasing development and
production targets. Cash costs per ounce for the quarter of
$2,181 were recorded (Q1 2011:
$2,471) and were impacted by
additional water handling and employee related costs incurred.
Financial results and corporate matters
Revenue of $33 million was
recorded for the quarter, an increase of 27% over the comparative
period in 2011. The increase in revenue can be ascribed to a 7%
increase in ounces sold as well as an 18% increase in the realized
gold price. The increase in cash and non-cash costs had a negative
impact on the loss from operations which amounted to $7.7 million (2011: $0.4
million). A $2 million
increase in net interest paid when compared to Q1 2011 is due to
interest for January 2011 being
included in the Burnstone project development costs. A further
$2.6 million impairment charge on the
loan advanced to our Black Economic Empowerment partner (Tranter
Burnstone (Pty) Ltd ("Tranter")) was recorded as a result of the
decline in the Company's share price. The valuation of the
zero-cost-collar hedge structures was immaterial for the quarter as
a result of the relative sideways movement in gold prices during
this period.
The Company closed the previously announced $50 million public offering (see press release
March 15, 2012) on March 30, 2012 with the 15% over-allotment option
granted to the Underwriters closing on April
5, 2012. Net proceeds from the Offering, totalling
$54 million, will be used as working
capital for the development and production ramp up at Burnstone. At
March 31, 2012, the Company had net
working capital of $15 million, which
included $44 million in cash
reserves, and also had $10 million
available to be drawn upon under the US$150
million term facility.
Following negotiations between the Company, Tranter and Investec
Bank Limited ("Investec"), a Term sheet was agreed to in late
April 2012 to settle a mutually
beneficial proposal whereby the Company provides Tranter with
further financial assistance over a period of 18 months to enable
them to meet their proposed restructured loan repayment obligations
to Investec and thereby remove their current breach of the loan
agreement. In terms of the proposal, Investec will remove all cash
margin requirements and also restructure the repayment in such a
matter that the required assistance from the Company does not
impact on its short term cash requirements. The parties are
currently working on finalizing the legal agreements and obtaining
the required approvals to enter into the binding legal agreements.
It is anticipated that this restructured loan and financial
assistance agreement will be executed before May 30, 2012.
Ferdi Dippenaar,
Great Basin Gold President and CEO, commented: "Good progress
has been made at both Hollister and Burnstone during the first
quarter of 2012. The focus has been to improve mining
flexibility through the increase in ore development and the
establishment of additional stopes, thereby enabling the Company to
meet its annual production targets.
Burnstone achieved its planned quarterly
production targets whilst addressing short-term infrastructural
challenges, which impacted on efficiencies in late 2011 and the
first few months of 2012. This has resulted in a 6% increase
in ore development meters, up from a monthly average of 845 meters
in Q1 2012 to over 900 meters in April
2012. In addition, ore development ends at the end of
April were 62, which is an improvement of 48% over the 42 ends
available on March 31, 2012.
Continued infill drilling has shown no further geological
challenges similar to the Graben fault that significantly
influenced our production build-up at Burnstone in 2011.
The operational benefit from increased
flexibility at our Hollister Mine and the completion of the acid
wash and carbon regeneration circuit at the Esmeralda Mill is
expected to allow cash costs from trial mining activities to
decrease to the planned levels for the year."
Ferdi
Dippenaar
President and CEO
Shareholders of the Company are reminded that
they may request a hard copy of the complete audited financial
statements free of charge upon request from any of the Investor
Services personnel above or from the Company's Corporate Office at
Tel: +27 (0) 11 301 1800, Fax: +27 (0) 11 301 1840 or Email:
info@za.grtbasin.com.
This document contains "forward-looking
statements" that were based on Great Basin Gold's expectations,
estimates and projections as of the dates as of which those
statements were made. Generally, these forward-looking statements
can be identified by the use of forward-looking terminology such as
"outlook", "anticipate", "project", "target", "believe",
"estimate", "expect", "intend", "should" and similar expressions.
Forward-looking statements are subject to known and unknown risks,
uncertainties and other factors that may cause the Company's actual
results, level of activity, performance or achievements to be
materially different from those expressed or implied by such
forward-looking statements. These include but are not limited
to:
- uncertainties and costs related to the Company's exploration
and development activities, such as those associated with
determining the extent of mineral resources or reserves which
exist on a property;
- uncertainties related to feasibility studies that provide
estimates of expected or anticipated costs, expenditures and
economic returns from a mining project; uncertainties related to
expected production rates, timing of production and the cash and
total costs of production and milling;
- uncertainties related to the ability to obtain necessary
licenses, permits, electricity, surface rights and title for
development projects;
- operating and technical difficulties in connection with mining
development activities;
- uncertainties related to the accuracy of our mineral reserve
and mineral resource estimates and our estimates of future
production and future cash and total costs of production, and the
geotechnical or hydrogeological nature of ore deposits, and
diminishing quantities or grades of mineral reserves;
- uncertainties related to unexpected political, judicial
or regulatory proceedings;
- changes in, and the effects of, the laws, regulations and
government policies affecting our mining operations, particularly
laws, regulations and policies relating to
-
- mine expansions, environmental protection and associated
compliance costs arising from exploration, mine development, mine
operations and mine closures;
- expected effective future tax rates in jurisdictions in which
our operations are located;
- the protection of the health and safety of mine workers;
and
- mineral rights ownership in countries where our mineral
deposits are located, including the effect of the Mineral and
Petroleum Resources Development Act (South Africa);
- changes in general economic conditions, the financial markets
and in the demand and market price for gold, silver and other
minerals and commodities, such as diesel fuel, coal, petroleum
coke, steel, concrete, electricity and other forms of energy,
mining equipment, and fluctuations in exchange rates, particularly
with respect to the value of the U.S. dollar, Canadian dollar and
South African rand;
- unusual or unexpected formation, cave-ins, flooding, pressures,
and precious metals losses (and the risk of inadequate insurance or
inability to obtain insurance to cover these risks);
- changes in accounting policies and methods we use to report our
financial condition, including uncertainties associated with
critical accounting assumptions and estimates;
- environmental issues and liabilities associated with mining
including processing and stock piling ore;
- geopolitical uncertainty and political and economic instability
in countries which we operate; and
- labour strikes, work stoppages, or other interruptions to, or
difficulties in, the employment of labour in markets in which we
operate mines, or environmental hazards, industrial accidents or
other events or occurrences, including third party interference
that interrupt the production of minerals in our mines.
Cautionary Note regarding Non-GAAP
Measurements
Cash cost per ounce/tonne is a not a generally
accepted accounting principles ("GAAP") based figure but rather is
intended to serve as a performance measure providing some
indication of the mining and processing efficiency and
effectiveness of operations. It is determined by dividing the
relevant mining and processing costs including royalties by the
ounces produced/tonnes milled in the period. There may be some
variation in the method of computation of "cash cost per
ounce/tonne" as determined by the Company compared with other
mining companies. Cash costs per ounce/tonne may vary from one
period to another due to operating efficiencies, waste to ore
ratios, grade of ore processed and gold recovery rates in the
period. We provide this measure to our investors to allow them to
also monitor operational efficiencies. As a Non-GAAP Financial
Measure cash costs should not be considered in isolation or as a
substitute for measures of performance prepared in accordance with
GAAP. Adjusted loss per share is also a Non-GAAP measure and is
calculated by excluding the impact of certain fair-value accounting
charges and once-off transactions. We also make reference in our
disclosures to "working capital" which is also a Non-GAAP measure
and includes cash and cash equivalents, trade and other
receivables, current inventories, trade payables and accrued
liabilities. There is material limitations associated with the use
of such Non-GAAP measures.
For further information on Great Basin Gold, investors should
review the Company's annual Form 40-F filing with the United States
Securities and Exchange Commission www.sec.com and home
jurisdiction filings that are available at www.sedar.com.
_________________________
1 Gold equivalent ounces calculated using metal price
of US$1,400/oz for Au and
US$30/oz for Ag.
SOURCE Great Basin Gold Ltd.